Infor LN & Baan OPERATIONS Tip: MPS Planned vs. MRP Planned

Kathy Barthelt 0 31370 Article rating: 5.0

When deciding what items should be MPS (Master Production Schedule) planned and what items should be MRP (Material Requirements Planning) planned, it's crucial to understand the nature of the items and their demand sources. Here's a breakdown:

  • Master Scheduled Items:

    • Master Scheduled Items are typically finished goods or service items.
    • These items receive their requirements from both Independent and Dependent demand sources.
       
  • Independent Demand:...

Infor LN & Baan FINANCE Tip: Is it possible to upload accounts receivable invoices into LN using Excel?

Kathy Barthelt 0 22590 Article rating: 5.0

Yes, this is possible, by following the steps below:

1. Maintain a batch

2. Maintain an invoice headerexport it, add an additional invoice header to the Excel file, and import it

3. Maintain an invoice line for the first invoice, export it, add additional invoice lines to the Excel file and import it
 

Below the above steps are described in detail...

Infor News You Can Use | The business case for moving your ERP to the cloud and choosing MT deployment

Kathy Barthelt 0 11293 Article rating: 5.0

As more companies invest in cloud computing for their business software and migrate their ERP systems to the cloud, many are considering whether single-tenant or multi-tenant cloud deployment is the best choice.

In this executive brief, Infor outlines insights from the analyst community on the growth of cloud technology, key distinctions between single- and multi-tenant deployments, and why the multi-tenant option for ERP may be the best move for your business.

Learn more>

Tick-Tock... It's time to get more out of your ERP

Crossroads RMC 0 9237 Article rating: 5.0

As crazy as it sounds, we’re about to enter the 2nd half of 2024. How are you doing on your 2024 goals? Planning for 2025 projects?

Maybe it's time to get more out of your Infor ERP system.

⇒⇒ TIME TO UPGRADE?

Is an upgrade to the latest version of your ERP the goal for 2024/2025? If so, Crossroads RMC brings 40 years of industry experience to the table to ensure that your upgrade achieves the results you’re looking for and does so on time and within budget.

Crossroads RMC's team of expert consultants will:

  • Review your custom components to see what can be eliminated
  • Provide an analysis of the specific benefits that your company can achieve by upgrading
  • Train your users on the latest functionality
  • Support your users on the old version while the project team focuses on the upgrade project
  • Handle the entire upgrade project from start to finish
  • Supplement your existing project team with 1-2 key resources
  • Develop the integration to that 3rd party system that is a MUST-HAVE when you upgrade


⇒⇒ NOT UPGRADING?

Infor LX/BPCS Tips & Tricks for FINANCE: Prevent Voiding of Selected Invoices

George Moroses 0 15538 Article rating: 5.0

This enhancement prevents users from voiding invoices after they have been selected for payment. If a user selects an invoice for payment and another user voids the invoice during the payment process, it can produce erroneous and duplicate records. The ACP500 programs were modified to check the status of an invoice before it can be voided. If the invoice has been selected for payment, a message is generated, and the invoice cannot be voided.

Infor LX/BPCS Tips & Tricks for TECHNOLOGY: Update User Security in IDF

George Moroses 0 17857 Article rating: 5.0

Automatically synchronize security changes from LX to IDF, replacing CPYSECIDF. This new process synchronizes users in IDF with those in core LX security whenever a user’s security settings are changed. When a user is deleted from an LX environment, they can also be automatically removed from the IDF environment. Changes to a user’s access to programs in LX are mirrored in IDF. Access to Companies, Facilities, and Warehouses are also synchronized. Additionally, when Business Roles or Business Units access is changed, all users assigned to those roles or units are updated in IDF security.

Infor LX/BPCS Tips & Tricks for OPERATIONS: Copy Shop Order

George Moroses 0 18401 Article rating: 5.0

In the Shop Order Selection program, action 3=Copy is available. This action allows copying any shop order except for flow orders or campaign orders. Instead of copying from the parent item's bill of material and routing, the new shop order’s materials and operations will be copied from the selected shop order. Note that if the existing shop order is linked to a customer order or line, this linkage will not be copied to the new shop order.

First1314151618202122Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Infor ERP Tip: Is your Infor ERP system up to date with all of the sales tax changes for 2021?
Next Article Infor LN & Baan Tip: Remove Posted Payment/Direct Debit Batches
Print
65582 Rate this article:
3.8
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories