Infor LN & Baan Tip of the Week: Job Shop Bill of Material – 10.7

Kathy Barthelt 0 77862 Article rating: 5.0

The job shop bill of material is defined by site. It is used as the source for the estimated materials in the job shop production order.

The new job shop bill of material differs from the old bill of material. These changes are applicable for the new job shop bill of material:

  • It has a header and a status.
  • It is always revision controlled.
  • It can be designated for planning and for costing.
  • The effective dates have been moved from the material lines to the header.
  • The BOM quantity has been moved from item production data to the header.
  • The use up has been moved from alternatives to the material line.
  • The warehouse is defined on the material line (mandatory).
  • The routing operation is defined on the material line (optional).

The job shop bill of material can be generated through the production bill of material.

IDF News: default order class for the warehouse customer

George Moroses 0 29552 Article rating: 5.0

In IDF Customers, the default order class for the warehouse customer should be a user-defined order class (base order class = 004). Do not use base order class 002 or 005, to allow for automatic invoicing of warehouse orders (if a separate manual Ship Confirm event is required per the order class, auto invoicing cannot occur from Pick Confirm).

Can you afford not to invest in MES?

Anthony Etzel 0 32815 Article rating: 5.0

Given the environment today with growing global competition in terms of innovation, cost and time to market (given by short product cycles) as well as with increasing regulatory demands, the answer to the question “Can you afford not to invest in MES?” is turning into a clear “NO”. 

Click here to read the full Critical Manufacturing article.

Crossroads MES is Infor’s global solution for manufacturing execution and is perfectly suited to fill the gap between your manufacturing initiatives and your ERP system.

Crossroads RMC proudly announces the LX 8.3.5 go live for Trinity Industries.

Anthony Etzel 0 39697 Article rating: 5.0

Trinity Industries is live on LX 8.3.5! This project was truly a team effort working in partnership with HCL America. Crossroads RMC's involvement included John Kasper (Finance), David Campbell and Nick Olson (Operations), Jacob Hale (Supply Chain Management), and Tony Curtis (LX Administration). 

Trinity began providing industrial products and services to customers more than 85 years ago. They started as a small butane-tank manufacturer and evolved over time into a premier diversified industrial company with market-leading businesses serving the energy, chemical, agriculture, transportation, and construction sectors.

Infor LX & BPCS Tip of the Week: Pre-Assigned Lot Numbers – LX

Anthony Etzel 0 54876 Article rating: 5.0

In addition to assigning lot numbers in Shop Order Entry/Maintenance (SFC500) after the shop orders have been released, users can now pre-assign lot numbers during the Multi-level Shop Order Release process (SFC530) and the Multi-Level Backflush process (LMP600) for sub-assemblies that are lot controlled items. The user has the choice of using the parent lot ID, the next sequential generated lot ID, or not pre-assigning lot IDs. Multiple items per lot must be installed to use the parent lot number option.

Infor's Support Schedule for Infor LN & Baan

How Crossroads RMC can help

Kathy Barthelt 0 76544 Article rating: 5.0

Infor recently announced their support schedule for all versions of Infor LN & Baan.

Not sure what your company’s strategy should be moving forward?

Let us help you figure out the best path forward for YOUR company. Our goal is to put you on a path that ensures that you are supported and that your needs are met today and in the future without breaking the bank. Visit our Services page to learn more>

First6263646567697071Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: Role-Based Security
Next Article BPCS/LX Tip of the Week: Inventory Transaction Post to G/L by Cost Type
Print
28614 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.

Categories