Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 178 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: Indirect Time

Anthony Etzel 0 1002 Article rating: No rating

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.
 

  1. If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  2. If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

 

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

10 Ways to Not Screw Up the OEE Project – It is More Important than You Think

Rich Grilli 0 37797 Article rating: 5.0


Is there a mandate in your company to increase OEE and it has landed on your plate? Ah yes, the OEE approach. You remember what that is right? The Overall Equipment Effectiveness  metric as developed in Japan during restoration made famous in crafting some serious efficiency. Well, someone in management has decided that this is the way to make his world better and now it’s up to you to make it happen.

But there are pitfalls along the way:

BPCS/LX Tip of the Week: Is Lot Control Necessary?

Anthony Etzel 0 72555 Article rating: No rating

Certain industries require lot control, where others may find it an option based on how they want to trace the material used in a product in the event of a defect, or recall.

LX provides tight lot controls and flexibility with lot number assignments. Shop orders can have a pre-assigned lot number, or a lot number can be automatically assigned when the item is produced. You can also assign a specific lot number for the entire shop order, or for each item/quantity reported against a shop order.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 79264 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In ERP LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC to Exhibit at COMMON Conference, April 26-29

Crossroads RMC 0 31482 Article rating: No rating

The Annual Meeting is COMMON’s largest educational event of the year, with four full days of in-depth IBM i, AIX, and Linux-related education that includes all-day pre-conference workshops, open labs and a wide variety of regular-length sessions. It is the annual meeting of the COMMON membership and the largest gathering of the Power Systems user community. Come see us in Booth 316.

BPCS/LX Tip of the Week: Batch Allocation

Anthony Etzel 0 67414 Article rating: 5.0

Thinking of moving from your old BPCS Version to LX?

There are numerous reasons to consider moving to Infor LX. It is a proven migration and it is easy to get there.

An area of interest may be allocations. Allocations can be difficult to manage, but with Infor LX, there is a new selection of ranges for Batch Allocations:

    • Sold To Customer
    • Ship To Number
    • Order Class
    • Order Number
    • Item Number
    • Request Date
    • Schedule Date
First118119120121123125126127Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: Important Porting Set Announcement (all versions of LN & Baan)

There has been a recent porting set change due to Infor’s Product Life Cycle Policy.  

How to determine the maintenance stage of an Infor LN product version and release

Before a customer starts deploying Porting Set 9.4a or a later release, they must determine the actual maintenance stage of their Baan / Infor LN product. The definition of the maintenance stages for the product versions and releases of all versions of Baan and Infor LN are outlined in the Product Support schedule as published in the PLC policy. The maintenance stage of the ERP version is either “Mainstream Maintenance”, “Extended Maintenance” or “Sustaining Maintenance”.

How to manage Porting Set updates

The following conditions apply to customers who intend to upgrade to Porting Set 9.4a or later Porting Set releases:

  • For customers with a product version in Mainstream Maintenance, there will be no difference with regards to Porting Set updates. They can install Porting Set 9.4a or any newer release.
  • Customers with a product version in Extended Maintenance will be able to use Porting Set 9.4a only under the condition that they acquire an Extended Maintenance license and have applied the corresponding validated license key to their SLM License server. This key is a Server license type.
  • Customers with a product version in Extended Maintenance who have not acquired an Extended Maintenance license will not be able to use Porting Set 9.4a or any newer version. The latest Porting Set for these customers that can be installed and used is 9.3j which was released in April 2021.
  • Customers with a product version in Sustaining Maintenance will not be able to use Porting Set 9.4a or any newer version. The latest Porting Set for these customers is 9.3j which was released in April 2021. Customers who are not entitled to upgrade to Porting Set 9.4a can use any Porting Set release prior to Porting Set 9.4a. These continue to be available through the Infor Support Portal.

You can find more information in KB 1946498 General: Infor LN and Baan Product Lifecycle Policy and KB 2204515, or you may contact Crossroads RMC for assistance in determining whether or not you are able to upgrade your porting set.

800.762.2077

Previous Article Don't laugh - the average lifespan of an ERP system is 7-10 years
Next Article Infor LN & Baan Tip: Save Space in General Ledger
Print
70915 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories