Infor LX & BPCS Tip: What items should be M-P-S planned vs. M-R-P planned?

George Moroses 0 31089 Article rating: 5.0

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand.....

Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

Kathy Barthelt 0 40774 Article rating: 5.0

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Infor LX & BPCS Tip: Changing an item to non-inventory

George Moroses 0 21422 Article rating: 5.0

When an attempt is made to change an item’s type to a non-inventory item from any other value, a new validation is performed to determine if the item has any inventory on hand and, if so, prevents changing the item’s type.

This enhancement available in LX 8.4 prevents LX from showing an on-hand inventory balance for a non-inventory item.

The programs or areas impacted include:

  • Facility/Planning Data Maintenance, MRP140D2
  • IDF Enterprise Item

To get this enhancement, request and apply MR 80120.

Top 10 Things (you might not know) About Crossroads RMC

Crossroads RMC 0 14740 Article rating: 5.0


10.  Crossroads RMC has been in business since 1984 & has been an  partner since 1991
 

 9. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽

 8.  Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓

 7.

 6.

 5.

 4.

 3.

 2.

 1.

DATA: See it. Understand it. Discuss it.

Crossroads RMC 0 14694 Article rating: 5.0

We’ve all heard author and management consultant Peter Drucker’s famous quote “If you can’t measure it, you can’t manage it.”  

What’s the right way to manage “It” though? Is it enough to put the data in the hands of the responsible manager and wait for change to occur? Does the manager have a pulse on everything that went into those numbers?

Your numbers tell a story, but there is a lot of...

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 19111 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

First1920212224262728Last

Tips:  LX | BPCS | M3

This enhancement provides additional views, additional order and line details, improved navigation, and additional capabilities to the IDF Customer Order Inquiry cards and to customer order-related business objects such as Allocations, Customer Invoices, Inventory Transaction History, Promotions, Drop Shipments.

Enhanced Order views based on user roles such as customer service, warehouse/logistics, salesperson/commission, data analysis/management reporting

  • Improved sort, select and filter capabilities
  • Enhanced navigation, data organization and data display
  • Improved customer service access to all transactions throughout the entire customer order life cycle – from quote to order, related invoices, and any RMAs, return orders, related credit memos
  • Improved grouping of related fields
  • New cards to present additional order and order line details
  • Consolidation of cards and card details when appropriate
  • Enhanced Display and Maintain capabilities for drillback to related customer, ship-to, item, carrier, terms, and other master file details
  • Improved display of dates, times and applicable time zones when Region Code time zone support is implemented
  • Multi language Description, Name and Address fields displayed in user’s language, if defined, else in base language

This enhancement provides search capabilities on segment value description in Segment Value List window (WINGSVD).

Segment Value List (WINGSVD):

  • Converted to a standard subfile
  • New action code 10=Search

This makes it easier to locate segment values when defining segment values in Model Account Builder or Alias definition. In addition, WINGSVD has been redesigned as a subfile to enable WebTop grid capabilities.

Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Cost Component Setup

To break down an item’s standard cost, sales price, or valuation price, use cost components. With cost components, you can compare estimated and actual costs, calculate production variances, and analyze costs in Standard Cost Calculation.

If cost components are set up in a detailed way, detailed records exist in the Item - Calculated Valuation Prices (ticpr2540m000) session and the Item - Standard Valuation Prices (ticpr3540m000) session. Additional financial integration transactions are created because integration transactions are logged by cost component. A detailed cost component setup also causes additional cost details in domains such as Sales and Warehousing. This increases database growth and makes performance worse, especially during production completion and the item receipt process.

Reduce the number of cost components in the effective cost component structure, which is displayed in the Effective Cost Component Structure (ticpr0112m000) session, as much as possible. The minimum number is three aggregated cost components: one for material, one for operation, and one for surcharges. From a performance point of view, the following is advised:

Reduce the number of cost components

  • One operation cost component for all operation rates.
  • One cost component for all subcontracting rates.
  • One cost component for item and warehouse surcharges.
  • One cost component for actual labor rates (in People). Ensure you only use cost components that are required.

Use aggregated cost components
The standard cost is calculated by (detailed) cost component for a multilevel BOM. A similar calculation of valuation prices (actual prices) would result in a price structure with many cost components, especially for manufactured items. In case of a warehouse transfer, issue to WIP, and so on, postings are made for every cost component. However, this detailed cost information does not add functional value in Warehousing. If you aggregate cost components, the number of cost components in financial transactions is reduced. Therefore, aggregate operation cost, material cost, and surcharges to the three cost components that are defined in the Item - Costing (ticpr0107m000) session

If you do not enter a Standard Cost Component Scheme in the Item - Costing (ticpr0107m000) session, production order costs, production order variances, and surcharges are posted by aggregated cost component. This improves performance and decreases database growth.

Previous Article Infor LN & Baan Tip: Project Status Options
Next Article Infor ERP Tip: Top 5 Ways Modern Analytics Reduces Spreadsheet Risk & Inefficiency
Print
41806 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories