Anthony Etzel 0 1002 Article rating: No rating

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.
 

  1. If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  2. If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

 

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

 

10 Ways to Not Screw Up the OEE Project – It is More Important than You Think

Rich Grilli 0 37265 Article rating: 5.0


Is there a mandate in your company to increase OEE and it has landed on your plate? Ah yes, the OEE approach. You remember what that is right? The Overall Equipment Effectiveness  metric as developed in Japan during restoration made famous in crafting some serious efficiency. Well, someone in management has decided that this is the way to make his world better and now it’s up to you to make it happen.

But there are pitfalls along the way:

BPCS/LX Tip of the Week: Is Lot Control Necessary?

Anthony Etzel 0 71812 Article rating: No rating

Certain industries require lot control, where others may find it an option based on how they want to trace the material used in a product in the event of a defect, or recall.

LX provides tight lot controls and flexibility with lot number assignments. Shop orders can have a pre-assigned lot number, or a lot number can be automatically assigned when the item is produced. You can also assign a specific lot number for the entire shop order, or for each item/quantity reported against a shop order.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 78739 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In ERP LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC to Exhibit at COMMON Conference, April 26-29

Crossroads RMC 0 31132 Article rating: No rating

The Annual Meeting is COMMON’s largest educational event of the year, with four full days of in-depth IBM i, AIX, and Linux-related education that includes all-day pre-conference workshops, open labs and a wide variety of regular-length sessions. It is the annual meeting of the COMMON membership and the largest gathering of the Power Systems user community. Come see us in Booth 316.

BPCS/LX Tip of the Week: Batch Allocation

Anthony Etzel 0 66712 Article rating: 5.0

Thinking of moving from your old BPCS Version to LX?

There are numerous reasons to consider moving to Infor LX. It is a proven migration and it is easy to get there.

An area of interest may be allocations. Allocations can be difficult to manage, but with Infor LX, there is a new selection of ranges for Batch Allocations:

    • Sold To Customer
    • Ship To Number
    • Order Class
    • Order Number
    • Item Number
    • Request Date
    • Schedule Date

Baan/LN Tip of the Week: Safety Time

Kathy Barthelt 0 99695 Article rating: No rating

You can add safety time in the item master for the item. This will add the number of days safety time to the order lead time thus bringing the order in x number of days early. (x is the safety time).

The safety time is on form 4 of the item master in Baan IV and in Item Ordering Data – Generation I tab in Baan V and LN.

First114115116117119121122123Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for Technology: Using audit files in the Exchange module

The audit server logs all database actions that change the contents of a table in so-called audit files. The Exchange module can use these audit files, which are useful in a multisite environment because the databases on all sites must have identical data. These audit files can also be used in data conversions.

Only the updates in a specific period are exchanged, which leads to an improvement in performance. Specify this period in the Export Data (Non-Regular) (daxch0233m000) and Export Data (on a Regular Basis) (daxch0234m000) sessions. Changes such as insert, update, and delete are processed and written into the ASCII files. Actions such as drop, clear, and create tables are ignored.

Audit control data is added to the resulting ASCII file. This data consists of a batchline ID, transaction ID, sequence ID, and an indicator. The control data is added at the beginning of each line and is formatted like other data fields such as the enclosing and separator characters.

An update writes two lines to the ASCII file. One line contains the key fields and old values of the updated fields. The other line contains the new values of the key fields and updated fields, even if a key field does not change.

The batchline ID is used for recognition when processing the ASCII files. The transaction and sequence IDs are used to ensure that the transactions are replayed in the same order as on the exporting site. The indicator defines the type of action that is executed on the table. Use the letter I to insert; use the letter D to delete; use the letter U to update with old values; and use the letter N to update with new values.

Previous Article Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?
Next Article Infor LN & Baan Tips & Tricks for Finance: Problem Invoices
Print
46252 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories