Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

George Moroses 0 28221 Article rating: 5.0

This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply....

Infor LX & BPCS Materials Tip: Over-Receipts

George Moroses 0 29836 Article rating: 5.0

If Infor LX is set up to prevent over-receipts, you cannot post a receipt quantity that is more than the remaining PO line quantity with the over-tolerance % added to it.

As an alternative, you can:

  • Receive the maximum, remaining line quantity plus over-tolerance percentage quantity, and reject the balance to quarantine or
  • Receive the full quantity into quarantine.


Note: Over-receipt checking applies only to receipts to stock.

Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)

Kathy Barthelt 0 74074 Article rating: 5.0

Customer Defined fields are fields that can be added to tables, screens, reports, and BODs. Validation and calculation logic can be defined around those fields. This gives you great added capability and flexibility… however, are you aware of the limitations of using CDFs?

  • You cannot define customer-defined fields for tables within Tools (the tl and tt packages).
  • External integrations.....

Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX

George Moroses 0 28116 Article rating: 5.0

The Credit Card Data Area program, SYS045D, enables you to create and maintain a configuration file that provides a gateway to a third-party payment application. The information you set up with this program is required to allow Infor LX to communicate with the credit card processing application that passes credit card payment information between Infor LX and the credit card providers.

Access: SYS menu

  • Use the Credit Card Data Area screen, SYS045D-01, to...

Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 29399 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 67450 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

First4445464749515253Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: How To Capture Re-Work Time (Part 1)

In SFC600, there is no code to capture the time spent on re-work. Re-work is usually at a specific operation, or when the part is finished and QC determines that re-work is required in order to pass inspection. You are faced with deciding on how to report the additional labor time.

Do you continue to report it against the operation, or create a re-work shop order?

If you are re-working through a specific operation you can capture the time as run labor with the SFC600 program. Now you need to deal with the variance of actual to standard time and what impact this has on costing.
Previous Article BPCS/LX Tip of the Week: Configuration Management
Next Article BPCS/LX Tip of the Week: The Item Master Requirements Code
Print
91056 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

Use this session to define simulated purchase prices for purchased items per site.

Field Information:

  • Cost Calculation Code - price calculation code
  • Item

The raw materials, subassemblies, finished products, and tools that can be purchased, stored, manufactured, and sold.

An item can also represent a set of items handled as one kit, or which exist in multiple product variants.

You can also define nonphysical items, which are not retained in inventory but can be used to post costs or to invoice services to customers. The examples of nonphysical items:

  • Cost items (for example, electricity)
  • Service items
  • Subcontracting services
  • List items (menus/options)
     
  • ​Site - The site for which the purchase price is simulated.
  • Purchase Currency - The currency of the simulated purchase price.
  • Simulated Price - Purchase price

The simulated purchase price and currency are recorded twice.

  • Simulated Price Multi Currency - The purchase price in multiple currencies.

The simulated purchase price and currency are recorded twice. The amount in this field is related to the price of the supplier.

  • Unit - Purchase price unit
  • Cost Component - The cost component that must be of the type Material Costs.

Note: The cost component specified in this field does not become part of the standard cost detail structure if it is part of the cost component scheme of the selected item. If calculations are performed with a calculation code not used for actualization (simulations only), the simulated purchase price is mapped to the cost component defined in the records for this session.

Categories