BPCS/LX Tip of the Week: Top Down Shop Order Schedule

Anthony Etzel 0 77956 Article rating: No rating

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Baan/LN Tip of the Week: Back Dating Cycling Counting Orders

Kathy Barthelt 0 106384 Article rating: No rating

Cycle Count Orders cannot be directly “back dated” in Baan IV, Baan V or LN, however, there are some work-arounds.

In Baan IV you can do an inventory adjustment and back date. Just set all dates on the adjustment to the date you want and Baan will post the adjustment in that period.

In LN you can do a Cycle Count/ Adjustment and again back date and Baan will post to that period.

 

Unfortunately, there is no work-around for Baan V.

BPCS/LX Tip of the Day: Inventory Management

Anthony Etzel 0 75924 Article rating: No rating

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 

Baan/LN Tip of the Day: Chart of Accounts

Kathy Barthelt 0 109724 Article rating: No rating

Zero sublevel accounts are posting level accounts. All others are parent accounts. Once the balances have been updated in the child ledger accounts, the parents are automatically updated.

Inquiries and reports can be printed or displayed either by child accounts or by parent accounts. On line drill-down is possible from either child or parent.

BPCS/LX Tip of the Day: Cycle Counting Part 2

Anthony Etzel 0 76990 Article rating: No rating

Understanding: The Cycle Count Alternative

The best way to cycle count is to count the same number of items each day and at the same time each day. The goal is to count your “A” items 4 times a year. The “A” items should be those item that are about 80% of the total inventory value and 20% of the total items. Consider creating your own cycle count schedule then instead of using the cycle count transaction, use the inventory adjustment transaction. The item balance is changed at the time the transaction is keyed. The transaction list can be used for the reconciliation process.

Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 105876 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 84056 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 131972 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.
First124125126127129131132133Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

Kathy Barthelt

Tip of the Week: 10 Ways to Succeed at an OEE Project Where 90% Fail

  1. Collect the requirements. Learn from everyone with the intent of developing a phased approach to implementing on your shop floor with OEE being Phase 1. 
  2. Create your list. Capture all of required functions, taking into account what the “output” of the system will be. What does the plant manager need to see in real-time? What KPI’s does each line need displayed in real-time? What reports are required?
  3. Insist Upon Real-time. In the moment data for the right OEE is the right approach. If it’s possible, collect the data automatically. Remember that real-time feedback to line operators results in an automatic increase in OEE.
  4. Evaluate your lines. Focus where production counts can be monitored automatically. If the data is in your PLC’s, can you get it out? OPC communication is the right way to go here. If not, the approach is to install a new dedicated PLC with sensors installed on each line.
  5. Find Your Data Points. If automatic production monitoring is not applicable, what will be your collection points and how will you collect the data?
  6. Calculate the Load. Determine how to load the “job” you’re reporting on into the OEE system. This will typically be the order/operation or the product from the ERP.
  7. Recognize Great Data. Do not accept “manual collection of data” as a viable approach because it produces false results and is labor-intensive.
  8. Be Tough. Evaluate systems based on OEE specificity to start and expandability to future phase functions as determined by your requirements. Plan to justify the OEE purchase on its own merits.
  9. Go Easy. Make sure the system is easy to implement. Software installation and configuration should take no more than 2 weeks.
  10. Be Simple. Put together a detailed but simple project plan indicating who will do what, how long it will take, and how you will monitor progress.
Read Full Article

Optimize Your Manufacturing Today!

Previous Article Baan/LN Tip of the Week: 5 Ways to Motivate Your Employees
Next Article Tip of the Week: Gain Efficiency & Save Money - Evaluate Your Production Lines
Print
110087 Rate this article:
No rating
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories