Baan/LN Tip of the Week: Aborted Finalization Run

Kathy Barthelt 0 80823 Article rating: No rating
When a finalization run is aborted and in the batches selected for this finalization run are transaction types having the update mode finalization, you must use the Restart Finalization Run session. This session can be found in the Transaction Processing menu of the General Ledger Module of the Finance Package.

BPCS/LX Tip of the Week: SFC600

Anthony Etzel 0 83936 Article rating: No rating
In addition to SFC650, this ERPLX program is also used to capture and post shop floor information.

The key difference between the two is that SFC600 only captures Labor (run time) reporting, machine time, downtime and indirect time.

If you use SFC600, then all shop order material receipts and issues would be captured using INV500.

Both Inventory and Shop Floor Transaction entry is keyboard dependent, unless you incorporate an automated method like an MES solution to capture the data.

BPCS/LX Tip of the Week: Downtime Reasons

Anthony Etzel 0 82435 Article rating: No rating

Using SFC600 to enter downtime.

You are tracking downtime and using SFC600 to enter the downtime, but you don’t know where to go to setup downtime reasons. You can set up the downtime reason codes in the INV application by selecting the reason code maintenance program INV140D1.

Once you are in the reason code maintenance program, position to the transaction effect code “D”. Using the transaction effect code “D” you can now setup as many downtime reason codes as needed. The reason code field is alpha numeric, so be creative with your reason code assignments.

Baan/LN Tip of the Week: Restricted User Access

Kathy Barthelt 0 77636 Article rating: No rating
Administrators are able to restrict access in Baan in several ways – including Companies, Packages, Modules, Sessions, and Tables – using the Authorization capabilities of the system.

In Baan IV, access can be given or denied on a user by user basis.

In Baan V and LN, the Authorization Management System can provide or deny access based upon roles to which users are assigned.

BPCS/LX Tip of the Week: Work Center - Cells

Anthony Etzel 0 63852 Article rating: No rating
The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

Baan/LN Tip of the Week: Closed, Final Closed, Provisional Close – What’s The Difference?

Kathy Barthelt 0 82955 Article rating: No rating

Fiscal, Reporting and Tax Periods can have status Open, Closed or Final Closed. If a period is Closed or Final Closed, you cannot post entries to those periods. If a period is Closed, you can re-set it to Open and post entries. If a period is Final Closed, you cannot post and you cannot set it back to Closed or Open.

A Provisional Close is run at year-end to bring the balances forward for the new year without having to close the previous year. A Provisional Close can be run as many times as you like. After a Final Close, a Provisional Close cannot be run.

The Provisional Close allows you to continue into the new year with all financial reporting and not have to rush with the Final Close until all adjusting entries are made and any final signoffs have been completed.

Baan/LN Tip of the Week: Product Families

Kathy Barthelt 0 80821 Article rating: No rating

In Baan IVC, plan items on the lowest plan level were automatically actual items (not product families). All plan items on higher plan levels were product families.

The relationship between a product family and items on lower plan levels was defined in a planning bill of material.

In Infor LN, every family item must be defined in the Item Base Data module. A family item can exist on any plan level. The relationship between a family item and items on lower plan levels is defined in aggregation relationships.

Aggregation relationships in Infor LN are much more flexible than the planning bills of material in Baan IV. For example, users can define aggregation relationships between items on the same plan level.

BPCS/LX Tip of the Week: Create the Master Schedule

Anthony Etzel 0 82419 Article rating: No rating

In the master schedule creation, you have the flexibility to enter a planning start date, or default to the facility planning start date. Infor LX uses the planning date to plan both orders with forecasts and customer orders as demand.You can create your master schedule from the Master Production Scheduling module (MPS).

First131132133134135137139140

Tips:  LX | BPCS | M3

Tips: LN | Baan

Crossroads RMC

Unlocking Success: The Power of Staff Augmentation with Crossroads RMC

Infor LX, BPCS, Infor M3, Infor LN & Baan

Consider this...

Your team is currently engaged in a critical project for your top client. However, to ensure the project's timely completion and high customer satisfaction, it's imperative to expand your team. You're aware that the recruitment process is time-consuming, and finding highly qualified individuals who don't require extensive training, especially in your ERP system and your specific business, is a challenging task.

Or perhaps this situation sounds familiar...

Your ERP system is running sluggishly, and you're aware that there are updates available that could enhance system performance. Unfortunately, your IT specialist is currently occupied with other tasks, and there's uncertainty about when the upgrade can be executed.

Both of these scenarios reflect the challenges businesses face in our era of rapid technological advancement. To maintain competitiveness, it's essential to meet client demands and ensure the smooth operation of internal systems, preventing any hindrances to current production. The hard reality is that your success hinges on having expert staff who can make an immediate, positive impact on your business.

So, how can you consistently maintain the right team size and composition to address contemporary challenges when hiring new personnel is a costly, protracted process?

The solution is staff augmentation. Whether you need to tackle immediate challenges or plan for the future, Crossroads RMC has got you covered. Our team is equipped to deliver top-tier ERP consulting and round-the-clock support services, ensuring your systems operate smoothly and your staff remains at peak productivity.

The Crossroads team offers on-demand resources in various areas, including:

  • Manufacturing Planning
  • Warehousing
  • Finance
  • Distribution
  • Customization
  • Integration
  • Data Migration
  • Upgrades & Implementations
  • ION / Infor OS Consulting
  • Report Development

And much more!

Reach out to Crossroads RMC today to explore how our team can assist your team in overcoming your most significant business challenges.

Contact Crossroads RMC today to discuss how our team can help your team solve your biggest business challenges. 800-762-2077

Learn more about our support services for:
Infor LN>
Baan>
Infor LX>
BPCS>

Print
16117 Rate this article:
5.0
Crossroads RMC

Crossroads RMCCrossroads RMC

Other posts by Crossroads RMC

Contact author

x

Categories