BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 82769 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 110666 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 81971 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

BPCS/LX Tip of the Week: The Item Master Requirements Code

Anthony Etzel 0 77075 Article rating: No rating

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

Grindmaster Cecilware Selects Crossroads RMC For Baan IV / Davisware Integration

Crossroads RMC 0 41100 Article rating: No rating

Grindmaster Cecilware, a leader in the development of products for the food and beverage industry, has selected Crossroads RMC to integrate their Baan IV system to Davisware Global Warranty. Davisware is an electronic customizable online solution that fits almost any warranty process. Grindmaster’s customers will be able to access the Davisware software online and process warranty claims which will then automatically feed back into the Baan IV system for further review and processing. The integration is expected to go live in Q1 of 2015.

Huf North America Goes Lives With Next Phase of RMC3 Data Collection

Crossroads RMC 0 42319 Article rating: No rating

Huf North America, a global leader in the production of mechanical and electronic key systems, lock sets, steering locks, and remote control systems for the automotive industry, has gone live with phase 2 of their Crossroads RMC data collection implementation. This go-live included Report Orders Complete, Labor Reporting, Material Issue, Inventory Transfers, barcode label modifications, as well as custom applications for their Paint / Polishing operations. This go-live was paired with the expansion of Huf’s Plastic Injection Molding and Paint Facility in Greeneville, TN. The next phase of this project will include the extension of the Crossroads RMC solution into Huf’s facility in Mexico.

First120121122123125127128129Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: What is Statistical Inventory Control (SIC) and How Does It Work?

Statistical Inventory Control (SIC) is an inventory-controlled order system designed to maintain stock levels based on predefined thresholds, rather than being demand-driven like EP (Enterprise Planning). Since SIC relies on inventory levels, it may lead to higher stock levels. To minimize financial risks, SIC is best suited for:

  • Low-cost items.
  • Items with predictable demand or short lead times.


Applications of SIC

  • Low-Cost Items: Particularly effective for inexpensive goods.
  • Predictable Demand or Short Lead Time: Suitable when demand patterns are stable or lead times are minimal.
  • Warehouse-Specific Planning: Useful for planning by warehouse rather than across the supply chain.
  • Trading Industries: Commonly employed in sectors like supermarkets.
  • Immediate Demands: Effective for items required immediately by customers.
  • Ease of Use: Simple to implement and manage.


Limitations of SIC

  • Does not account for dependent demand from planned orders (e.g., MPS/MRP/INV).
  • Does not generate distribution orders.
  • Ignores time-phased planned orders.
  • Lacks forecast consumption techniques.
  • Uses both nettable and non-nettable warehouses.

How SIC Works

SIC operates based on the Reorder Point, Stock Levels, and Order Method.

Triggering SIC

When Economic Stocks (calculated as On-Hand Inventory + On-Order – Allocated Stocks) on the Horizon Date fall below the Reorder Point, SIC triggers the creation of:

  • Planned Purchase Advice.
  • Planned Production Advice.


Order Methods in SIC

The quantity for these advices is determined by the Order Method, which can be one of the following:

  • Replenish to Maximum Stock
  • Fixed Order Quantity
  • Economic Order Quantity (EOQ)
  • Lot-for-Lot

Example: SIC in a Supermarket

Scenario: Managing stock for Ice Cream (1 Kg Pack)

  • Current Stock: 10 PCs
  • Reorder Point: 5 PCs
  • Safety Stock: 2 PCs
  • Lead Time: 1 Day
  • Order Method: Replenish to Maximum (Maximum Stock: 20 PCs)
  • Maximum Anticipated Consumption: 3 PCs/Day

Process:

  1. Customer purchases reduce the stock.
  2. When stock reaches 5 PCs, SIC is triggered.
  3. A Purchase Advice is generated for 15 PCs to replenish stock to the maximum level (20 PCs).
  4. During the lead time (1 day), the remaining 3 PCs (excluding Safety Stock) meet customer demands.
  5. In emergencies, Safety Stock can also be utilized.

Statistical Inventory Control offers a practical approach for managing inventory levels, particularly in industries with predictable demand or fast-moving items. However, its limitations make it less ideal for complex or time-phased planning scenarios.

Previous Article Infor LN & Baan Tips & Tricks for FINANCE: Use of Electronic Bank Statements
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Archiving Data from tipcs300 and ticst300 Tables
Print
55236 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories