Infor LX & BPCS Tip: MPS Planned vs. MRP Planned

George Moroses 0 19838 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned?
Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor LX (ERP LX) will calculate the cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

Infor LN & Baan Finance Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 45243 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is...

Crossroads RMC Welcomes Robert Brown!

Crossroads RMC 0 17350 Article rating: 5.0

Crossroads RMC Welcomes Robert Brown, as a Sr. Business Consultant!
Bob brings 30+ years of shop floor and project management skills to Crossroad RMC. He is a self-starter that has progressively mastered the Manufacturing, Supply Chain, and Finance modules within Infor LX. Bob will get started with EDI/ECM set up for new trading partners and within the Supply Chain ranks. Bob is a great addition to the Crossroads RMC team, and we look forward to his leadership expertise on implementations and upgrades in the near future.

You can benefit from a business process review only if...

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 20002 Article rating: 5.0

Did you implement your ERP system 5 years ago… or maybe 20 years ago? At the time, it was like a brand new car… sleek, fast, top-of-the-line, and fuel-efficient. And although it may have needed a few minor “adjustments”, overall you were very pleased. Fast forward to today. Does it still have that new car smell? Does it run as efficiently as it used to? Do you know how to fix a problem when it occurs?

While ERP systems are certainly designed to last, over time, your business changes, your customers’ needs change, employees change and you are left with a system that may run “fine”, but you certainly don’t feel the same way about it as you did when it was brand new.

So the good news is that you CAN restore that “new car smell” with a utilization review, or business process review.

What is a Utilization or Business Process Review and Why Do I Need One?
Simply put, a business process review is an...

Dashboards vs. Reports – What do they offer and which do I need?

Crossroads RMC 0 25512 Article rating: 5.0

Companies are collecting oceans of data, and struggle with transforming it into usable information. Most businesses focus on two methods of sharing data - the report and the dashboard. While these two terms mean many things to many people, it is important to understand what these terms mean and how the report and dashboard have similar features but they are not the same thing.  

What is a Report?

A report is meant to be used to gather detailed intelligence on the operations within an organization, thus a report can be either very broadly covering a wide scope of related information, or narrowly focusing on details of a single item, purpose, or event. All of this information, while presented in a report, is meant to be a snapshot in time.

Quite often, a report is built within the ERP system itself and often is constrained by the graphical and user limitations within the ERP. More often than not, large amounts of data are exported to Excel where added features allow for better manipulation of the data to a format that is digestible by users. Regardless, the data is only valid for that moment and time.

What is a Dashboard?

A dashboard is a graphical interface that provides at-a-glance views revolving around answering a central question. For example, an executive may ask you for up-to-the-minute details on "how the business is doing?". The answer to that question is as complex as the organizational structure of the company, but it is probably very simply measured with approximately 10 metrics. Those 10 metrics can likely be analyzed in chart form, and can and should be combined into one chart when the numbers are relatable or are on a similar scale. All these things should be considered when building a dashboard.

Dashboards, similar to the one in your vehicle, display critical data. Imagine driving down the road and having to push a bunch of buttons to find out how much fuel you have left, or having to pull over and pop the hood to check the oil pressure. It would be dangerous and a waste of your precious time. Your car's control panel or dashboard displays the most crucial information in an easy-to-use, graphical way.

How do Dashboards and Reports differ?

Infor Customer Meeting: LX, XA, and System21 All-Hands Call

Live Webinar for all Users - Wednesday, April 20 2022

Crossroads RMC 0 17661 Article rating: 5.0

Infor Customer Meeting: 
Live Webinar for all Users

Wednesday, April 20
11:30am - 12:00pm EST

Please join Infor leadership, who will discuss the exciting future strategy for our LX, XA, and System21 customers in the Americas. In this session, we will cover our stated direction, product future, and how this will positively impact your business.  Additionally, we will discuss the driving forces behind these changes and how our study group of customers has been reacting.  Whether you are a long-time customer or a relatively new customer of Infor’s, we welcome you to join this brief update of the future of your ERP solution and introduce you to the Infor team that will service and support your organization.

Our GM of the Americas, Bill Vellante, and VP of the Americas, Jay Allison will host this 30-minute session.

RSVP now

Join Event

Infor ERP Tip: Top 5 Ways Modern Analytics Reduces Spreadsheet Risk & Inefficiency

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 26494 Article rating: 5.0

Spreadsheets are often the tool of choice for many organizations to store and arrange information for financial planning, analytics, compliance, and more. Ironically, for many business processes that involve managing data, it creates the exact opposite effect––silos of information and inefficiency. And because it stores organizational data in a readily sharable way, there is a high risk of exposing confidential information.

Read this Infor best practice guide to discover the top five business processes that a modern data and analytics architecture can automate and deliver far more value than spreadsheet-driven techniques.

Infor Best Practice Guide: 5 Ways Modern Analytics Reduces Spreadsheet Risk and Inefficiency

First2425262729313233Last

Tips:  LX | BPCS | M3

Item Facility Master has a new attribute to define the override inspection days lead time CICP.ICINSD.

