BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Anthony Etzel 0 65319 Article rating: No rating

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 760 Article rating: No rating

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 1086 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 1064 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1101 Article rating: No rating

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Why define location fields in the work center file?

Anthony Etzel 0 568 Article rating: No rating

If you setup the “From” and “To” Location fields in the Work Center file, this will then determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions would happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to ERP LX.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1143 Article rating: No rating

What should you do if you have negative inventory reflected in your system?

You should do a cycle count or inventory adjustment, but first, do a review of the inventory or location history to determine when this happened.

If a negative inventory is allowed, it most likely will be corrected upon receipt of the item. For example, assume that there is a PO that has not been received in Baan/LN, but the goods came in and got shipped out on a sales order. The inventory goes negative, but when the PO receipt is entered, the inventory would be corrected. In this case, no adjustment should be made.

A little due diligence will go a long way to ensure that you are only making an adjustment to your system when warranted.

First120121122123125127128129Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip of the Week: The Production Bill of Material – 10.7

The production bill of material is globally specified at the company level. It can be used as a source for the definition of the local material lists, such as:

  • The production model in the repetitive module.
  • The production model in the job shop module.
  • The subcontracting model in the subcontracting module.

The production bill of material can be generated through the engineering bill of material. The new production bill of material differs from the old bill of material:

  • It has a header and a status.
  • It is always revision controlled.
  • The effective dates have been moved from the material lines to the header.
  • The BOM quantity has been moved from item production data to the header.
  • The use up has been moved from alternatives to the material line.
  • The material line excludes logistic data (no warehouse nor routing operation).

The production bill of material is not mandatory.

Production bill of material revisions:
The production bill of material is revision controlled. The objective of the revision is to control the changes to the bill of material over time.

The P-bom includes this revision-related data:

  • Revision number
  • Effective date and Expiry date
  • Status (New, Approved, Expired)
  • Creation date and Created by: user
  • Approval date and Approved by: user
  • Expiry date and Expired by: user
  • Source information
Previous Article Infor LN & Baan Tip of the Week: Job Shop by Site Changes in LN 10.7
Next Article Infor LN & Baan Tip of the Week: Standalone Sessions in LN 10.7
Print
180552 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories