Hoffmaster Clintonville Plant Goes Live with Crossroads MES & LX

Anthony Etzel 0 32484 Article rating: No rating

On March 1, 2016, Hoffmaster’s Clintonville plant went live with Crossroads MES and LX. The goal of the project was to convert from another ERP to LX and replace a green screen MES system that required the manual recording of production and labor activity keyed from shop floor terminals.

Hoffmaster achieved their goal by completing a successful data conversion and detailed prototyping of LX and Crossroads. The project team remarked that the Crossroads MES implementation was by far the easiest part of the project. One of the critical requirements of the chosen MES solution was to verify UPC and UCC label formats that called for in-line labeling of product packages and cases. Crossroads MES satisfied that requirement, and also provided an interface to finished goods inventory via the scanning of LPN numbers when reporting production.

The Clintonville plant is a leading manufacturer of disposable tabletop products.

BPCS/LX Tip of the Week: Actual Costs for Manufactured Items

Anthony Etzel 0 52742 Article rating: 5.0

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.

Baan/LN Tip of the Week:GRINYA Reconciliation – What Could Go Wrong?

Kathy Barthelt 0 77261 Article rating: No rating

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan or LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error.

To ensure, it’s recommended that the Integrations Setup tables should be audited either through Baan/LN or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Morrison Brothers Goes Live With Crossroads MES in Record Time!

Crossroads RMC 0 31681 Article rating: No rating

On February 18, 2016, the Maquoketa plant of Morrison Brothers went live with the Crossroads MES solution. The goal was to remove all the shop floor paperwork and eliminate the manual recording of production and labor. The company achieved this goal in just 96 days from project kick-off to go live. Included in the go-live was the ability to deliver drawings electronically to the Crossroads MES workstations. This was a critical component of the implementation as it ensured that each workstation would always be operating off the latest revision of the engineering documents.

A rollout of the Crossroads MES solution is planned for Morrison’s Dubuque plants later this year. 

Morrison Brothers is a major producer of petroleum marketing equipment in the United States and abroad.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 72910 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 51131 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 84211 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i

Kathy Barthelt 0 32679 Article rating: No rating

Crossroads RMC is proud to announce the official release of NextTrack Sales – a sales analysis tool for Baan, LN, and IBM i. NextTrack Sales allows you to get the “big picture”, or get down into the finer details. The tool provides a sophisticated pivot grid and charting functionality, export to Excel, PDF printing, and emailing capabilities to bring your sales data to life. Analyze your Baan Sales data to examine trends, identify market opportunities, and much more. Click here for more details.

First103104105106108110111112Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Cash Flow Functionality and Setup

A cash flow statement provides a historical view of the movement of cash within a company. This statement offers an overview of both the origins and destinations of cash, aiding management in evaluating the company's ability to fulfill short-term financial obligations. To differentiate between various sources and uses of cash, reason codes can be utilized. When interacting with cash transactions in relevant sessions, users have the option to input or review the corresponding cash flow reason. The cash flow statement organizes cash transactions based on these reasons. LN software system maintains year-specific opening balances for cash flow transactions. Should the need arise, users can manually input opening balances in the Opening Balance Cash Flow (tfgld2118m000) session.

To set up the cash flow statement, use the following sequence of sessions:

  1. Group Company Parameters (tfgld0101s000): If you want to generate cash flow statements in any of the financial companies of the group, you must select the Cash Flow Statement check box.
  2. Reasons (tcmcs0105m000): Define reason codes for the sources and uses for cash that you want to distinguish. The Reason Type must be Cash Flow.
  3. Purchase Types (tcmcs2101m000): For the purchase types related to cash transactions, select the default cash flow reasons.
  4. Sales Types (tcmcs2102m000): For the sales types related to cash transactions, select the default cash flow reasons.
  5. Chart of Accounts (tfgld0108s000): For ledger accounts used for cash transactions, select the default cash flow reason in the Cash Flow Reason field. The ledger accounts must have level zero and must not be a text account, an intercompany account, or an integration account.


To enter and view cash flow transactions: Transactions that must be included in the cash flow statement must have a cash flow reason linked to them. For most transactions, ERP LN derives the default cash flow reason from the sales type, the purchase type, or the ledger account.

If you manually enter cash transactions, you can enter a cash flow reason. You can view cash flow transactions in the following sessions:

  1. Cash Flow History (tfgld2519m000): This session displays, for one cash flow reason, the opening balance, the closing balance, and the movement during one financial period.
  2. Cash Flow Transactions (tfgld1523m000): This session lists the transactions by cash flow reason.

In both sessions, on the Specific menu you can click Opening Balance to start the Opening Balance Cash Flow (tfgld2118m000) session. Use this session to view the calculated opening balances for a cash flow reason or to enter manually an opening balance, if necessary.


To print the cash flow statement: Use the Print Cash Flow Transactions (tfgld1419m000) to print the cash flow statement. You can print the report for one financial company and one fiscal year, and for a range of financial periods and cash transaction reasons.

To print the cash flow statement, use the following sequence of sessions:

  1. Cash Flow History (tfgld2519m000): On the Specific menu, click Cash Flow Transactions. The Cash Flow Transactions (tfgld1523m000) session starts.
  2. Cash Flow Transactions (tfgld1523m000): Click Print. The Print Cash Flow Transactions (tfgld1419m000) session starts.
  3. Print Cash Flow Transactions (tfgld1419m000): To print the cash flow statement, in the Report field, select Cash Flow Reason Transactions.


Other related KBs which would be helpful in Cash Flow process queries:
1998168 How to link child Cash Flow Reason Group to Cash Flow Reason

Previous Article Infor LN & Baan Tip: Considerations for Release to Warehousing for a Cost Item
Next Article Infor LN & Baan Tip: All About Invoicing Methods
Print
54908 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories