Infor LX & BPCS Manufacturing Tip: Shop Calendar Maintenance – SFC140D1

George Moroses 0 27591 Article rating: 5.0

This program features multiple-level shop calendar maintenance. You can maintain a shop calendar at the global, facility, or work center level. Global level entries override default values found in Work Center Maintenance, CAP100D1, for any program that uses the shop calendar.

Facility overrides affect all work centers in a Facility and are exceptions to the global level. Exceptions defined at the Facility level apply to all work centers for the facility. Work Center calendar entries are the most specific. These entries apply....

Infor LX & BPCS Materials Tip: Over-Receipts

George Moroses 0 29443 Article rating: 5.0

If Infor LX is set up to prevent over-receipts, you cannot post a receipt quantity that is more than the remaining PO line quantity with the over-tolerance % added to it.

As an alternative, you can:

  • Receive the maximum, remaining line quantity plus over-tolerance percentage quantity, and reject the balance to quarantine or
  • Receive the full quantity into quarantine.


Note: Over-receipt checking applies only to receipts to stock.

Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)

Kathy Barthelt 0 72885 Article rating: 5.0

Customer Defined fields are fields that can be added to tables, screens, reports, and BODs. Validation and calculation logic can be defined around those fields. This gives you great added capability and flexibility… however, are you aware of the limitations of using CDFs?

  • You cannot define customer-defined fields for tables within Tools (the tl and tt packages).
  • External integrations.....

Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX

George Moroses 0 27568 Article rating: 5.0

The Credit Card Data Area program, SYS045D, enables you to create and maintain a configuration file that provides a gateway to a third-party payment application. The information you set up with this program is required to allow Infor LX to communicate with the credit card processing application that passes credit card payment information between Infor LX and the credit card providers.

Access: SYS menu

  • Use the Credit Card Data Area screen, SYS045D-01, to...

Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 28599 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 66134 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

First4041424345474849Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Understanding What Goes On Out On The Factory Floor – Part 4

Understanding: What Was Issued to the Shop Order

The shop order inquiry program provides several function keys. By using the function key for the material, the display will present what components have been issued under the issued quantity column. You are also presented with the required quantity. While viewing the quantities you may see that more was issued than what was required. Possibly there was scrap and more material was required to be issued. Perhaps there was an over issue and the balance of the material is slated to be returned to stock.

A red flag should go up if the Shop Order quantity finished is equal to the required quantity for the end item and all the components have not been issued. You may want to investigate why.

Previous Article BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3
Next Article BPCS/LX Tip of the Week: Changing the Master Schedule