Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 104381 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 82663 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 110497 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 81886 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

BPCS/LX Tip of the Week: The Item Master Requirements Code

Anthony Etzel 0 76948 Article rating: No rating

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

Grindmaster Cecilware Selects Crossroads RMC For Baan IV / Davisware Integration

Crossroads RMC 0 41074 Article rating: No rating

Grindmaster Cecilware, a leader in the development of products for the food and beverage industry, has selected Crossroads RMC to integrate their Baan IV system to Davisware Global Warranty. Davisware is an electronic customizable online solution that fits almost any warranty process. Grindmaster’s customers will be able to access the Davisware software online and process warranty claims which will then automatically feed back into the Baan IV system for further review and processing. The integration is expected to go live in Q1 of 2015.

First119120121122124126127128Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tips & Tricks for OPERATIONS: Update, Cancel or Remove Outbound Order Lines

When the originating order or order line of an outbound order line is canceled or changed, this affects the outbound order line and may affect the related outbound advice, shipments, or shipment lines.

For most order origins, warehousing order-type parameters determine whether these actions are allowed:

  • Update the outbound order line if the originating order is changed.
  • Cancel the originating order line and the outbound order line.
  • Delete the canceled outbound order line.

If updating is allowed, changes made to the originating order are updated to the outbound order line and the related outbound advice, and, if present, picking lists, are deleted.

If updating is not allowed, a message is displayed, and the input is blocked when you try to change the originating order line.

If canceling is allowed, the outbound order line is deleted or set to Canceled when the originating order line is canceled.

When a canceled outbound order line is deleted, if present, the related outbound advice and picking list are also deleted. Outbound order lines originating from manual order origins cannot be deleted when canceled.

To process an outbound order line that is not deleted but set to Canceled, the outbound order line must be set to Shipped. The status of the outbound order line determines whether all steps of the outbound and shipment procedures must be completed to process the outbound order line.

When a canceled outbound order line is set to Shipped, the shipped quantity is automatically set to 0. You can create a transfer order to return the not-shipped goods to inventory.

If canceling is not allowed, you cannot cancel the originating order line or the outbound order line. A message to that effect is displayed when you try to cancel the originating order line.

To prevent the goods from being shipped when canceling is not allowed, you must complete the outbound and shipment procedures. When confirming the shipment line, you must set the shipped quantities to 0 and create a transfer order to return the not-shipped goods to inventory.

Previous Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Adding a Timestamp to LN Standard Tables
Next Article Infor LN & Baan Tips & Tricks for FINANCE:  Currency Differences Accounts
Print
54259 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories