Infor LX & BPCS Materials Tip: Over-Receipts

George Moroses 0 29378 Article rating: 5.0

If Infor LX is set up to prevent over-receipts, you cannot post a receipt quantity that is more than the remaining PO line quantity with the over-tolerance % added to it.

As an alternative, you can:

  • Receive the maximum, remaining line quantity plus over-tolerance percentage quantity, and reject the balance to quarantine or
  • Receive the full quantity into quarantine.


Note: Over-receipt checking applies only to receipts to stock.

Infor LN & Baan Tip of the Week: Limitations of Customer Defined Fields (CDFs)

Kathy Barthelt 0 72691 Article rating: 5.0

Customer Defined fields are fields that can be added to tables, screens, reports, and BODs. Validation and calculation logic can be defined around those fields. This gives you great added capability and flexibility… however, are you aware of the limitations of using CDFs?

  • You cannot define customer-defined fields for tables within Tools (the tl and tt packages).
  • External integrations.....

Infor LX & BPCS Tip of the Week: Credit Card Processing Within LX

George Moroses 0 27522 Article rating: 5.0

The Credit Card Data Area program, SYS045D, enables you to create and maintain a configuration file that provides a gateway to a third-party payment application. The information you set up with this program is required to allow Infor LX to communicate with the credit card processing application that passes credit card payment information between Infor LX and the credit card providers.

Access: SYS menu

  • Use the Credit Card Data Area screen, SYS045D-01, to...

Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 28449 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 65909 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

First4041424345474849Last

Tips:  LX | BPCS | M3

Crossroads RMC

Tip of the Week: Finding the Cause of Waste

If a particular machine in your shop breaks down a lot, and you are seeing lots of scrap on every job, maybe it is time to look at what is going on. Is there truly a problem with the machine? If so, get it fixed, or move production to another line. Maybe it is a problem with how the machine operator has been trained, or maybe it is due to poor quality materials that are being used as components on a given job. Until you dig in to find the root cause, you can’t fix the problem.  

Optimize Your Manufacturing Today!

Previous Article Tip of the Week: Gain Efficiency & Save Money - Evaluate Your Production Lines
Next Article BPCS/LX TIP OF THE WEEK: INVENTORY TRANSFERS
Print
62618 Rate this article:
No rating

Contact

Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Tips: LN | Baan

Categories