Infor LN & Baan Tip: Defining “Unavailability” in Infor LN

Kathy Barthelt 0 29431 Article rating: 5.0

This topic describes the definition of temporary unavailability for resources in a calendar.

Use one of the following sessions:

  • Recurring unavailability
    For recurring unavailability, such as national holidays, define the recurrence in the Recurrences (tcccp0143m000) session. Add that recurrence to the applicable calendar and...

“Sorry, boss. We can’t help you move the business forward.”

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 17639 Article rating: 5.0

Imagine saying that to your boss, or the president of your company. What would their response be? Do you think they would say, “It’s ok, we can wait to save a ton of money and move us ahead of the competition... No problem... let me know when you have time to work on it.”  Pretty unlikely. Instead, they will want you to...

What you missed: Infor’s vision for the IBM i teams’ future alignment and focus – Register today!

Inforum

George Moroses 0 22696 Article rating: 5.0

What you missed at Inforum

Infor’s vision for the IBM i teams’ future alignment and focus – Register today!

February 8 | 11am CT / 12pm ET

Join this webinar to hear Jay Allison, Director of Sales, share some insight into Infor’s vision for the IBM i teams’ future alignment and focus. Also hear from David Rapacz, Product Manager for Infor LX, on what you may have missed at Inforum as well as some product updates.

Register today via the LX Community calendar.

Infor LN & Baan Tip: Porting Set Issues

Kathy Barthelt 0 60611 Article rating: 5.0

Are you on the latest porting set for your version of Baan or Infor LN?

Here are some issues you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating...

It’s mid-January and IT’S GO TIME!

Infor LX | BPCS | Infor LN | Baan

Crossroads RMC 0 20219 Article rating: 5.0

The calendar is fresh, the resolutions are made and the opportunities are endless!

So, it is time to dive right in and start tackling your to-do’s?

Right??

...Not just yet!

First, you need to take the time to think about your ERP strategy.

What’s an ERP strategy?

Infor LX & BPCS Tip: What is IDF and Why Do I Need It?

George Moroses 0 27894 Article rating: 5.0

The Infor Development Framework (IDF) re-architects the way a user interacts with the application by providing an efficient, task-oriented process to view the application information that is contained within Infor LX. IDF enables users to configure their view of the application data without modifying the core application and its supportability.

The examples below describe how users can configure their display of data and maximize overall productivity:

  • Arrange application information into multiple groupings and sequences that make sense for the job.
  • Hide information that does not apply to a particular job or task.
  • Filter records to show only the information that applies to the job or task that the user is performing.
  • Customize the information for an individual user, for a group of users, or for all users.

To get more details on how IDF can benefit your company, please contact Anthony Etzel today!

Infor LN & Baan | Infor LX & BPCS Tip: Time for the dreaded three words?

Crossroads RMC 0 28877 Article rating: 5.0

Manual     Physical     Inventory

While it may be accurate (and I say MAY), is a Manual Physical Inventory the right way? Best practices would say absolutely not!

The better way is implementing Cycle Counting. Why Cycle Counting instead of a full physical inventory? With a cycle count, the count focuses on a selected range of stock that can be carried out in parallel with a company’s normal operations. Cycle Counts represent a streamlined method of inventory management to ensure less disruption on the business processes associated with receiving, consuming, or dispatching of stock. 

The “freeze” is no longer required, your staff doesn't need to work long hours over the holidays, and you get accurate inventory counts all year long! Crossroads RMC can help you implement Cycle Counting efficiently and painlessly, contact us today to get started. 800.762.2077

Infor LN & Baan Period End & Fiscal Year End Processing Checklist

Kathy Barthelt 0 61369 Article rating: 5.0

Year-end is always a busy time and it is easy to forget things that must be done in your ERP system to close out the year properly and also set you up for a good start to the following year. Here are some things that you should make sure to add to your to-do checklist:

The year-end close process provides an opportunity to:

_____ Remove discontinued items.

_____ Remove sold purchase receipts.

_____ Remove lot attributes for sold lots.

_____ Update standard cost based on current cost field (for environments without Manufacturing only).

Prepare for Year-End Close

_____ Conduct full physical...

First3233343537394041Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for OPERATIONS: Absorbing Cost Items into Projects

Operations: To absorb the cost of cost items into specific projects, you'll need to handle them as customized items. However, cost items cannot directly be defined as customized items. Customized items must be physical, either manufactured or purchased.

That said, it's still possible to absorb cost items into a project, although indirectly. Here's how:

  1. Set Up Ledger Account: First, create a new ledger account in session tfgld0508m000 and set the type to "PCS" (project) in the operations management integrations. This account will be used for matching and approving purchase orders for cost items.

  2. Create and Activate Projects: Ensure that the necessary projects are created and set to active status.

  3. Purchasing Cost Items:

    • If needed, create the cost items.
    • Create a purchase order for the cost items without referencing a project number.
  4. Matching PO to Costs:

    • When matching the purchase orders in session tfacp2107m000, select "Add Costs" from the specific menu on the toolbar (you'll need to be in the matching details to access this).
    • This will open session tfacp1133s000, where you will enter the previously specified ledger account number.
    • Once done, the "PCS Transactions" option on the toolbar becomes available. Selecting this brings up session tipcs3140m000 (General Actual Project Costs).
       
  5. Disbursing Costs to Projects: In session tipcs3140m000, the PO costs for the cost items can be disbursed to any open and active project.

Since these are cost items, they won't go into stock. The key is ensuring that the cost disbursement ("Add Costs") is correctly linked to the appropriate project, giving users visibility of the cost items as general project costs.
 

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Adding a Timestamp to LN Standard Tables
Print
21888 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories