Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 88617 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In ERP LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period. For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

Crossroads RMC to Exhibit at COMMON Conference, April 26-29

Crossroads RMC 0 35677 Article rating: No rating

The Annual Meeting is COMMON’s largest educational event of the year, with four full days of in-depth IBM i, AIX, and Linux-related education that includes all-day pre-conference workshops, open labs and a wide variety of regular-length sessions. It is the annual meeting of the COMMON membership and the largest gathering of the Power Systems user community. Come see us in Booth 316.

BPCS/LX Tip of the Week: Batch Allocation

Anthony Etzel 0 74108 Article rating: 5.0

Thinking of moving from your old BPCS Version to LX?

There are numerous reasons to consider moving to Infor LX. It is a proven migration and it is easy to get there.

An area of interest may be allocations. Allocations can be difficult to manage, but with Infor LX, there is a new selection of ranges for Batch Allocations:

    • Sold To Customer
    • Ship To Number
    • Order Class
    • Order Number
    • Item Number
    • Request Date
    • Schedule Date

Baan/LN Tip of the Week: Safety Time

Kathy Barthelt 0 110202 Article rating: No rating

You can add safety time in the item master for the item. This will add the number of days safety time to the order lead time thus bringing the order in x number of days early. (x is the safety time).

The safety time is on form 4 of the item master in Baan IV and in Item Ordering Data – Generation I tab in Baan V and LN.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 104148 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

 

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: Product Routing

Anthony Etzel 0 75001 Article rating: No rating

Defining the Product Routing first requires the items to be setup in the Item Master file. Other master files also need to be defined prior to creating the routing.
These include:

  • The Facility defined with a SYS program
  • The Warehouses defined with an INV program
  • Locations defined with an INV program
  • The Machines (required if using capacity planning or an MES interface) defined with an MDM program

After the above data is set up, the Department file and Work Center files can be setup in MDM. Now you are ready to define a product route.

Baan/LN Tip of the Week: Month End – Miscellaneous To-Do’s

Kathy Barthelt 0 106206 Article rating: No rating
  • Print Sales Order History Information
    • all invoices processed through sales
  • Check Inventory Valuation
    • this should tie out to your inventory accounts
  • Print Integration Information
    • see all postings from WIP to finished goods
  • Print G/L Transaction Information
    • print specific transaction types for any GL account
  • Print Lot Control Information
    • will show where serial numbers were used
First127128129130132134135136Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

The Best Baan | Infor LN Manufacturing Reports to Analyze Company Performance

You know what ERP data you need to analyze your company’s production health, but sometimes it is a struggle to get that data in a format that is meaningful. Here are some reports in Baan & Infor LN which you may find useful.

As is the case with most ERP reports, with each version progression from the earliest versions of Baan to the latest version of Infor LN, there are improvements in selection criteria and report content. Some may require some setup and others may require some formatting if you would like to export them to Excel. Contact me if you have questions or need assistance.

BAAN & LN MANUFACTURING:

Baan IV

  • Print Actual Cost by Production Order ticst0401m000
    • This report can be run at any time in the production order’s life to show how hours-spent and material-used compare between estimated and actual usage.
       
  • Print Work Center Utilization By Week tiscf1402m000
    • This report shows capacity issues at work centers/machines which help identify production bottlenecks.


Baan V

  • Print Estimated vs Actual Material Costs ticst0401m000
    • This report can be run at any time in the production order’s life to show how actual material-used compares to estimated usage.
       
  • Print Estimated vs Actual Hour Costs ticst0402m000
    • This report can be run at any time in the production order’s life to show how actual hours-spent compares estimated hours.
       
  • Print Work Center Utilization By Week tiscf1402m000
    • This report shows capacity issues at work centers/machines which help identify production bottlenecks.


Infor LN

  • Print Estimated vs Actual Material Costs ticst0401m000
    • This report can be run at any time in the production order’s life to show how actual material-used compares to estimated usage.
       
  • Print Estimated vs Actual Hour Costs ticst0402m000
    • This report can be run at any time in the production order’s life to show how actual hours-spent compares estimated hours.
       
  • Utilization report from– Print Resource Order Plan cprrp0430m000
    • This report from Enterprise Planning will show all orders from planning and production. By incorporating both order types, capacity issues can be seen short range where planning has determined that new orders are needed, as well as long range where planners may find opportunities to shift work or even to plan machine maintenance.

Previous Article The Best Baan IV | Baan V | Infor LN Financial Reports to Analyze Company Performance
Next Article Infor LN & Baan Tip of the Week: Reports to Analyze Company Performance
Print
72219 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories