Infor LN & Baan Manufacturing Tip: All About Routings

Kathy Barthelt 0 64779 Article rating: 4.0

The planning data for the method of manufacturing is defined in Routing. A routing consists of operations, with each operation identifying the last to be carried out in a work center and/or on a certain machine defined for a specific site.

Routings can be as follows:

  • Standard Routing - A generic routing that can be attached to multiple items
  • Item specific - A routing that is applied to one item
  • Network routing - A routing containing sequentially ordered operations and parallel operations
  • Order quantity dependent routing - A routing that is defined for a specific quantity of items

You use the Routing module to record routings for manufactured items. You can define the following:

Infor LX & BPCS Manufacturing Tip: Backward Scheduling

George Moroses 0 26808 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LX & BPCS Tip: What is IDF and how could it make my life easier?

George Moroses 0 28359 Article rating: 5.0

The Infor Development Framework (IDF) re-architects the way a user interacts with the application. IDF provides an efficient, task-oriented process to view application information that is contained within Infor LX. IDF enables users to configure their view of the application data without modifying the core application and its supportability.

The examples below describe how users can configure their display of data and maximize overall productivity:

  • Arrange application information into multiple groupings and sequences that make sense for the job.
  • Hide information that does not apply to a particular job or task.
  • Filter records to show only the information that applies to the job or task that the user is performing.
  • Customize the information for an individual user, for a group of users, or for all users.
     

Infor LN & Baan Tip: Deleting Records

Kathy Barthelt 0 66107 Article rating: 5.0

To improve performance and reduce database growth, deleting records is highly effective. The disadvantage of deleting records is that data is no longer available. Usually, however, not all records need to be saved. For example, line activities are stored by warehouse. Normally, you do not need to keep these records. Therefore, after closing a warehouse order, line activities can be removed. The User's Guide for ERP LN Archiving and the corresponding Baan IV/V Guides describe several sessions you can use to delete old data. Other data such as items and business partners can be reviewed once in a while, after which you can delete the data you no longer need. For every order and contract table, a session is available to archive and delete old orders. In these sessions, you can specify several characteristics to select the orders to be removed, such as date or status. Run these sessions on a regular basis.

Are ERP System Blockages Thwarting Your Progress?

Kathy Barthelt 0 26629 Article rating: 5.0

After a week of blocking the Suez Canal, the now-famous cargo ship, Ever Given has been freed from the 27,000 cubic meters of sand and mud that were surrounding the ship. Supply chains are flowing again. I for one am very glad to hear that the ship has been freed since coffee, toilet paper and a whole host of other items were being held up! In all seriousness, it was and is a crisis that will have ripple effects on the global economy.

As I often do, I started to relate this crisis to the world of ERP that we live in. Although we are not responsible for dealing with a situation like what happened in the Suez Canal, we all deal with problems in our jobs every day. Some of these problems are small, and some are not so small. Some problems are caused by human error, some by prevailing winds that blow us in a particular direction, and some by circumstances out of our control. It is what we do about the problems we encounter that make all the difference. We could bury our heads and hope the problems somehow go away on their own, or we can take action and do something to bring about the change necessary to get past the blockage.

I see “blockages” every day in working with my customers. Sometimes it is a lack of understanding of best practices in a given department, or a reliance on tribal knowledge that determines how and why something is done in the system, or inefficient manual processes destroying a company’s efficiency, or hundreds (or thousands) of customizations standing in the way of an upgrade, or employees labeling an ERP system as “no longer a fit” when their company is only using 10% of the available functionality in the system.

So, maybe today we could focus on what it would take to remove the “blockage” that we have in our way. What benefits could we realize if we worked together to bring about incremental change? Could we actually get that upgrade done? Could we start operating based on industry-leading best practices? Could we increase our market share? Could we decrease our costs and boost our revenue? All of this is possible.

Contact me today so that we can begin to work together to solve the problems that stand in the way of your progress.

solutions@crossroadsrmc.com or 800.762.2077

Infor LN & Baan Tip: Broadcast message to users

Kathy Barthelt 0 65740 Article rating: 5.0

Did you know that you can send a broadcast message to users on the system? This is especially useful if you need users to exit their sessions, or in the event of system maintenance.   

  • For Baan IV users, see KB 22869250
  • For LN users, see KB 1830758

Infor LX & BPCS Tip: Product interface list, SYS635D

George Moroses 0 28213 Article rating: 5.0

Did you know?  Product interface list, SYS635D

This program creates a report that contains all interface program call records that were created for the Infor LX programs specified in the range on this screen. The report contains a line for each record found. The line displays the following information:

  • The name of an Infor LX program that contains a user exit to an add-on program
  • The interface point in the Infor LX program, that is, an identifier of the point in the program code where the user exit is requested
  • The execution sequence number of the record, because more than one add-on program can exist that can run from the same interface point
  • The add-on program to call at the interface point. The Add-on Product Interface file, ZXI, stores the records.

Access: Menu SYS

Infor LX & BPCS Finance Tip of the Week: Invoice Level Inquiries – ACR300D7

George Moroses 0 31447 Article rating: 5.0

Use the Invoice Level Inquiries program, ACR300D7, to perform online customer account receivable inquiries and to perform write-off transactions on open invoices. The inquiries display customer master file and credit information, open and closed invoices, debits, credits, payments, and dunning statuses. Additional detail information is available, such as original prefix and document number, customer order number, customer purchase order number, reason codes, and currency.

You can view closed items for a period specified in Transaction History System Parameters, SYS824D-01.

Open items are aged in one of five user-defined aging periods as defined in Accounts Receivable Parameters, ACR820D-01.

First3637383941434445Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: Role-Based Security
Next Article BPCS/LX Tip of the Week: Inventory Transaction Post to G/L by Cost Type
Print
28548 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.