BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 343 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Database Sizing – Moving to LN

Kathy Barthelt 0 219 Article rating: No rating
The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

How Do You Measure Success in Your Business?

Anthony Etzel 0 52965 Article rating: 5.0

Business owners may measure success in different ways – some tangible, some intangible.

In order to establish how you should measure success for your business, you need to first examine how you measure your personal success. If you are a business owner, or a part of the management team of the company you work for, ask yourself these questions to see how you measure up:

Assess personal success.

1.    Am I happy in my job?

2.    Do I have passion for what I’m doing?

3.    Do I get the desired results based on the effort I’m putting in?

4.    Am I putting forth my best effort?

5.    Am I patient and allow for sufficient time to see results?

6.    Do I get respect from my co-workers?

7.    Do I have the endurance to hang in there when things get a bit rough?


Reflect on successes and failures.

After answering these questions, do you need to make any changes? Do you still have the same ambition and drive to achieve the goal? Are you content with your work, or have you come to the conclusion that you have not done your best?

To be successful...

Baan/LN Tip of the Week: Switching to a Difference Series

Kathy Barthelt 0 204 Article rating: No rating

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1). Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Day: MRP/MPS Simulation

Anthony Etzel 0 786 Article rating: No rating
The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

BPCS/LX Tip of the Day: Inventory Stocking Levels – LX

Anthony Etzel 0 735 Article rating: No rating

The system supports four levels of inventory. You can view summaries of stock at each level through the Material Status Inquiry program or through reports.

 

Below are the four levels:

â–ª  Item

â–ª  Item + warehouse

â–ª  Item + warehouse + location

â–ª  Item + warehouse + location + lot

 

The lot number level and/or container of inventory can cross multiple warehouses and locations. For example, item + lot or item + lot + container. Locations exist within warehouses. There is no limit on the number of warehouses, locations, or lots that you can assign to an item.

Baan/LN Tip of the Day: Transfers - LN

Kathy Barthelt 0 2779 Article rating: No rating
A Transfer involves either one or two warehouses. If items are transferred between two different warehouses, all activities of the warehousing procedures must be carried out. However, if a transfer takes place between two locations within the same warehouse, the receipt activities are not carried out. You can use transfer orders to define a replenishment system within a single warehouse. This system controls replenishment from bulk locations to pick locations. Note: LN allows you to modify the outbound order line data based on the value the Allow Updating Outbound Order Lines up to and including field is set to in the Warehousing Order Types (whinh0110m000) session.

BPCS/LX Tip of the Day: LX Inventory Pallet Status Flow

Anthony Etzel 0 50177 Article rating: No rating

Four fields in the Item/Warehouse record (IIW file) affect the disposition of the

pallet status.

 

1.  Goods Receiving Code: You define these codes in Goods Receiving Maintenance (WHM130). The codes control whether or not the stock passes through inspection, what percentage, or quantity of a delivery to inspect, and the number of quarantine days, if any.

 

2.  Inspection Zone/Inspection Location: Either the Inspection Zone or the Inspection Location must be entered on the Item/Warehouse Master Maintenance screen WHM150D2-01.

 

First112113114115117119120121Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for TECHNOLOGY: Impact of Configuration Changes on Audit Trails

Impact of Configuration Changes on Audit Trails

The impact of changes in the audit settings varies depending on the specific circumstances. The issues typically arise when changes made to audit settings are implemented at runtime without requiring all users to exit the system (LN). As a result, some users may continue to generate audit trails using the old configuration, while those who log in after the changes take effect will create audit trails based on the new configuration.

Changes in User Profiles

Below is a summary table that illustrates the effects of these changes for a specific table within a company:

Change Description Impact
Add a table Users that still use the old settings do not audit some transactions.
Remove a table Some transactions that must not be audited with the new settings are still audited by users that use the old settings.
Change the audit type for a table or field Some transactions are audited according to the old settings, and other transactions are audited according to the new settings.
Add or remove a field After you audit transactions in the table with the new settings, users that use the old settings can no longer perform transactions on this table. Therefore, users with the old settings can be forced to restart LN.

Note on Changes in Field-Specific Auditing:
When you toggle field-specific auditing on or off for a table, which alters the number of fields being audited, the effect is analogous to adding or removing a field. However, not every modification to the audit settings impacts the runtime settings. Converting the new settings to runtime might result in no net change for the entire configuration if the overall effect of the adjustments neutralizes each other.

Previous Article Infor LN & Baan Tips & Tricks for OPERATIONS: Using Country of Origin for Purchase Orders
Next Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Print
28414 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories