BPCS/LX Tip of the Week: Actual Costs for Manufactured Items

Anthony Etzel 0 53796 Article rating: 5.0

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.

Baan/LN Tip of the Week:GRINYA Reconciliation – What Could Go Wrong?

Kathy Barthelt 0 78710 Article rating: No rating

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan or LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error.

To ensure, it’s recommended that the Integrations Setup tables should be audited either through Baan/LN or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Morrison Brothers Goes Live With Crossroads MES in Record Time!

Crossroads RMC 0 32691 Article rating: No rating

On February 18, 2016, the Maquoketa plant of Morrison Brothers went live with the Crossroads MES solution. The goal was to remove all the shop floor paperwork and eliminate the manual recording of production and labor. The company achieved this goal in just 96 days from project kick-off to go live. Included in the go-live was the ability to deliver drawings electronically to the Crossroads MES workstations. This was a critical component of the implementation as it ensured that each workstation would always be operating off the latest revision of the engineering documents.

A rollout of the Crossroads MES solution is planned for Morrison’s Dubuque plants later this year. 

Morrison Brothers is a major producer of petroleum marketing equipment in the United States and abroad.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 74318 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 52176 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 85990 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i

Kathy Barthelt 0 33427 Article rating: No rating

Crossroads RMC is proud to announce the official release of NextTrack Sales – a sales analysis tool for Baan, LN, and IBM i. NextTrack Sales allows you to get the “big picture”, or get down into the finer details. The tool provides a sophisticated pivot grid and charting functionality, export to Excel, PDF printing, and emailing capabilities to bring your sales data to life. Analyze your Baan Sales data to examine trends, identify market opportunities, and much more. Click here for more details.

First110111112113115117118119Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Cost Component Setup

To break down an item’s standard cost, sales price, or valuation price, use cost components. With cost components, you can compare estimated and actual costs, calculate production variances, and analyze costs in Standard Cost Calculation.

If cost components are set up in a detailed way, detailed records exist in the Item - Calculated Valuation Prices (ticpr2540m000) session and the Item - Standard Valuation Prices (ticpr3540m000) session. Additional financial integration transactions are created because integration transactions are logged by cost component. A detailed cost component setup also causes additional cost details in domains such as Sales and Warehousing. This increases database growth and makes performance worse, especially during production completion and the item receipt process.

Reduce the number of cost components in the effective cost component structure, which is displayed in the Effective Cost Component Structure (ticpr0112m000) session, as much as possible. The minimum number is three aggregated cost components: one for material, one for operation, and one for surcharges. From a performance point of view, the following is advised:

Reduce the number of cost components

  • One operation cost component for all operation rates.
  • One cost component for all subcontracting rates.
  • One cost component for item and warehouse surcharges.
  • One cost component for actual labor rates (in People). Ensure you only use cost components that are required.

Use aggregated cost components
The standard cost is calculated by (detailed) cost component for a multilevel BOM. A similar calculation of valuation prices (actual prices) would result in a price structure with many cost components, especially for manufactured items. In case of a warehouse transfer, issue to WIP, and so on, postings are made for every cost component. However, this detailed cost information does not add functional value in Warehousing. If you aggregate cost components, the number of cost components in financial transactions is reduced. Therefore, aggregate operation cost, material cost, and surcharges to the three cost components that are defined in the Item - Costing (ticpr0107m000) session

If you do not enter a Standard Cost Component Scheme in the Item - Costing (ticpr0107m000) session, production order costs, production order variances, and surcharges are posted by aggregated cost component. This improves performance and decreases database growth.

Previous Article Infor LN & Baan Tip: Project Status Options
Next Article Infor ERP Tip: Top 5 Ways Modern Analytics Reduces Spreadsheet Risk & Inefficiency
Print
60451 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories