BPCS/LX Tip of the Week: Uses for LX Bill of Material

Anthony Etzel 0 89103 Article rating: No rating
In Infor LX, based on how your items are set up and on how you structure the Bill of Material, the following are some usages of a bill of material by functioning area:

  • Engineering & QA – change control, product design and specifications
  • Manufacturing – build instructions , material pick lists
  • Accounting – product costing
  • Materials Inventory – material and inventory planning
  • Sales – customer order processing
  • Production Scheduling – item scheduling (also a component of an MES solution)

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 69859 Article rating: No rating
In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

Why Your Operation Doesn’t Stand a Chance in Hell of Going From Good to Great (and What to do About it)

David Dickson 0 110446 Article rating: 5.0

You dream of building a manufacturing powerhouse.

An operation with loads of throughput, profit, and efficiency in every process to make your products the best quality you can make them.

You want to be as successful as the factories and companies they write about in books like  Good to Great, changing your operation, and even motivating and inspiring your teams to do so too.

But you know you haven’t got a chance in hell of seeing that kind of success unless you can truly change and make significant differences over the long haul.

Of course, the big question is How? 

BPCS/LX Tip of the Week: Indirect Labor Reporting

Anthony Etzel 0 79426 Article rating: No rating
In the Shop Floor Control Module, you have the ability to key in both direct labor and indirect labor. However you want to establish specific types (reasons) for the indirect labor. The SFC600 labor entry program shows a reason code field, but it is designed for reject quantity and machine downtime reasons, not indirect labor reasons.

There is a way around this. With an MES solution you have the ability to setup and report indirect time against a specific reason code.

Baan/LN Tip of the Week: Configuring Items in Infor LN

Kathy Barthelt 0 86373 Article rating: No rating

In Infor LN, the configuration of a generic item not always results into a customized item. Configured items can now be customized items as well as standard items. If users configure items without PCS projects, standard items are generated instead of customized items.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 75859 Article rating: No rating
In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: Shop Order Status

Anthony Etzel 0 82192 Article rating: No rating

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 83916 Article rating: 4.0
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.
First118119120121123125126127Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Job Management

You can use job management to schedule jobs based on your organizational requirements. For example, you can schedule jobs at non-peak hours to improve the overall system performance in a heavily loaded environment. A job consists of one or more sessions or shell commands, or both, that run without user interaction. The sessions and shell commands in a job can be started while you are not logged on to the ERP system. You can schedule jobs to start processes periodically, at a defined interval, or immediately. Typically, you use job management for print and processing sessions.

Job data  - To create a job, you must specify basic job data and link sessions or shell commands, or both, to the job. In the basic job data, you specify whether the job is periodical. For periodical jobs, you specify how the job will be scheduled.

Shared job data tables  - Typically, each company stores its own basic job data. As a result, a job runs for a particular company. However, in a job, you can also run sessions in more than one company. You can run sessions in multiple companies when the job data tables of the associated companies are physically mapped to a single main company.

Job execution - Jobs can be started in multiple ways. The job’s status defines how you can start the job. You can start the job if the job’s status is In Queue or Free.

Job history -  When the execution of a job stops, for example, when the job completes successfully or when a runtime error occurs, information is written to a history log. The job history contains information, such as the date and time of the execution and the reasons why the job and its associated session ended.

Previous Article Infor LN & Baan Materials Tip: Sales Quotations
Next Article Infor LN & Baan Tip: Pro Forma Invoice
Print
102143 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author