Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

Infor LX & BPCS Tip of the Week: MPS vs. MRP

George Moroses 0 64993 Article rating: 5.0

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, Infor/ERP LX will calculate cumulative lead time (also called “the Critical Path”) for you (use the “indented BOM” display in BOM300 and find the item with the longest lead time “L/T”). Note: You may have to use Action 21, Line Detail, to see the “L/T” lead time for each item.

You’ve got a handle on your inventory requirements, right? Are you confident you can handle a rush order, or ten rush orders?

Baan & LN Add-Ons

Kathy Barthelt 0 35873 Article rating: 5.0

RMCbuild gives you the ability to report a component’s gross requirement, shortage, on-hand inventory, on-order inventory, allocated inventory, inspected inventory, production or work orders due to replenish component inventory, buyer or planner, and/or item group… and more.

RMCbuild takes all the surprise and guess work out of inventory planning. Give your employees the tools they need to do their job effectively.

Avalara isn't only tax calculation and returns filing....

Baan & Infor LN

Kathy Barthelt 0 40648 Article rating: 5.0

Did you know that in addition to tax calculation and returns filing, Avalara can also help with:

  • Business license and tax registration
  • Streamlined Sales Tax qualification
  • Nexus analysis and compliance
  • Tax document management including exemption certificates
  • Audit preparation

Contact us today! We partner closely with Avalara to provide you with solutions on ALL version of Baan and Infor LN!
 

Infor LN & Baan: Is Your House All In Order?

Kathy Barthelt 0 32216 Article rating: 5.0

Have you successfully closed all of the fiscal, tax and reporting periods for 2019 and closed the year? Sometimes this task hangs out there looming because either people don’t know what needs to be done, or there is a fear there are going to be problems.

Let Crossroads RMC’s expert finance consulting team help you through this.

Move into 2020 with ease! Contact Kathy Barthelt today to put together a plan for your close.
800.762.2077

Want a way to convert IBM i ® spool files into full-color, professional forms that are output as PDF documents?

Anthony Etzel 0 32669 Article rating: 5.0

Want a way to convert IBM i ® spool files into full-color, professional forms that are output as PDF documents?

Crossroads RMC and TL Ashford can help you get there!

TLAForms provide a reliable, feature-rich, cost-effective forms solution for IBM i, with no programming required!

Contact Anthony Etzel for more info: 1.630.955.1310, x125 or aetzel@crossroadsrmc.com

Join us in St. Louis for inPOWER 2020!

inPower 2020

George Moroses 0 31890 Article rating: 5.0

We can’t wait to see you this May at the PREMIER event for Infor LX & BPCS users! Join us for the conference and a special customer appreciation event!

Why attend?

  • Participate in exclusive training sessions
  • Attend user experience and industry presentations on topics relevant to your business
  • View new product demos to give you the tools needed to tackle issues we all share

Click here to register and please let us know that you will be attending!

What is the right balance of KPIs to make sure your production line is running at peak performance?

Analytics Dashboard

Crossroads RMC 0 33702 Article rating: 5.0

How can we make sure the production line is running at peak performance?

One very effective way is to put the right balance of production KPIs in place. Some of these are leading indicator KPIs that help provide insight into future performance and some are results KPIs that tell you how you have done. It is good to have both.

Check out this list of 21 examples of KPI indicators for 2020 to help improve manufacturing performance.

Analytics Dashboard for Infor LN & Baan
Analytics Dashboard for Infor LX, BPCS & Infor M3

First5354555658606162Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Why Would You Buy a BMW, But Use a Scooter?

Congratulations! You bought that shiny, new car! It has all the features you can possibly want and goes a million miles an hour. It can take you anywhere your heart desires…….but you rely on a manual scooter to get you around. You know, the kind you had when you were a kid…BEFORE you could drive…before you could afford the BMW. Make sense? Uh... no.

You’d never do this, right? So, why are you doing this with the ERP system that runs your business? Why are you relying on spreadsheets and separate little Access databases to record and store the information that is the most critical to your business when you have an ERP system that is meant for this? Why continue to plod along at a snail's pace when you have the tools to take your business to the next level?

Your ERP system is your BMW. Use it. See what it can do for you. Think you’ve used it to its potential? Unlikely. We’ve helped customers breathe new life into their EXISTING ERP version all by unlocking functionality for them that was already there and ready to use! We’ve also helped by offering add-ons to the ERP that can make your productivity skyrocket.

Ask us how. We’ve got an extra set of keys to the BMW in case you lost yours.

Optimize Your Manufacturing Today!

Previous Article Tip of the Week: The 3 Secrets to Improving Your MO (Manufacturing Optimization)
Next Article BPCS/LX Tip of the Week: At a Loss?
Print
49165 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.

Categories