Infor LX & BPCS Manufacturing Tip of the Week: Backward Scheduling

George Moroses 0 28255 Article rating: 5.0

Operations are automatically backward scheduled at shop order release time. The backward scheduling algorithm starts with the shop order due date and schedules each operation based upon the standard move and queue times in the routings and the number of days the job is expected to run at standard. The system calculates and stores the operation scheduled start date. The dates may be modified by the shop order maintenance program. The number of days that a job is expected to run an operation is dependent upon the available capacity for that work center and the total hours scheduled for that operation.

The backward scheduling algorithm also considers...

Infor LN & Baan Finance Tip: How to clear balances on invoices that will be moved to a new company

Kathy Barthelt 0 65436 Article rating: 5.0

To clear out the balances of outstanding invoices that will be added into new companies or moved into new companies, credit notes could be created for them and have them linked to all the invoices of one customer/supplier. 

Another option is to...

Crossroads RMC's support team is friendly, well trained, experienced, and committed to resolving your support & technical issues as quickly & effectively as possible.

Crossroads RMC 0 24782 Article rating: 5.0

How good would you feel if you knew that 30+ years of ERP manufacturing experience was on the other end of the phone when you placed a support call?

That’s what our customers get when they call Crossroads RMC for help.

Crossroads RMC offers a number of services to help you make the most of your Infor ERP investment, regardless of the version of Infor LX, BPCS, Infor LN, Baan, or Infor M3, you are running. Our support team is friendly, well trained, experienced, and committed to resolving your support and technical issues as quickly and effectively as possible. To ensure all your support needs are met, we offer several different methods:

  • TELEPHONE SUPPORT:
    Our phones are answered by live representatives to ensure that you receive prompt, personal, and efficient assistance. These services are available Monday through Friday 8:30 am to 5:00 pm ET. We also offer standby support and after-hour support when requested.
  • ONLINE SUPPORT:
    Online support is available by logging onto your system using a remote connection. With a live connection, our consultants are able to view your system and troubleshoot issues in real-time.
  • REMOTE & ON-SITE CONSULTING:
    Consulting is an excellent option if more in-depth service, training, or troubleshooting is needed. End-User training or group custom training on new features and solutions is also handled effectively using this method of support.
  • BUSINESS ASSESSMENTS:
    Experienced Crossroads RMC Consultants will compare your existing business processes with your existing software and put together a detailed report of their findings. This includes recommendations for improving the day-to-day running of your business while getting the maximum benefit from your software. This also ensures that you are up to date with any features and technologies without adding disruption to your business.

Learn more about our support services>

Infor LN & Baan Tip: Performance Standard Cost

by Infor

Kathy Barthelt 0 63975 Article rating: 5.0

Everything you ever wanted to know about Calculating Standard Cost and Actualizing Standard Cost / Revaluing Inventory (ticpr2210m000 | ticpr2220m000)

Calculating standard cost and re-valuing inventory are important capabilities within your Infor ERP system for a variety of reasons. Sometimes these sessions experience performance issues. Here is a brand new PowerPoint released by Infor to discuss both the functional and technical side of these sessions. Get every last what, where, why, and how answered so that you can improve how these sessions run on your system.

Download Infor PowerPoint>

First3940414244464748Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tip: MPS planned vs. MRP planned

What items should be MPS planned, and what items should be MRP planned…

Master Scheduled Items are those items that are finished goods, or service items, that receive their requirements either specifically from Independent demand, or both Dependent and Independent demand.

  • Independent Demand is demand that cannot be calculated from higher-level demand in the product structure, and therefore must be either a forecast or an actual customer order (Finished Goods or Service parts sold to customers).
  • Dependent demand is derived from higher-level demand in the product structure. Dependent demand includes components, raw materials, and sub-assemblies. (these are not normally Master Scheduled Items).
  • Service Parts may have both independent demand from forecast and/or customer orders, as well as dependent demand from higher-level demand if that item is also used in other sub-assemblies or products.
  • Cumulative Lead Time is a concept used in Master Production Scheduling (MPS) that combines the “fixed” lead time, and the “variable” lead time needed to produce the product. It is the longest path through a given Bill-of-material. Based on the MPS setup options, your ERP will calculate cumulative lead time (also called “the Critical Path”) for you.

Infor LN does not differentiate between the two. Here, it is simply an enterprise planning EP with one set of planned orders. It is possible to set up items and generate orders at plan levels, but not necessary. In theory, you could make plan level 1 similar to MPS items.

Another way of defining independent demand in LN terms is that it is demand not related to other planned items. Dependent demand comes from related planned items above in the BOM structure.

COLT still exists both in purchase and manufactured planned items. It has both non-critical and critical lead times based on components set as critical. Once calculated it can be used to update the order and planning horizons of a plan item.

Relevant Sessions:

In Baan IV
Maintain Item Data tiitem0101m000
Generate MPS timps3201m000
Maintain Master Production Schedule timps3101m000
Display Planned Inventory Movements by Item timrp1510m000
Display Planned MRP Purchase Orders timrp1521m000

In Baan V
Plan Item Data cprpd1500m000
Item Master Plan cprmp2101m000
Time-Phased Overview cprrp0520m000

In Infor LN
Item – Planning cprpd1100m000
Item Master Plan cprmp2101m000 (same as Master MPS above if used)

Previous Article Infor ERP Tip: Is your Infor ERP system up to date with all of the sales tax changes for 2021?
Next Article Infor LN & Baan Tip: Remove Posted Payment/Direct Debit Batches
Print
65639 Rate this article:
3.8
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories