Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1101 Article rating: No rating

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Why define location fields in the work center file?

Anthony Etzel 0 568 Article rating: No rating

If you setup the “From” and “To” Location fields in the Work Center file, this will then determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions would happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to ERP LX.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1143 Article rating: No rating

What should you do if you have negative inventory reflected in your system?

You should do a cycle count or inventory adjustment, but first, do a review of the inventory or location history to determine when this happened.

If a negative inventory is allowed, it most likely will be corrected upon receipt of the item. For example, assume that there is a PO that has not been received in Baan/LN, but the goods came in and got shipped out on a sales order. The inventory goes negative, but when the PO receipt is entered, the inventory would be corrected. In this case, no adjustment should be made.

A little due diligence will go a long way to ensure that you are only making an adjustment to your system when warranted.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 261 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer


With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 133 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Day: Inventory Transactions

Anthony Etzel 0 586 Article rating: No rating

Define Inventory transactions for issuing components to the shop and receiving finished items. See the Inventory help text for examples of transactions.

  • Transaction type I - Single Issue to Shop Order. Use this transaction type to issue one component at a time. Use this for high-value items that are marked as Must Single Issue on the Item Master file.
  • Transaction type M - Multiple Issue to Shop Order. Use this transaction type to issue all the components as listed in the Shop Order, in one transaction. Note that this transaction type does not issue Must Single Issue items.
  • Transaction type S - Receipt from shop. Use this transaction type to receive the finished item into stock and update the shop order accordingly. 

The Shop Order Lot/Location Allocation program is an alternative to using the above Inventory transactions. Use this when the item is finished, and you want to review exactly what was used to make it. You can review the components as allocated, make any changes, and finally accept the finished order.

Baan/LN Tip of the Day: Multi-Company Warehousing 10.4

Kathy Barthelt 0 435 Article rating: No rating

You can define internal trade relationships between enterprise units or individual warehouses of the same logistic company for the transfer of material, labor, or other costs between warehouses, and to generate invoices for these without using sales orders and purchase orders. For example, you can use this to transfer goods between warehouses in different countries.


You can define warehouse surcharges, which are added to the actual costs of the goods either when the goods are issued from a warehouse or when the goods are received.

BPCS/LX Tip of the Day: MRP/MPS Simulation in LX

Anthony Etzel 0 785 Article rating: No rating

The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut, or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center

loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

First109110111112114116117118Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Avoid Being a Quitter: How Crossroads RMC Can Help You Achieve Your Goals

Unlocking Success Infor LX/BPCS & Infor LN and Baan

Avoid Being a Quitter

As the calendar flips to January 1st, it marks the beginning of a new year filled with fresh opportunities and resolutions. It's that time when many of us set ambitious goals for ourselves, both personally and professionally. But, how often do these aspirations fizzle out before we even hit the second Friday of the year? It's so common that they even call it "Quitter's Day." However, it's not too late to stay on track and realize your ambitions. In this article, we'll focus on the professional side of goal-setting and how Crossroads RMC can be your ally in achieving manufacturing excellence.

Step 1: Make Your Goals Bite-Sized

While you might have grand ambitions, like upgrading your ERP system, increasing customer satisfaction, or optimizing your supply chain, achieving these goals often involves breaking them down into smaller, manageable projects. Here's how you can start:

  • Why: Understand why you want to make these changes. Is it to retain your top customers, leverage new ERP features, or streamline your supply chain?
  • What: Clearly define the desired outcomes – be it increased sales, enhanced efficiency, or cost reduction.
  • Who: Identify the key players who can help you achieve these goals. Do you have the necessary resources in-house, or should you consider external expertise?
  • When: Establish a timeline, considering your overall company initiatives, project priorities, and deadlines. Make your goals specific, measurable, attainable, and time-based (SMART).

For example:

  • Increase customer satisfaction for our top 5 customers by 10% in the next 6 months.
  • Reduce production mistakes in our welding department by 50% within a year.


Step 2: Identify Roadblocks

What's preventing you from reaching your goals? Is it a lack of resources, support, or the right tools? Consider these factors:

  • Lack of bandwidth: Assess your team's capacity. Can you involve colleagues from other departments or partners?
  • Support: Get buy-in from business leaders by demonstrating the ROI and benefits of your project. Educate your coworkers on its importance.
  • Tools: Explore features in your ERP system that you might not be utilizing fully. Is an upgrade or additional software add-ons needed?

 
Step 3: Take Action and Persist

Creating a plan is vital, but remember, the path to success isn't always smooth. Prepare for challenges and adapt as needed:

  • Develop a comprehensive plan to execute your goals.
  • Communication is key. Keep your team informed about progress and challenges.
  • Adjust your plan when necessary. Mistakes are part of the journey and can lead to future success.


How Crossroads RMC Can Help You in 2024

At Crossroads RMC, we understand the challenges manufacturers face, and we're here to support your journey to success. Here's how we can assist:

  • Implement new functionality in your existing ERP system.
  • Lead the way in upgrading your ERP to the latest version.
  • Provide training based on best practices for your employees.
  • Automate time-consuming, manual processes.
  • Integrate your systems, creating a seamless, cohesive environment.
  • Deliver ERP add-on solutions that save you time and money.

We offer a comprehensive range of consulting services and software designed to optimize manufacturing by reducing costs, improving quality, and enhancing efficiency.

Learn More:

Infor LX & BPCS Services> Infor LX & BPCS Software>

Infor LN & Baan Services> Infor LN & Baan Software>
 

It's Time for Action!

Contact us today at solutions@crossroadsrmc.com or call us at 800.762.2077 to discuss your ERP goals. Let Crossroads RMC be your partner in making 2024 a resounding success for your manufacturing business!

Print
14131 Rate this article:
.2
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories