BPCS/LX Tip of the Week: Multi-level Shop Order Release Due Dates

Anthony Etzel 0 58082 Article rating: 5.0

Previously, Material Requirements Planning (MRP) preferred practices meant that the component’s due date was the same as the parent’s shop order release date. Because MRP trends have changed, the preference for this due date is the day before the release date of the parent. Although Infor LX already has this functionality in Shop Order Maintenance programs (SFC500), users could not change how due dates were determined for lower level shop orders in Multi-Level Shop Order Release, SFC530D.

This enhancement provides an additional parameter for Multi-Level Shop Order Release. This parameter allows the user to change how the due date of the child components is determined. The user is now able change how the due date is determined for multi-level shop orders. If the Due Date of Children parameter is set to 1=Yes, the due date of the child components is the same as the release date of the parent. If the parameter is set to 0=No, the due date is the day before the release date of the parent.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: How is Your Productivity?

Kathy Barthelt 0 84207 Article rating: No rating

Are your employees not as productive as you’d like them to be? Are jobs not getting completed on schedule? 

Without actual data, making decisions about how efficient your operation is will be difficult. Start tracking actual time to complete each operation. Compare different production lines running the same job. Is one line running more efficiently? If so, start looking at why. Track downtime, setup, etc. Once you start really analyzing each piece of the puzzle, you can begin to uncover areas that are ripe for improvement.

Optimize Your Manufacturing Today!

Tip of the Week: Create a Repeatable Process

Kathy Barthelt 0 104058 Article rating: No rating

If you’ve been successful doing something in the past, you want to keep doing it that way. Are your procedures documented? Do you have workflows defined? Would creating video tutorials be helpful, especially for new employees? Giving employees the tools to be successful helps to ensure the success of the business as a whole.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: 6 Powerful Steps to Win With Automation

Anthony Etzel 0 57110 Article rating: 5.0
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.     
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: 6 Powerful Steps to Win With Automation

Kathy Barthelt 0 85347 Article rating: No rating
  1. Eliminate paper shop packet and distribution of the paperwork to the shop floor.    
  2. Eliminate manual (paper-based) recording activities and the need to key in the transactions.
  3. Easy electronic scheduling by sequence and changing job priorities.
  4. Evaluate differences using actual times compared to standards.
  5. Improve data accuracy and eliminate the need to chase and fix errors.
  6. Practice Real-Time data reporting to monitor efficiencies and identify problems as they occur.

Optimize Your Manufacturing Today!

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 81299 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.

In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
    1. Price
    2. Quantity
    3. Vendor rating
    4. Delivery dates
    5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

Optimize Your Manufacturing Today!

BPCS/LX Tip of the Week: Using Pre-Assigned Lot Numbers

Anthony Etzel 0 48384 Article rating: 5.0

Some items in the manufacturing process may require a lot number. A quick and easy way to release the Shop Orders with lot numbers is by using the Multi-Level Shop Order Release.

Simply select the end item from the selection screen and use action 10 for the multi-level order release. At the bottom of the release screen is the field “Pre-Assign a Lot Number to Shop Orders”. Select 1 for the pre-assigned lot number assignment option.

This option will use the pre-assigned lot number on the shop order, if the lot number exists. If the lot number does not exist, the system will automatically create a lot number and assign it to the shop order for all items that are lot-controlled.

Optimize Your Manufacturing Today!

Blonder Tongue Goes Live with Crossroads MES

Anthony Etzel 0 27054 Article rating: 5.0
Blonder Tongue Labs recently went live with the Crossroads MES solution over their current BPCS 6.0.4 environment. They selected the Crossroads MES solution for its shop floor management and reporting capabilities. Blonder Tongue is a leader in the field of cable-television communications products. They are planning an upgrade to LX and will expand the usage of Crossroads MES in the LX environment.
First8990919294969798Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Tim Baker – Infor LX User Group’s Newest Board Member!

Tim Baker – Infor LX User Group’s Newest Board Member!

We are proud to announce that Tim Baker, Crossroads RMC Senior Solutions Architect & Project Manager, has become a member of the Infor LX User Community Board of Directors!

Tim brings 32 years of experience to Crossroads RMC and takes pride in offering exceptional leadership and expertise to achieve the goals and objectives of his clients. It is this level of experience that will make Tim an excellent representative for the Infor LX Community going forward as a member of the board.

At Crossroads RMC, Tim serves as a Senior Solutions Architect and Project Manager for Infor LX and Infor ION implementations. He has been a Senior Manager of Software Development and Support, Senior System Analyst, and has managed software development team objectives and projects, which included planning, installation, and software modification of BPCS, Infor LX (ERP LX), I2, DC Service, and web development software. Additionally, he has managed a multitude of projects and led analysis, design, training, and development efforts across multiple ERP verticals.

Please join us in congratulating Tim and wishing him well in his efforts to help the Infor LX User Community!
​Infor User Communities allow you to network with other customers and discuss any of Infor’s software solutions. 

Not currently a member of the Infor LX User Group?
The LX User Group has moved to https://concierge.infor.com. All access requests require approval by your organization's support admin. Once you have access to https://concierge.infor.com, click on the Communities box, and join the LX - User Group - LX.

Print
30538 Rate this article:
5.0
George Moroses

George MorosesGeorge Moroses

Other posts by George Moroses

Contact author

x

Categories