Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 114770 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 71378 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

PDIC Goes Live with Crossroads MES

Anthony Etzel 0 52675 Article rating: 5.0

PDIC, a leading producer of wire products, went live with the Crossroads MES solution on June 30th,2014. PDIC needed a better way to deploy and report shop floor information to BPCS 6.02. Their goal was to eliminate all their manual reporting and position themselves to take advantage of the Crossroads Dashboards.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 125905 Article rating: 5.0

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Establish Costing For Purchased Items

Anthony Etzel 0 85959 Article rating: No rating

How Does Infor LX Establish Costing For Purchased Items?

In LX, you will establish a standard cost (you define the standard) that LX will use for the purchase items. You also need to establish in LX the Cost Type, the Cost Bucket, and the Cost Set needed for cost accounting.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 78054 Article rating: No rating

How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Crossroads MES Version 11 Released

Anthony Etzel 0 52702 Article rating: No rating

Crossroads MES Version 11 was rolled out in March, 2014. Some of the new features include a new GUI interface, improved End of Shift review functions, pre-formatted production label printing, and an electronic shop packet on the factory worker Job In screen.

Crossroads MES Released for Tablet

Anthony Etzel 0 49222 Article rating: 3.7

Crossroads RMC announces that the Crossroads MES solution is now compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

First121122123124125126127128130

Tips:  LX | BPCS | M3

Tips: LN | Baan

Crossroads RMC is proud to introduce our new Production Order Variance Reports package for Infor LN

The package includes numerous reports and sessions to view the variances in a way that Finance can identify problems based on the Finance Integration Transactions in the General Ledger.

There are a few main sessions with many detailed sessions linked to them. The reports can be run from the main Print Production Order Variance Reports or in the individual detailed session.

Sessions included in the report package:

1. Print Finalized Trans – Variance Reports.

a. Financial Trans. by L/Acct – Prod. Order Variances - Recap

b. Financial Trans. by L/Acct – Prod. Order Variances – Details

2. Update Production Order Variances (updates special variance table).

3. Production Order Variance Overview – Main view

a. Production Order Variance Details

b. Price Variance Details – Material Variances

c. Price Variance Details – Operation Variances

d. Efficiency Variance Details – Material Variances

e. Efficiency Variance Details – Operation Variances

f. Efficiency Variance Details – Reject Variances

g. ACO Variance Details – Reject Variances

h. Accept Production Order Variances

i. Un-accept Production Order Variances

j. Finally Accept Production Order Variances

4. Print Production Order Variance Reports:

a. Production Order Variance – Overview

b. Production Order Price Variance – Material Revaluation

c. Production Order Price Variance – Operation Revaluation

d. Production Order Efficiency Variance – Material

e. Production Order Efficiency Variance – Operation

f. Production Order Efficiency Variance – Rejects

g. Production Order ACO Variance – Rejects-Additional Costs

5. Delete Production Order Variances (used to redo a month)

Contact Kathy Barthelt to learn more.

Previous Article About 65% of the world’s population are visual learners. This extends into the ERP software realm, too.
Next Article Infor LN & Baan Tip of the Week: Customer Defined Fields
Print
71703 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories