Hoffmaster Clintonville Plant Goes Live with Crossroads MES & LX

Anthony Etzel 0 32481 Article rating: No rating

On March 1, 2016, Hoffmaster’s Clintonville plant went live with Crossroads MES and LX. The goal of the project was to convert from another ERP to LX and replace a green screen MES system that required the manual recording of production and labor activity keyed from shop floor terminals.

Hoffmaster achieved their goal by completing a successful data conversion and detailed prototyping of LX and Crossroads. The project team remarked that the Crossroads MES implementation was by far the easiest part of the project. One of the critical requirements of the chosen MES solution was to verify UPC and UCC label formats that called for in-line labeling of product packages and cases. Crossroads MES satisfied that requirement, and also provided an interface to finished goods inventory via the scanning of LPN numbers when reporting production.

The Clintonville plant is a leading manufacturer of disposable tabletop products.

BPCS/LX Tip of the Week: Actual Costs for Manufactured Items

Anthony Etzel 0 52737 Article rating: 5.0

In LX, the actual costs that can be set up fall into three categories: Material, Labor, and Overhead. If your LX database is set up properly with the LX cost accounting, you should be able to identify:

  • How much the item should cost
  • How to track the cost of work underway
  • How much the item actually did cost
  • Why the job cost varied from the expected cost
     

Capturing the data to track activity with associated costs can be time-consuming. With an MES solution, the information you need for costing is tracked instantly.

Baan/LN Tip of the Week:GRINYA Reconciliation – What Could Go Wrong?

Kathy Barthelt 0 77247 Article rating: No rating

One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan or LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error.

To ensure, it’s recommended that the Integrations Setup tables should be audited either through Baan/LN or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Morrison Brothers Goes Live With Crossroads MES in Record Time!

Crossroads RMC 0 31676 Article rating: No rating

On February 18, 2016, the Maquoketa plant of Morrison Brothers went live with the Crossroads MES solution. The goal was to remove all the shop floor paperwork and eliminate the manual recording of production and labor. The company achieved this goal in just 96 days from project kick-off to go live. Included in the go-live was the ability to deliver drawings electronically to the Crossroads MES workstations. This was a critical component of the implementation as it ensured that each workstation would always be operating off the latest revision of the engineering documents.

A rollout of the Crossroads MES solution is planned for Morrison’s Dubuque plants later this year. 

Morrison Brothers is a major producer of petroleum marketing equipment in the United States and abroad.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 72906 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 51127 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 84203 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC Releases NextTrack Sales – Sales Analysis Tool for Baan, Infor LN and IBM i

Kathy Barthelt 0 32676 Article rating: No rating

Crossroads RMC is proud to announce the official release of NextTrack Sales – a sales analysis tool for Baan, LN, and IBM i. NextTrack Sales allows you to get the “big picture”, or get down into the finer details. The tool provides a sophisticated pivot grid and charting functionality, export to Excel, PDF printing, and emailing capabilities to bring your sales data to life. Analyze your Baan Sales data to examine trends, identify market opportunities, and much more. Click here for more details.

First103104105106108110111112Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Manufacturing Tip: Performance Problems in Generate Order Planning (cprrp1210m000)

When the Generate Order Planning (cprrp1210m000) session is run it can take minutes to days to finish the process.

The performance of this session depends on many settings, like the number of plan items, the number of orders, but it also depends on hardware and database setup.

Here are some guidelines on how performance can be improved.

  • Be sure you are always on the latest solutions with the planning sessions. We are constantly improving the software to gain more speed in the Enterprise Planning (EP) sessions.
  • The number of planned items is critical. Try to reduce the number of planned items. Is it necessary that all items be planned via EP? For shop floor stock the TPOP or SIC replenish systems are often more suitable.
  • When you use PCS, be sure to close the projects when they are finished. When a PCS project has status Closed, the customized items will not be planned.

It's better to run Remove Plan Items for closed Projects (cprpd1220m000). This session removes the item planning data for customized items of closed projects.

  • If you run EP with the option, Also Generate Item Master Plan and/or Online Update Item Master Plan, consider if you need an Item Master Plan for all plan items. An Item Master Plan is usually meant for global long-term planning. Again this is not very useful for shop floor stock. Reducing the number of master-planned items improves performance.
  • When you use Resource Master Plans; are all your resources really critical? If a work center is not critical do not create a Resource Master Plan for it.
  • When using Item Master Plans and/or Resource Master Plans, set in Scenarios (cprpd4100m000) the total scenario length as short as possible. For example, if your sales order horizon is 2 years, a scenario end date which is 3 years after the current date is sufficient. During the calculations of the Item Master Plan and the Resource Master, all periods defined in the scenario are checked and calculated. So if you have the end date of the scenario on 2038, EP will do the calculations (for every master-planned item) until 2038.

Defining a rolling scenario will keep your scenario length constant and you don’t have to worry that you run beyond your scenario's end date.

  • Updating the pegging relations has a serious impact on the EP performance. In EP Parameters (cprpd0100m000) you can set the Pegging Horizon in days. Keep this horizon as short as possible. The Update Signals by Item/Planner option also has some impact, but less than the pegging.
  • EP uses the so-called phase numbers to detect the lowest level in which an item is used within a BOM structure or in a supplying relation. If the phase numbers are not ‘up-to-date’, EP will correct the phase numbers during the planning. This takes time during the planning run. If there are loops in BOMs or in supplying relations, this recalculation has a big impact on the performance. Therefore you could run Compute Phase Numbers (cprpd6200m000) on a regular basis. For example once a month. Always run this session with the Generate Report option selected. If loops are detected these are reported. Be sure to solve all the reported errors.
  • When unexpected results occur, especially when the data is imported from external packages, always check the number of records in tables cprpd100 and cprpd120. The number of records should match! Remark: From 10.4 onwards the table cprpd120 has become obsolete so this point not applicable anymore.
  • The number of calendars also impacts planning performance. Then for every warehouse, work center, or BP, and so on, a different calendar is defined. Planning has to read all of these calendars from start to end. This can have a huge impact on performance.
    • If you link a calendar to a work center or warehouse, avoid defining a new calendar for every work center/warehouse. Try to link the same calendar to more than one department.
    • Define the start of the calendar close to the start date of the scenario. For example, the current date is 01-07-2014, the start date of the scenario is 365 days in the past. So a start date for your calendar could be 01-07-2012.
    • Define the end date of the calendar not too far in the future. Depending on the end date of the scenario you could use 5 years ahead.  For example, the current date is 01-07-2014, the end date of the scenario is 3 years in the future. So an end date for your calendar could be 01-07-2022. Do not define an end date past 19-01-2038, which is the last UTC date Infor LN can handle.

Also, the interaction with the database can have a big impact on performance. 
A commonly used way to improve the total run time of the EP run is to start the session in parallel processing. 
See also Knowledge Base Article 22881401 Performance, Tracing and tuning Guide, for more details.

These guidelines are just some hints, and a good starting point because performance is a complex issue.

Previous Article Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)
Next Article Infor LN & Baan Tip: Broadcast message to users
Print
67287 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories