Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 7347 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

Is Your ERP System Hurting Your Business?

The Importance of an Integrated System

Kathy Barthelt 0 5017 Article rating: 5.0

It could be if your ERP system isn't integrated with other systems that contain mission-critical business data.

Having data in two (or more) systems that don’t talk to one another is like baking a pizza crust in one oven and the toppings in another. Once baked, you may have food to snack on, but it sure isn’t pizza! Pizza requires the cheese, sauce and spices to bake with the crust, so all the flavors meld together when you take that first delicious bite. 

That’s the value of an integrated ERP system. When you...

Optimize with Infor Development Framework: IDF

Infor LX | BPCS | M3

George Moroses 0 5963 Article rating: 5.0

Why You Need IDF

The Infor Development Framework (IDF) not only helps you modernize the look and feel of your LX software but also the interactions of the IBM i software with other applications in your business.

“The IDF is a multi-user interface, single codebase architecture that’s metadata-driven (and) provides a lot of flexibility to adapt the software for their processes.” says Infor. This is the direction that Infor is going starting...

RSS
First567810121314Last

Theme picker

Tips:  LX | BPCS | M3

Determining whether to use Master Production Schedule (MPS) planning or Material Requirements Planning (MRP) planning for items in Infor LX and BPCS involves understanding the nature of the items and their demand characteristics.

Master Scheduled Items typically encompass finished goods or service items. These items receive their requirements either from Independent demand, Dependent demand, or a combination of both...

Advanced Remittance Processing, ARP, provides an automated approach to your cash application process. ARP works together with Accounts Receivable to save valuable time and resources by automatically applying incoming payments to open receivables during daily batch processing. You can easily and efficiently resolve unapplied remittances online.

Advanced Remittance Processing (ARP) is an automatic cash application process that allows you to perform the following functions:

1234567810Last

Theme picker

Tips: LN | Baan

Kathy Barthelt
/ Categories: Infor LN & Baan Tips

Infor LN & Baan Tip: Project Status Options

Ever wonder what the implications are of choosing one project status versus another?

Here is the explanation of project status possible values:

Free
You can carry out project engineering. This means that you can:

  • Define the project master schedule (PMS) by using the Project Control module.
  • Maintain the project structure.
  • Maintain the customized product structure by using customized bills of material and routing sheets.
  • Carry out project estimating.

Simulated
You simulate the rough capacity requirements planning and the detailed material and resource requirements planning (RRP) based on the network planning. The capacity requirements for a simulated project are visualized separately. Infor LN (ERP LN) generates planned RRP purchase orders, planned production orders, and PRP warehouse orders for customized items. However, those orders cannot be released. Moreover, the RRP does not allocate standard items to the project.

Active
This status indicates the project's execution stage. You can release planned orders so that the required purchase and production activities can be actually started and completed.

Canceled
The project has been canceled. You cannot release new orders for the project, but you can, however, finish pending logistical activities. You can close a canceled project, but a project can also remain canceled. If the project remains canceled, be aware that the final costs are not posted to Financials, and that WIP can still exist for completed orders. Costs are only posted if you close the project.

Finished
As far as manufacturing is concerned, the project is finished. Also, all purchase and production activities have been completed or closed, and all sales orders have been delivered for the project.

Closed
Financially, the project has been closed. This means that the financial project results have been computed. Financial project transactions can no longer be posted to the project.

To be Closed
If you select the COGS and Revenues restricted to Financial Company of PCS Project check box in the Project Control Parameters (tipcs0100m000) session, financial transactions are posted on the financial companies of the sales office, service department, and/or warehouse instead of on the financial company of the PCS project. If internal invoices are sent from the PCS project to those departments, and the internal invoices are not completed yet, the Close Project (tipcs2250m000) session sets the project status to To be Closed instead of to Closed. You must first complete the internal invoices, and then run the Close Project (tipcs2250m000) session again to set the project status to Closed.

Archived
The project has been archived. This means that all project data has been stored in archive files and is removed from the original files.

Previous Article Infor LN & Baan Tip: LN Order Management - Generating Purchase Receipts
Next Article Infor LN & Baan Tip: Cost Component Setup
Print
12528 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Theme picker

Contact author

x

Categories