BPCS/LX Tip of the Week: Top Down Shop Order Schedule

Anthony Etzel 0 77026 Article rating: No rating

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Baan/LN Tip of the Week: Back Dating Cycling Counting Orders

Kathy Barthelt 0 105109 Article rating: No rating

Cycle Count Orders cannot be directly “back dated” in Baan IV, Baan V or LN, however, there are some work-arounds.

In Baan IV you can do an inventory adjustment and back date. Just set all dates on the adjustment to the date you want and Baan will post the adjustment in that period.

In LN you can do a Cycle Count/ Adjustment and again back date and Baan will post to that period.

 

Unfortunately, there is no work-around for Baan V.

BPCS/LX Tip of the Day: Inventory Management

Anthony Etzel 0 74972 Article rating: No rating

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 

Baan/LN Tip of the Day: Chart of Accounts

Kathy Barthelt 0 108477 Article rating: No rating

Zero sublevel accounts are posting level accounts. All others are parent accounts. Once the balances have been updated in the child ledger accounts, the parents are automatically updated.

Inquiries and reports can be printed or displayed either by child accounts or by parent accounts. On line drill-down is possible from either child or parent.

BPCS/LX Tip of the Day: Cycle Counting Part 2

Anthony Etzel 0 76037 Article rating: No rating

Understanding: The Cycle Count Alternative

The best way to cycle count is to count the same number of items each day and at the same time each day. The goal is to count your “A” items 4 times a year. The “A” items should be those item that are about 80% of the total inventory value and 20% of the total items. Consider creating your own cycle count schedule then instead of using the cycle count transaction, use the inventory adjustment transaction. The item balance is changed at the time the transaction is keyed. The transaction list can be used for the reconciliation process.

Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 104924 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 83003 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 111088 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.
First120121122123125127128129Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES:

Operations: Copying EBOMs - Which copying method should I use?

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Technology: Using audit files in the Exchange module

The audit server logs all database actions that change the contents of a table in so-called audit files. The Exchange module can use these audit files, which are useful in a multisite environment because the databases on all sites must have identical data. These audit files can also be used in data conversions.

Only the updates in a specific period are exchanged, which leads to an improvement in performance. Specify this period in the Export Data (Non-Regular) (daxch0233m000) and Export Data (on a Regular Basis) (daxch0234m000) sessions. Changes such as insert, update, and delete are processed and written into the ASCII files. Actions such as drop, clear, and create tables are ignored.

Audit control data is added to the resulting ASCII file. This data consists of a batchline ID, transaction ID, sequence ID, and an indicator. The control data is added at the beginning of each line and is formatted like other data fields such as the enclosing and separator characters.

An update writes two lines to the ASCII file. One line contains the key fields and old values of the updated fields. The other line contains the new values of the key fields and updated fields, even if a key field does not change.

The batchline ID is used for recognition when processing the ASCII files. The transaction and sequence IDs are used to ensure that the transactions are replayed in the same order as on the exporting site. The indicator defines the type of action that is executed on the table. Use the letter I to insert; use the letter D to delete; use the letter U to update with old values; and use the letter N to update with new values.

Finance: Problem Invoices

You can use a problem code to indicate that a problem exists for a sales invoice. If the invoice-to business partner notifies you about a problem with the invoice and does not pay it, you can link a problem code to the invoice.

In the direct debits procedure, problem invoices are automatically discarded. For each problem code, you can set an option to prevent linked invoices from being selected on reminder letters.

Previous Article Infor LN & Baan Tips & Tricks: Action Required - Infor LN Cloud Edition - Fonts Update!
Next Article Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?
Print
50989 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories