Infor LN & Baan Tip: Separate item codes for incoming & outgoing subassemblies

Kathy Barthelt 0 61990 Article rating: 5.0

You may be wondering if it's necessary to have separate item codes for incoming and outgoing subassemblies.

No, it is not necessary to have separate item codes for incoming and outgoing subassemblies, but it is recommended. In theory, you could have only one item code with the description subassembly and use the same item code for the outgoing subassembly and for the incoming subassembly. However, when monitoring inventory movements and financial integration transactions, it will be difficult to understand the process. Also, the costing logic is much clearer when different item codes for the incoming and outgoing subassemblies are used. Because of this, it is advised to use a different item code for the outgoing subassembly and a different item code for the incoming subassembly.

Infor LX & BPCS Tip: Changing an item to non-inventory

George Moroses 0 24196 Article rating: 5.0

When an attempt is made to change an item’s type to a non-inventory item from any other value, a new validation is performed to determine if the item has any inventory on hand and, if so, prevents changing the item’s type.

This enhancement available in LX 8.4 prevents LX from showing an on-hand inventory balance for a non-inventory item.

The programs or areas impacted include:

  • Facility/Planning Data Maintenance, MRP140D2
  • IDF Enterprise Item

To get this enhancement, request and apply MR 80120.

Top 10 Things (you might not know) About Crossroads RMC

Crossroads RMC 0 15272 Article rating: 5.0


10.  Crossroads RMC has been in business since 1984 & has been an  partner since 1991
 

 9. Crossroads RMC offers functional & technical training on all versions of Infor LX, BPCS, Infor LN, and Baan and will completely tailor the training to your specific needs. 🤝🏽

 8.  Our consultants have over 1,000 years of combined experience working with manufacturers just like you! 🤓

 7.

 6.

 5.

 4.

 3.

 2.

 1.

DATA: See it. Understand it. Discuss it.

Crossroads RMC 0 15432 Article rating: 5.0

We’ve all heard author and management consultant Peter Drucker’s famous quote “If you can’t measure it, you can’t manage it.”  

What’s the right way to manage “It” though? Is it enough to put the data in the hands of the responsible manager and wait for change to occur? Does the manager have a pulse on everything that went into those numbers?

Your numbers tell a story, but there is a lot of...

Infor LX & BPCS Tip: Tracking Financial Journal Entries

George Moroses 0 21143 Article rating: 5.0

An 8.4.1 EGL audit enhancement now provides visibility to who and when a financial journal was last maintained and to who and when the journal was approved. The enhancement provides audit attributes for last maintain user, date, time and approval user, date time on the Financial Journal Entry and Financial Journal Entry Lines.  

The programs or areas impacted include:

First2324252628303132Last

Tips:  LX | BPCS | M3

Anthony Etzel

Infor LX & BPCS Tip of the Week: ION Tip – Pausing Receiving and Sending of Messages

If it is necessary to pause sending and receiving of BOD messages on your IBM i during your month-end process, it is best practice for the document flows that point to the IBM i to guarantee delivery of BOD messages. Once the month-end process has been completed, you will need to Resume the ‘Receiving’ and ‘Sending’ Active Connection Points so your documents will continue to process.

Pausing Sending messages

To pause sending messages to ION:

  1. Select Connect > Active Connection Points.
  2. Select the connection point that must be paused for sending messages.
  3. In the Sending Paused column, click Pause. The page is automatically refreshed and the Sending Paused checkbox is selected. A Resume button becomes available. 

Sending of messages by this connection point is stopped. No new messages are picked up from the source application's outbox. The connection point still processes messages that were already picked up from the outbox. This action can take some time in the background even though the sending status of the connection point is already changed to Paused. Any new message, that was published from an application after the sending of its connection point is paused, has not yet entered ION and is not yet available in ION OneView.

Pausing Receiving messages

To pause receiving messages from ION:

  1. Select Connect > Active Connection Points.
  2. Select the connection point that must be paused for receiving messages.
  3. In the Receiving Paused column, click Pause. The page is automatically refreshed and the Receiving Paused checkbox is selected. A Resume button becomes available.

Receiving messages by the connection point is paused.  No new messages are delivered to the destination application's inbox. All new incoming messages to this application are parked in its incoming pending messages queue inside ION.  The connection point still processes messages that were already picked up from the incoming pending messages queue. This action may take some time in the background even though the receiving status of the connection point is already changed to Paused.

Resuming sending / receiving messages

To resume sending or receiving messages from ION:

  1. Select Connect > Active Connection Points.
  2. Select the connection point that must be resumed for message processing.
  3. Select one of these actions:
    1. To resume the pickup of messages from an application outbox, click Resume in the Sending Paused column.
    2. To resume the delivery of messages to an application inbox, click Resume in the Receiving Paused column.

The page is automatically refreshed and, depending on the selected action, the Sending Paused checkbox or the Receiving Paused checkbox is cleared. A Pause button is now available.

Previous Article Infor LX & BPCS Tip of the Week: LX 8.4 Database
Next Article Infor LX / BPCS Tip of the Week: Pre-assigned lot numbers for multi-level SO release
Print
71734 Rate this article:
5.0

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.