Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

George Moroses 0 34976 Article rating: 5.0

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand.....

Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

Kathy Barthelt 0 64225 Article rating: 5.0

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Infor LX & BPCS Tip: Changing an item to non-inventory

George Moroses 0 25058 Article rating: 5.0

When an attempt is made to change an item’s type to a non-inventory item from any other value, a new validation is performed to determine if the item has any inventory on hand and, if so, prevents changing the item’s type.

This enhancement available in LX 8.4 prevents LX from showing an on-hand inventory balance for a non-inventory item.

The programs or areas impacted include:

  • Facility/Planning Data Maintenance, MRP140D2
  • IDF Enterprise Item

To get this enhancement, request and apply MR 80120.

Top 10 Things (you might not know) About Crossroads RMC

Crossroads RMC 0 16397 Article rating: 5.0


10.  Crossroads RMC has been in business since 1984 & has been an  partner since 1991
 

 9. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽

 8.  Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓

 7.

 6.

 5.

 4.

 3.

 2.

 1.

DATA: See it. Understand it. Discuss it.

Crossroads RMC 0 16699 Article rating: 5.0

We’ve all heard author and management consultant Peter Drucker’s famous quote “If you can’t measure it, you can’t manage it.”  

What’s the right way to manage “It” though? Is it enough to put the data in the hands of the responsible manager and wait for change to occur? Does the manager have a pulse on everything that went into those numbers?

Your numbers tell a story, but there is a lot of...

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 22447 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

First3031323335373839Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

What is preventing you from upgrading your Infor LN or Baan ERP System?
Kathy Barthelt

What is preventing you from upgrading your Infor LN or Baan ERP System?

Your answer to this question is likely customizations… customizations that were once the best thing since sliced bread but now have become the bane of your existence.

There is something you can do about it! 

Crossroads RMC has many options for dealing with customizations: 

  • Customizations can be re-written to call standard Baan or Infor LN functions via APIs, libraries, BODs, and BDEs.
  • Your customizations can be re-programmed using Extensibility for smaller customizations and LN Studio for larger customizations.
  • RMCgen can be used to create your own custom components without modifying standard programs.
  • Analytics Dashboard allows for an endless variation of Infor LN or Baan views to be created all without touching your ERP system.
  • Infor Report Designer and Infor Document Management can be used to create your own custom-designed report output.
  • Crossroads partners with Nazdaq to deliver custom-designed reports through the B2Win Suite which also integrates with Infor Document Management.
  • New functionality in the latest version of the ERP software may allow you to eliminate many of your customizations.

It all starts with an assessment of your custom components. This is something that can be done internally by you, or with the assistance of Crossroads RMC consultants.

Why continue to live with the elephant in the room who insists on blocking the doorway to progress? Start the process today to get rid of the customizations that are preventing you from taking your ERP system to the next level. Contact us today to learn more: 800.762.2077, solutions@crossroadsrmc.com, or request a phone consultation.

Previous Article The Importance of an Integrated System
Next Article How well does your ERP Serve your Finance team?
Print
72078 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories