In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article BPCS/LX Tip of the Week: What is Lean Make to Order?
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
113985 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

In typical LN REST API integrations, permissions and authorizations are not implemented or rarely used. To ensure smooth data exchange and avoid errors, it is recommended to disable the authorization and security settings.

Recommendation:

  • In the Authorization and Security Parameters session (tcsec0100m000):

    • Clear the Authorization and Security Enabled check box.

    • Clear all check boxes under Authorization Enable for on the Enabling tab.

Why This Matters:

  • Enabling authorization and security without proper setup can lead to errors and blocked transactions during integration.

  • For example, work center permissions may interfere with:

    • Creating new shifts

    • Booking machine hours

    • Read more