Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 105030 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 83318 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 111340 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 82598 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

BPCS/LX Tip of the Week: The Item Master Requirements Code

Anthony Etzel 0 77913 Article rating: No rating

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

Grindmaster Cecilware Selects Crossroads RMC For Baan IV / Davisware Integration

Crossroads RMC 0 41398 Article rating: No rating

Grindmaster Cecilware, a leader in the development of products for the food and beverage industry, has selected Crossroads RMC to integrate their Baan IV system to Davisware Global Warranty. Davisware is an electronic customizable online solution that fits almost any warranty process. Grindmaster’s customers will be able to access the Davisware software online and process warranty claims which will then automatically feed back into the Baan IV system for further review and processing. The integration is expected to go live in Q1 of 2015.

First122123124125127129130131Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: All About Invoicing Methods

Invoicing Methods are a set of parameters that define the types of orders and order lines that can be collected on an invoice, the type of invoice to be generated and the costs to be aggregated on Project invoices and Service invoices.

If options to combine tax codes, departments, sales representatives' line of business area, etc... are checked, LN will combine all available transactions ready to be invoiced that have different tax codes departments, sales representatives, etc...into only one invoice.

If options to combine sales orders, sales order types, and shipments are checked then all sales orders that are created for the same business partner where the shipment and/or sales order type is different will be combined into one invoice.

For example:

  1. If sales order SLS001 is created for BP BP1000 with 2 lines where each line has a different shipment number, and the invoice method is combining shipments, both lines will be part of the same invoice. If the option to combine shipments is not checked then LN will create an invoice per shipment.
  2. If sales order SLS001 is created for BP BP1000 with 2 lines and 2 different shipment numbers and sales order SLS002 is created for the same BP with a cost item, LN will create one invoice for both orders if the option to combine sales orders and shipments is checked. If only the option to combine sales orders is checked then 3 different invoices will be created as all 3 lines will have different shipment numbers. If they have different sales order types and this option is not checked on the invoice method session then also 3 invoices will be created but if it is checked along with sales order and shipment number then only one invoice will be created.
  3. If we take scenario 1 again and both lines have different tax codes and the option to combine tax codes is not selected then LN will create a separate invoice for each line based on the tax code.
     

Note: In the case that the Business Partner Tax Country is different, even if we select combine tax codes, the system will create a separate invoice based on the Business Partner Country to full the statutory compliances for that BP country.

Previous Article Infor LN & Baan Tip: Cash Flow Functionality and Setup
Next Article Infor LN & Baan Tip: Why was the session "General Ledger Diagnostics Workbench" built?