Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

George Moroses 0 31370 Article rating: 5.0

This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply....

Infor LX & BPCS Materials Tip: Over-Receipts

George Moroses 0 32955 Article rating: 5.0

If Infor LX is set up to prevent over-receipts, you cannot post a receipt quantity that is more than the remaining PO line quantity with the over-tolerance % added to it.

As an alternative, you can:

  • Receive the maximum, remaining line quantity plus over-tolerance percentage quantity, and reject the balance to quarantine or
  • Receive the full quantity into quarantine.


Note: Over-receipt checking applies only to receipts to stock.

Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)

Kathy Barthelt 0 79269 Article rating: 5.0

Customer Defined fields are fields that can be added to tables, screens, reports, and BODs. Validation and calculation logic can be defined around those fields. This gives you great added capability and flexibility… however, are you aware of the limitations of using CDFs?

  • You cannot define customer-defined fields for tables within Tools (the tl and tt packages).
  • External integrations.....

Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX

George Moroses 0 31084 Article rating: 5.0

The Credit Card Data Area program, SYS045D, enables you to create and maintain a configuration file that provides a gateway to a third-party payment application. The information you set up with this program is required to allow Infor LX to communicate with the credit card processing application that passes credit card payment information between Infor LX and the credit card providers.

Access: SYS menu

  • Use the Credit Card Data Area screen, SYS045D-01, to...

Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 32150 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 73360 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

First4849505153555657Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

What do you do when there is no pre-built Infor integration from UPS or FedEx to your LN system?

Call Crossroads RMC, of course! 

That’s how one of our Infor LN customers solved their cloud implementation dilemma. Crossroads RMC partnered to streamline their shipping process on Infor LN 10.5.2 in the cloud. Four sites went live with RMCship in 2019 and as a result, they have increased accuracy by eliminating manual steps and streamlining their operations.

Contact Crossroads RMC today to get started 800.762.2077

Previous Article Infor LN & Baan Tip of the Week: What is the LN Report Designer and what is required to use it?
Next Article Infor LN & Baan Tip of the Week: New Inventory Aging Analysis Report – 10.7
Print
114030 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories