Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

George Moroses 0 34134 Article rating: 5.0

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand.....

Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

Kathy Barthelt 0 62060 Article rating: 5.0

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Infor LX & BPCS Tip: Changing an item to non-inventory

George Moroses 0 24310 Article rating: 5.0

When an attempt is made to change an item’s type to a non-inventory item from any other value, a new validation is performed to determine if the item has any inventory on hand and, if so, prevents changing the item’s type.

This enhancement available in LX 8.4 prevents LX from showing an on-hand inventory balance for a non-inventory item.

The programs or areas impacted include:

  • Facility/Planning Data Maintenance, MRP140D2
  • IDF Enterprise Item

To get this enhancement, request and apply MR 80120.

Top 10 Things (you might not know) About Crossroads RMC

Crossroads RMC 0 15336 Article rating: 5.0


10.  Crossroads RMC has been in business since 1984 & has been an  partner since 1991
 

 9. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽

 8.  Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓

 7.

 6.

 5.

 4.

 3.

 2.

 1.

DATA: See it. Understand it. Discuss it.

Crossroads RMC 0 15499 Article rating: 5.0

We’ve all heard author and management consultant Peter Drucker’s famous quote “If you can’t measure it, you can’t manage it.”  

What’s the right way to manage “It” though? Is it enough to put the data in the hands of the responsible manager and wait for change to occur? Does the manager have a pulse on everything that went into those numbers?

Your numbers tell a story, but there is a lot of...

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 21277 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

First2324252628303132Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Blocking or Unblocking Warehouses

You can block a warehouse for inbound procedures, outbound procedures, or both. For example, you can block inbound and outbound procedures for a warehouse if the warehouse must be closed temporarily for inspection.

You can impose these types of blockings:

  • Full block: Full block on warehousing procedures.

  • Interactive block: Override blocking allowed except blocks on confirm shipment or confirm receipt.

If you impose a full block on inbound procedures, the receipt and inbound inspection procedures are not allowed for the warehouse.

If you impose a full block on outbound procedures, the outbound, outbound inspection, and shipment procedures are not allowed for the warehouse.

An interactive block on inbound procedures blocks the confirm receipt step. For the other inbound steps (for goods already received), a warning is displayed and you are prompted to cancel the procedure or to continue.

These are the other inbound steps:

  • Generate and release inbound advice
  • Print and confirm storage lists
  • Put away stock

If you perform the outbound steps of a warehouse transfer and an interactive inbound block is imposed on the receiving warehouse, you are warned that the receiving warehouse is blocked.

An interactive block on outbound procedures blocks the confirm shipment step. For the remaining outbound and shipment steps, a warning is displayed and the user is prompted to cancel the procedure or to continue. Assembly, internal inventory movements and inventory adjustments are also allowed.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Interest Invoices
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Archiving Concept
Print
16393 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories