Baan/LN Tip of the Week: Switching to a Difference Series

Kathy Barthelt 0 76765 Article rating: No rating

In general, you can enter a different series in the order field if you have an available series. To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1). Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

Hoffmaster Clintonville Plant Goes Live with Crossroads MES & LX

Anthony Etzel 0 35216 Article rating: No rating

On March 1, 2016, Hoffmaster’s Clintonville plant went live with Crossroads MES and LX. The goal of the project was to convert from another ERP to LX and replace a green screen MES system that required the manual recording of production and labor activity keyed from shop floor terminals.

Hoffmaster achieved their goal by completing a successful data conversion and detailed prototyping of LX and Crossroads. The project team remarked that the Crossroads MES implementation was by far the easiest part of the project. One of the critical requirements of the chosen MES solution was to verify UPC and UCC label formats that called for in-line labeling of product packages and cases. Crossroads MES satisfied that requirement, and also provided an interface to finished goods inventory via the scanning of LPN numbers when reporting production.

The Clintonville plant is a leading manufacturer of disposable tabletop products.

BPCS/LX Tip of the Week: Actual Costs for Manufactured Items

Anthony Etzel 0 56811 Article rating: 5.0

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.

Baan/LN Tip of the Week:GRINYA Reconciliation – What Could Go Wrong?

Kathy Barthelt 0 83603 Article rating: No rating

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan or LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error.

To ensure, it’s recommended that the Integrations Setup tables should be audited either through Baan/LN or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Morrison Brothers Goes Live With Crossroads MES in Record Time!

Crossroads RMC 0 34845 Article rating: No rating

On February 18, 2016, the Maquoketa plant of Morrison Brothers went live with the Crossroads MES solution. The goal was to remove all the shop floor paperwork and eliminate the manual recording of production and labor. The company achieved this goal in just 96 days from project kick-off to go live. Included in the go-live was the ability to deliver drawings electronically to the Crossroads MES workstations. This was a critical component of the implementation as it ensured that each workstation would always be operating off the latest revision of the engineering documents.

A rollout of the Crossroads MES solution is planned for Morrison’s Dubuque plants later this year. 

Morrison Brothers is a major producer of petroleum marketing equipment in the United States and abroad.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 79215 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 55504 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 89605 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

First114115116117119121122123Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Industry Insights: Simplifying Integration Across LN and LX with Infor ION

Why this matters

Many integration challenges come from systems that don’t communicate effectively. Data is often duplicated, delayed, or manually transferred between applications, creating inefficiencies and limiting visibility.

What this solves

Infor ION provides a structured way to connect applications and enable consistent data flow across your environment, helping reduce manual processes and improve how information is shared.


How it works

Infor ION acts as a central integration layer, allowing systems to communicate using standardized messages.

In Infor LN, ION is natively integrated, enabling streamlined data exchange across applications.
In Infor LX environments, ION can be used as part of an integration strategy to connect ERP with external systems and platforms.

This enables:

  • Integration between Infor applications, third-party platforms, and in-house systems

  • Consistent, real-time data exchange

  • Reduced reliance on point-to-point integrations

ION also supports:

  • Workflow automation

  • Event monitoring

  • Task and alert management


Key benefit

Instead of building multiple direct connections between systems, ION creates a more scalable and manageable integration framework.


Practical insight

Integration is not just about connecting systems, it’s about how data flows between them. A structured integration layer like ION helps ensure information is accurate, timely, and usable across the business.

If you’re looking to connect systems more effectively or support growth without added complexity, we’d be happy to share what’s working. Talk with our team 1.888-767-4860

Previous Article Infor ERP Tips & Tricks: Gain Insight into Inventory Variances with Cycle Counting Analytics
Next Article Is Your ERP Environment Ready for What's Next?
Print
1646 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories