Crossroads MES Released for Windows 10

Anthony Etzel 0 29988 Article rating: No rating

Crossroads RMC is pleased to announce the availability of Crossroads MES, V11 for Windows 10. Any customers wishing to upgrade from a previous version to V11 can do so by contacting  support@crossroadsrmc.com. As previously announced, Crossroads MES  is also compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 66199 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 64087 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 70666 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 89906 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 62687 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 65421 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 31677 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

First119120121122124126127128Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

What is preventing you from upgrading your Infor LN or Baan ERP System?

What is preventing you from upgrading your Infor LN or Baan ERP System?

Your answer to this question is likely customizations… customizations that were once the best thing since sliced bread but now have become the bane of your existence.

There is something you can do about it! 

Crossroads RMC has many options for dealing with customizations: 

  • Customizations can be re-written to call standard Baan or Infor LN functions via APIs, libraries, BODs, and BDEs.
  • Your customizations can be re-programmed using Extensibility for smaller customizations and LN Studio for larger customizations.
  • RMCgen can be used to create your own custom components without modifying standard programs.
  • Analytics Dashboard allows for an endless variation of Infor LN or Baan views to be created all without touching your ERP system.
  • Infor Report Designer and Infor Document Management can be used to create your own custom-designed report output.
  • Crossroads partners with Nazdaq to deliver custom-designed reports through the B2Win Suite which also integrates with Infor Document Management.
  • New functionality in the latest version of the ERP software may allow you to eliminate many of your customizations.

It all starts with an assessment of your custom components. This is something that can be done internally by you, or with the assistance of Crossroads RMC consultants.

Why continue to live with the elephant in the room who insists on blocking the doorway to progress? Start the process today to get rid of the customizations that are preventing you from taking your ERP system to the next level. Contact us today to learn more: 800.762.2077, solutions@crossroadsrmc.com, or request a phone consultation.

Previous Article The Importance of an Integrated System
Next Article How well does your ERP Serve your Finance team?
Print
77578 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories