BPCS/LX Tip of the Week: Indirect Labor Reporting

Anthony Etzel 0 84176 Article rating: No rating
In the Shop Floor Control Module, you have the ability to key in both direct labor and indirect labor. However you want to establish specific types (reasons) for the indirect labor. The SFC600 labor entry program shows a reason code field, but it is designed for reject quantity and machine downtime reasons, not indirect labor reasons.

There is a way around this. With an MES solution you have the ability to setup and report indirect time against a specific reason code.

Baan/LN Tip of the Week: Configuring Items in Infor LN

Kathy Barthelt 0 95542 Article rating: No rating

In Infor LN, the configuration of a generic item not always results into a customized item. Configured items can now be customized items as well as standard items. If users configure items without PCS projects, standard items are generated instead of customized items.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 84474 Article rating: No rating
In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: Shop Order Status

Anthony Etzel 0 88042 Article rating: No rating

You can see the status of the Shop Order when using SFC300 Shop Order Inquiry. You want to be sure that your shop orders are at the correct status in order to report against them.

The following are the shop order status codes:

04 = The Shop order has been entered.

05 = The Shop order has been released and printed.

14 = The Shop order has been released, but not printed. If a shop order is at this status, you have released it and it is not printed due to a system failure, or the order has been put on hold.

XX = The Shop order is closed.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 91184 Article rating: 4.0
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

Baan/LN Tip of the Week: What could go wrong with GRINYA?

Kathy Barthelt 0 86129 Article rating: No rating
One common GRINYA issue would be incorrectly entered Integration Setups.

Check the Baan/LN manual for recommended Integration setups. If such a mistake were to occur, it is important to know for what period of time the Integration was in error. It is recommended that the Integrations Setup tables be audited either through Baan or Database Auditing. Corrections can be quickly calculated when an exact timeframe can be determined.

Baan/LN Tip of the Week: Differentiating An Item By Supplier - LN

Kathy Barthelt 0 88785 Article rating: No rating

In LN, you can differentiate between items at various suppliers:

  • Locations (warehouses),
  • Purpose (planning, purchase)
  • Origin (supplier, warehouse)

Example

An item is supplied by two different suppliers. Supplier A ships in lots of 100 pieces due to how the item is packed. Supplier B ships the goods in units of 60 pieces.

You can define specific parameters for each supplier. The following sessions can be used to define these characteristics:
 
  • Items - Planning (cprpd1100m000)
  • Check Item Data by Warehouse (whwmd2210m000)
  • Item Supplier Plan (cpvmi0530m000)
These sessions define entities that have an n-to-1 relationship with the general item data.

 

BPCS/LX Tip of the Week: Inventory Control

Anthony Etzel 0 95206 Article rating: No rating

In Infor LX you need to determine how inventory will be moved in and out of warehouse storage locations, and which of the following transactions to use for inventory control:


  • A transfer transaction can be used to move inventory from one warehouse location to another warehouse location.
  • A production receipt transaction is used to add inventory to a warehouse location.
  • A material issue or backflush is used to reduce inventory from a warehouse location.
First130131132133135137138139Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Are ERP System Blockages Thwarting Your Progress?

Are ERP System Blockages Thwarting Your Progress?

After a week of blocking the Suez Canal, the now-famous cargo ship, Ever Given has been freed from the 27,000 cubic meters of sand and mud that were surrounding the ship. Supply chains are flowing again. I for one am very glad to hear that the ship has been freed since coffee, toilet paper and a whole host of other items were being held up! In all seriousness, it was and is a crisis that will have ripple effects on the global economy.

As I often do, I started to relate this crisis to the world of ERP that we live in. Although we are not responsible for dealing with a situation like what happened in the Suez Canal, we all deal with problems in our jobs every day. Some of these problems are small, and some are not so small. Some problems are caused by human error, some by prevailing winds that blow us in a particular direction, and some by circumstances out of our control. It is what we do about the problems we encounter that make all the difference. We could bury our heads and hope the problems somehow go away on their own, or we can take action and do something to bring about the change necessary to get past the blockage.

I see “blockages” every day in working with my customers. Sometimes it is a lack of understanding of best practices in a given department, or a reliance on tribal knowledge that determines how and why something is done in the system, or inefficient manual processes destroying a company’s efficiency, or hundreds (or thousands) of customizations standing in the way of an upgrade, or employees labeling an ERP system as “no longer a fit” when their company is only using 10% of the available functionality in the system.

So, maybe today we could focus on what it would take to remove the “blockage” that we have in our way. What benefits could we realize if we worked together to bring about incremental change? Could we actually get that upgrade done? Could we start operating based on industry-leading best practices? Could we increase our market share? Could we decrease our costs and boost our revenue? All of this is possible.

Contact me today so that we can begin to work together to solve the problems that stand in the way of your progress.

solutions@crossroadsrmc.com or 800.762.2077

Print
29700 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories