Baan/LN Tip of the Week: Default Order Frequency

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Previous Article BPCS/LX Tip of the Week: What is Lean Make to Order?
Next Article Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance
Print
114061 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

Please solve captcha
x

Tips:  LX | BPCS | M3

Enhances purchase order efficiency by automatically calculating the Vendor Delivery Date based on user input.

  • When a purchase order line is created, the user enters the item, order quantity, and Due Date.

  • LX automatically calculates the Vendor Delivery Date, adding buffer time for quality control, testing, and inspection activities.

  • If the Due Date is revised, an informational message prompts the user to review and potentially update the Vendor Delivery Date.

Enhancements:

  • A new PUR820 system parameter enables automatic recalculation of the Vendor Delivery Date.

  • Instead of a manual reminder, PUR500 now issues a message: “Vendor Delivery Date recalculated,” showing the updated date.

Benefits:

  • Eliminates the need to manually review and update the Vendor Delivery Date.

  • Removes the need to delete and recreate PO lines to trigger automatic date calculation.

Enables integration between LX and Infor OS Federation Services (IFS) to automate user provisioning.

  • Bi-directional user synchronization between Infor OS and LX:

    • Infor OS user creation or changes automatically create or update users in LX.

    • IBM i user profiles can be created if needed.

    • Updates to SYS600 user data are reflected in Infor OS.

  • Security Role Integration:

    • LX Security Roles and Units are published as IFS Security Roles via SyncSecurityRoleMaster BODs.

    • LX receives inbound SyncSecurityUserMaster BODs from IFS to create or update user records in SYS600.

    • SYS600 Exit Points trigger ProcessSecurityUserMaster BODs to request user creation or updates in IFS on behalf of LX.

Available Versions: 8.3.5, 8.4.1, 8.4.2

FirstLast

Tips: LN | Baan

In typical LN REST API integrations, permissions and authorizations are not implemented or rarely used. To ensure smooth data exchange and avoid errors, it is recommended to disable the authorization and security settings.

Recommendation:

  • In the Authorization and Security Parameters session (tcsec0100m000):

    • Clear the Authorization and Security Enabled check box.

    • Clear all check boxes under Authorization Enable for on the Enabling tab.

Why This Matters:

  • Enabling authorization and security without proper setup can lead to errors and blocked transactions during integration.

  • For example, work center permissions may interfere with:

    • Creating new shifts

    • Booking machine hours

    • Read more

Categories