BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 63221 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 66468 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 32197 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 68554 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 133937 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 66203 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

Kathy Barthelt 0 131929 Article rating: 3.0

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

BPCS/LX Tip of the Week: Indirect Time Reporting

Anthony Etzel 0 64826 Article rating: No rating

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

First120121122123125127128129Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Is Your ERP Environment Ready for What's Next?

For many manufacturers, ERP has been the foundation of their business for years. It manages orders, inventory, production, purchasing, and financials. But as technology and business demands continue to evolve, many organizations are beginning to ask a different question:

Is our ERP environment ready for what's next?

For some, that conversation includes cloud migration. For others, it's about integration, visibility, analytics, or supporting future growth.

The good news is that modernization doesn't have to start with a major migration project.

Start with the Business, Not the Technology

One of the biggest misconceptions about modernization is that it begins with selecting a new platform.

In reality, the most successful projects begin by understanding the business challenges you're trying to solve.

Questions worth asking include:

  • Are systems connected and sharing information efficiently?

  • Where are manual processes creating delays?

  • Does reporting provide the visibility needed to make timely decisions?

  • Can the current environment support future growth?

The answers often reveal opportunities that can deliver value immediately, regardless of whether cloud migration is part of the long-term strategy.
 

Modernization Is a Journey

Many manufacturers take a phased approach to modernization.

Some begin by improving integrations between systems.

Others focus on reporting and analytics to improve visibility and decision-making.

Some explore cloud-based services while continuing to leverage their existing ERP investment.

The goal isn't simply to move applications to a new platform. It's to create a more connected, scalable environment that supports the business for years to come.
 

Planning Your Cloud Journey

As cloud adoption continues to grow, many organizations are evaluating what a migration path might look like.

Infor's Leap program was created to help customers take a structured approach to cloud modernization through readiness planning, industry best practices, and a defined migration framework.

Whether a move is months away or several years down the road, understanding the available options can help organizations make informed decisions and reduce risk.
 

Where Crossroads RMC Fits In

Every manufacturer's environment is different.

That's why the first step isn't choosing a cloud platform. It's understanding your business processes, integrations, reporting requirements, and long-term objectives.

At Crossroads RMC, we help manufacturers evaluate their current environment, identify opportunities for improvement, and develop a roadmap that aligns technology investments with business goals.

Sometimes that roadmap includes cloud migration.

Sometimes it starts with integration, analytics, or process improvements.

The important thing is having a plan.
 

Final Thoughts

Modernization looks different for every organization. For some, it's cloud migration. For others, it's improving integrations, analytics, or business processes.

The important thing is having a roadmap that aligns technology investments with business goals.

If you're evaluating what's next for your ERP environment, we'd be happy to share what we're seeing and help you explore your options.

Start the conversation

Previous Article Industry Insights: Simplifying Integration Across LN and LX with Infor ION
Next Article Industry Insights: Why More Manufacturers Are Replacing Paper Work Instructions
Print
1941 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories