Why You Need IDF

The Infor Development Framework (IDF) not only helps you modernize the look and feel of your LX software but also the interactions of the IBM i software with other applications in your business.

“The IDF is a multi-user interface, single codebase architecture that’s metadata-driven (and) provides a lot of flexibility to adapt the software for their processes.” says Infor. This is the direction that Infor is going starting with LX 8.3.4 covering inquiries that can replace green screen 300 series inquiries. Newer versions of LX 8.4 and above introduces master file maintenance programs with the IDF and there are no longer green screen master file maintenance programs. 

It’s a Win-Win!  - So why aren't you taking advantage of the IDF? 

  • Not installed?
  • It's installed, just not using it?
  • Not licensed?
  • Don't know how to use it?

To get you started, Crossroads RMC specializes in:

  • Installation
  • User set-up
  • Security authorization
  • Basic and advanced training
  • User navigation by replacing multiple green screen sessions
  • Creating business objects and views


To learn how the IDF and Crossroads RMC can optimize your Infor LX, ERP LX, BPCS, and M3, please contact George Moroses today!

Get a free consultation

Previous Article Infor LX & BPCS Tip: The Top 6 Benefits of CLD
Next Article Infor LN & Baan Tip: 15 Reconciliation Steps for GRNI Transactions
Print
18435 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Understanding: How many hours remain in total and at each operation?

Now let’s look at what information is being supplied from the shop floor.

It’s not uncommon for transaction reporting to be captured manually on the shop packet that was issued to the factory floor when the SO was released.

The big question is, is anything done with the data? Is it collected and keyed to a  spreadsheet and not shared, or is the transaction data keyed to SFC600? If it is being keyed, ask how often and by whom? Some companies use alternative methods to capture transaction data that do not require batch keying via a keyboard.

Not a lot of data is required to be keyed to SFC600 in order for the SO Inquiry to be useful. The data that should be reported for the transaction process is as follows:

  • The type of hours being reported – machine, run labor, setup labor
  • If reporting setup and run labor you want an employee clock number
  • The shop order and the operation that is being reported
  • Is the operation complete
  • How many good were produced at this operation
  • How many hours – the numbers of hours are critical. Do the employees estimate how many hours they worked, or do they track actual time started and stopped in order to calculate the actual number of hours.

Based on what is captured and how often will have an impact on the SO inquiry screen. Understanding the batch times as to when the transactions are keyed will provide you with the window as to the SO status at that point in time. Or, are they keyed as they happen in a near real time fashion so that you can have a more current view of the factory floor.

Understanding: How many hours remain in total and at each operation?

First let’s look at some key BPCS Master File data starting with the routing file.

How many routing steps (operations) are set up that reflect how the product is produced in the factory? If you take a short cut and set up only one operation for the entire process, then you will limit the information seen on the SO inquiry program. Set up the operation steps to reflect what you want to report back to from the factory floor.

Will each of the routing steps run in one work center, or in different work centers? To keep it simple you may want to set up work centers as departments. For example:

  • Assembly
  • Machine
  • Paint
  • Etc.

For each operation setup consider how you have set up the following:

  • Load Codes – for example a code 5 is used if reporting both setup time and run labor time. These codes are maintained in the work center file
  • Basis Code – typical codes are P for pieces per hour,  3 is used for hours per 1,000 pieces
  • Setup hours – if you set them up, you also want to report them
  • Run hours – Direct Labor
  • Machine hours

How you set up th