  • When an item facility has a defined override inspection days lead time, that value will be used instead of the system parameter inspection days lead time.

MRP exception report, MRP200B
Purchase planning report, PUR285B
Purchase order / Requisition maintenance, PUR500D3
Purchase order consolidation / release, PUR640B1
Vendor splits, PUR653B

This enhancement improved the subfile utilized in MRP320D Master Schedule Detail Inquiry -SCR001 by expanding the subfile with data rather than clearing the subfile as user pages. This change provides full support for the WebTop 4.8 Grid decorator.

This enhancement updated the approach used to populate the subfile to allow a deployed Webtop Grid to function correctly. There is no visible or user-impacted change to the way the program functions.

This enhancement provides improved functionality and full support of a Webtop grid applied to the subfile.

Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Considerations for Release to Warehousing for a Cost Item

When there are two Cost Items, one with Release to Warehousing applied and the other with Release to Warehousing not applied, upon approval of the Sales Order, the Cost Item that is released to Warehousing will go straight to Staged status, pending Shipment confirmation, while the Cost Item that is not released to Warehousing will be up for Sales Deliveries.

Apart from this main difference in functionality between having and not having this option to release to Warehousing checked, there are other impacts to consider. Below is some information gathered from various KBs related to the impact of having release to Warehousing applied (or not). KBs used as reference are listed as “– REF: KB XYZ”. Editing the checkbox “Release to Warehousing” itself If there is a Sales Order (in status Free is enough) for a Cost Item, the check box is not editable. As soon as all the Sales Orders for which the Item is involved are Closed (or Canceled or Deleted) the check box becomes editable again. – REF: KB 1439313 & KB 1613780 Simultaneous/separate release to Warehousing with Physical Items In a scenario where a Cost Item (that is released to Warehousing) and a physical Item are released to Warehousing separately, then the shipment confirmation of each of these Items will occur separately. If they are released simultaneously, the shipment of the Cost Item will not be processed unless and until the physical Item is ready to be shipped. – REF: KB 1449001 Note: Ensure a Warehouse is added to Order Lines to ensure Release to Warehousing Activity is applicable. – REF: KB 2229767 Invoicing

To invoice them separately or together, factors to consider are:

  • Composing Criteria, a list of fields that need to match to have a single invoice created – REF: KB 717977
  • Invoicing Methods (tcmcs0555m000) in the General tab, select Combine, for example, Shipments, to combine different Shipments of the same Sales Order into one Invoice. This Invoicing Method is also defined in
  • Invoice-to role of a Business Partner (tccom4112s000) in the Invoicing tab. – REF: KB 812637
  • For a Return Order where a Cost Item and a Physical Item were originally invoiced together, to invoice them together again, consider using Original Document type = Invoice and link the original Invoice to the Return Order. – REF: KB 2072847 

Note: Consider solution in KB 2108605 if Composing Criteria is met, yet still Credit Notes are not combined for a Return Sales Order copied from original Sales Order for one Physical Item and one Cost Item without release to Warehousing. 

ASN ASN cannot be generated for Purchase Order Lines with Cost Item if not released to Warehousing. – REF: KB 1548301 & KB 2111341 Intercompany Trade Intercompany Trade can be applied for a Cost Item that is released to Warehousing, as Intercompany Trade needs a Warehouse and a Department. – REF: KB 2112430 Customs Value Cost Items that are released to Warehousing that are handled via normal Sales Order Lines are considered as delivered goods and will get the customs value assigned like other Items being subject to warehouse handling. Cost Items handled on Shipment Lines as "Additional Cost" are not considered as delivered goods but as pure costs. The customs value of these shipment lines gets defaulted with a zero amount and cannot be modified. The same applies to additional costs on sales order lines. – REF: KB 1600847 Freight  Cost Items cannot be used for Freight handling. – REF: KB 1830170 Additional Cost

  • For automatically generated Additional Costs in Sales Orders, Cost Items that are released to Warehousing are not released to Warehousing. This is because automatic Additional Costs are always generated with 0 quantity, therefore only the amount is filled for these Lines, which leads to the Delivery Type being set to Sales and not Warehouse. As a result, delivery must take place in Sales module. – REF: KB 1995781
  • For Additional Cost Lines added to Shipment for Cost Items, refer to KB 2236856.

Intrastat Record When using Cost Items without release to Warehousing, there is no shipping data within Invoicing. Therefore, the corresponding Intrastat record cannot be found during the printing of the Invoice. To get the Invoice data filled on the Intrastat record, Cost Items with release to warehousing should be used. Otherwise, session Update Intrastat Transactions with Invoicing Data (tccom7271m100) should be ran to update the Invoicing data in Intrastat. – REF: KB 2005482

Previous Article Infor LN & Baan Tip: What conditions must exist before changing an item's inventory unit?
Next Article Infor LN & Baan Tip: Cash Flow Functionality and Setup
Print
37639 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories