BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 39763 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 55104 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 25911 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 46971 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 50274 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 43945 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

Baan/LN Tip of the Week: SIC Planning for MRP/MPS Planned Items

Kathy Barthelt 0 63110 Article rating: 3.0

If you have a parts warehouse and prefer to use SIC for planning (re-order point) but need to use MRP/MPS planning for production, create a non-nettable warehouse for the parts warehouse and run the SIC plan against that warehouse.

When running the SIC plan, be sure to set the Order System to “MPS to MRP” for Baan IV and to “Planned to Planned” for Baan V and LN.

Using this method you keep the parts inventory out of the production planning and in the hands of the parts warehouse planner.

BPCS/LX Tip of the Week: Indirect Time Reporting

Anthony Etzel 0 45836 Article rating: No rating

In Infor LX, there are two ways to enter indirect labor. You can use either SFC600 or SFC650.

  • If you use SFC600 and enter a reason code for the indirect labor, the reason you entered is written to the Labor Ticket file.
  • If you use SFC650 and enter a reason code for the indirect, the reason code is not written to the labor Ticket file.

In either case, the reason code is not validated from the transaction file because there is no indirect transaction code. The indirect code that can be setup is machine downtime. If you need to validate and track indirect by reason and validate the reason code, then you may want to explore an MES solution that works with Infor LX.

First105106107108110112113114Last

Tips:  LX | BPCS | M3

This enhancement provides additional views, additional order and line details, improved navigation, and additional capabilities to the IDF Customer Order Inquiry cards and to customer order-related business objects such as Allocations, Customer Invoices, Inventory Transaction History, Promotions, Drop Shipments.

Enhanced Order views based on user roles such as customer service, warehouse/logistics, salesperson/commission, data analysis/management reporting

  • Improved sort, select and filter capabilities
  • Enhanced navigation, data organization and data display
  • Improved customer service access to all transactions throughout the entire customer order life cycle – from quote to order, related invoices, and any RMAs, return orders, related credit memos
  • Improved grouping of related fields
  • New cards to present additional order and order line details
  • Consolidation of cards and card details when appropriate
  • Enhanced Display and Maintain capabilities for drillback to related customer, ship-to, item, carrier, terms, and other master file details
  • Improved display of dates, times and applicable time zones when Region Code time zone support is implemented
  • Multi language Description, Name and Address fields displayed in user’s language, if defined, else in base language
Last

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Defining “Unavailability” in Infor LN

This topic describes the definition of temporary unavailability for resources in a calendar.

Use one of the following sessions:

  • Recurring unavailability
    For recurring unavailability, such as national holidays, define the recurrence in the Recurrences (tcccp0143m000) session. Add that recurrence to the applicable calendar and availability type in the Calendar Recurrences (tcccp0144m000) session, and clear the Available check box for the unavailable days.
    With calendar recurrences you define recurring exceptions in a calendar, and set a time schedule for daily, weekly, monthly, or yearly unavailable time in one action.
  • Unavailable days for all availability types
    To define occasional unavailability, such as a department trip, use the Calendar Non-Available Days (tcccp0119m000) session. What you define here applies to all availability types.
     
  • Unavailable days for a specific availability type
    To define unavailability for a single day, complete the following steps:
  1. Start the Calendar Working Hours (tcccp0120m000) session.
  2. Find the applicable calendar and availability type, and clear the Available check box for a working hours type on the relevant date.
  • Unavailable during a part of a day
    To indicate that part of a day is unavailable, use the Calendar Recurrences (tcccp0144m000) or the Calendar Working Hours (tcccp0120m000) session to specify the time intervals that are available. All other times are considered unavailable. You cannot directly specify an unavailable time interval.

If you defined unavailable dates in the Calendar Non-Available Days (tcccp0119m000) or the Calendar Recurrences (tcccp0144m000) session, in the Calendar Working Hours (tcccp0120m000) session, click Update Calendar.

Note:

  • Unavailability always applies to entire days. If the Calendar Working Hours (tcccp0120m000) session contains multiple time intervals for a single date, and the Available check box is cleared for some intervals and selected for other intervals on the same day, the entire day is unavailable.
  • A calendar recurrence that makes a day unavailable has no effect on the availability of that day in the parent calendar.


It is not useful to define a special availability type for unavailability, because Infor LN does not maintain and update the working hours and the capacity data of a calendar in the Calendar Working Hours (tcccp0120m000) session based on non-available availability types.

Previous Article Infor LN & Baan Tip: Porting Set Issues
Next Article Infor ERP Tip of the Week: 5 Steps to Managing Sales Tax
Print
25245 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories