Infor LN & Baan Tips & Tricks for Operations: Copying EBOMs - Which copying method should I use?

Kathy Barthelt 0 50374 Article rating: 5.0

To determine which copying method you must use, answer question 1 and follow the instructions.

Question 1: Is the source component a project item (that is, is a project defined in the first segment of the item code)?

  • If the answer is yes, proceed with question 3.
  • If the answer is no, proceed with question 2.


Question 2: Is the target component a project item?

  • If the answer is yes, select copy method NonProj Item to Proj Item.
  • If the answer is no, proceed with question 4.

Question 3: Is there a relationship with the same project?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, proceed with question 4.


Question 4: Is there a relationship with the target item?

  • If the answer is yes, proceed with question 5.
  • If the answer is no, select copy method No Copy Action.


Question 5: Does the item exist already?

  • If the answer is yes, select copy method EBOM to Production BOM Only.
  • If the answer is no, select copy method Copy E-Item to Item.

Infor LX / BPCS Tips & Tricks for Finance: Inventory Period Balance Freeze

George Moroses 0 18170 Article rating: 5.0

Users can now freeze period-end balances at the end of a fiscal period. You can now store the opening/ending on hand balance for each Inventory period at the Item (IIM), Warehouse/Item (IWI) and Lot/Location (ILI) levels. This information can then be used for inventory tracking and valuation purposes, as well as other ad hoc financial and audit reporting requirements. Infor LX clients can backdate inventory transactions into the immediate previously closed period, and thus update what was saved as the opening/ending balance throughout the current open period.

Infor LX / BPCS Tips & Tricks for Operations: Retain Lot Status on Shipped Resupply Orders

George Moroses 0 13246 Article rating: 5.0

When a lot is completely shipped on a customer order, the Lot Status is changed to Z. Since a resupply order must still be received in the To Warehouse to complete the transaction, do not update the lot status when the resupply order is shipped. If a lot is completely shipped on a resupply order, LX no longer updates the lot status to Z, because the shipped lot retains its current lot status, the additional steps, no additional steps are required to receive it in the To Warehouse.

Infor LX / BPCS Tips & Tricks for Technology: Reset Purchase Order In Use

George Moroses 0 14051 Article rating: 5.0

This feature resolves or resets a purchase order or requisition that is no longer being processed, but the system still indicates it is 'in use'. The user selects Purchase Order/Requisition in Use Maintenance, PUR940D, from the Purchasing Management Menu, PUR, located in the Special Processing sub-menu. The user then enters an order or requisition to remove the 'In Use' status.

End of Year E R P Checklist: Streamline Your Transition to the New Year

Crossroads RMC 0 7068 Article rating: 5.0

The end of the year is a busy time for everyone, but a little preparation can make the start of the next year smoother and more productive. Here's a checklist broken out by the department to help optimize your ERP system as you wrap up this year.

  1. All Departments Checklist
  2. Technology Checklist
  3. Operations Checklist
  4. Finance Checklist
First34568101112Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

It’s Mid-January, and IT’S GO TIME!
Crossroads RMC
/ Categories: Services News

It’s Mid-January, and IT’S GO TIME!

Infor LX | BPCS | Infor LN | Baan

The calendar is fresh, the resolutions are set, and the opportunities are endless!

But before you dive headfirst into tackling your to-do list, take a moment.

Pause.

Now is the perfect time to reflect and plan your ERP strategy.

What’s an ERP Strategy?

An ERP strategy is a roadmap for the steps you should take before, during, and after implementing an ERP system. It’s designed to ensure your ERP delivers on its promise of functionality and success—the backbone of running your business effectively.

Think of it like planning a road trip:

  • Which cities will you visit?
  • Where will you stay?
  • What landmarks do you want to explore?

Without a plan, you’re winging it. While spontaneity might work for a vacation, it’s risky when it comes to your ERP system.

A poorly executed road trip might waste time or cause frustration, but a poorly executed ERP strategy? That can hinder your business growth, create inefficiencies, and lead to costly mistakes.

What if:

  • You never evaluated whether your ERP aligns with your company’s growth strategy?
  • Your employees didn’t fully understand how to use critical features, leading to incomplete or incorrect transactions?
  • You missed out on new ERP features or overlooked opportunities to streamline processes, saving time and money?

Whether your next steps include a major ERP upgrade, integrating new tools, or optimizing the system you have today, there’s always room for improvement.


How Crossroads RMC Can Help

At Crossroads RMC, we provide tailored ERP solutions to ensure your success. Our services include:

  • Implementing New Functionality: Unlock the full potential of your current ERP version.
  • ERP Upgrades: Stay current by upgrading to the latest version.
  • Employee Training: Train new employees or retrain your team with best practices.
  • Process Automation: Reduce manual, time-consuming tasks.
  • System Integration: Connect all your tools into a cohesive system that communicates seamlessly.
  • ERP Add-On Solutions: Save significant time and money with innovative add-ons.

Our mission is to optimize your manufacturing operations by reducing costs, improving quality, and increasing efficiency.


Explore:

Let’s Make This Your Year

Contact Crossroads RMC today to develop an ERP strategy that positions your business for success in 2025 and beyond.

solutions@crossroadsrmc.com | 800.762.2077

IT’S GO TIME!

Print
6011 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories