Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 104959 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 83053 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 111165 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 82377 Article rating: No rating
For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

BPCS/LX Tip of the Week: The Item Master Requirements Code

Anthony Etzel 0 77527 Article rating: No rating

In the Item Master File, the requirements code is used to specify the type of demand for the item. Planned order requirements are determined from the type of demand. If the requirements code is left blank, the planning systems treat the item as a sum code (3).
 

Other options for the field are:


1 = Dependent demand that is indirectly generated from the parent item requirements.

2 = Independent demand generated from customer orders and forecasts.

3 = The Sum of both independent and dependent demand.

Grindmaster Cecilware Selects Crossroads RMC For Baan IV / Davisware Integration

Crossroads RMC 0 41372 Article rating: No rating

Grindmaster Cecilware, a leader in the development of products for the food and beverage industry, has selected Crossroads RMC to integrate their Baan IV system to Davisware Global Warranty. Davisware is an electronic customizable online solution that fits almost any warranty process. Grindmaster’s customers will be able to access the Davisware software online and process warranty claims which will then automatically feed back into the Baan IV system for further review and processing. The integration is expected to go live in Q1 of 2015.

First122123124125127129130131Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 3

Understanding: The quantities required, finished and remaining at the operation and in total for the Shop Order

The shop order may require 1,000 pieces but only 950 are reported as finished in total for the shop order. The quantity required is what is planned on the SO and it may be a higher number than what is finished, factoring in that there can be scrap. If a 1,000 pieces are required to be produced, and there is always is scrap of 10 pieces, then plan for scheduling a quantity of 1,010.

The quantity finished for the end item is what is reported in the inventory application with a production order receipt transaction. At the operation level, if the quantity is reported at the operation, there will be a value in the PCS Complete field on the operation detail screen showing the pieces completed through that operation.

If you want to get a handle on the difference between the required quantity and the finished quantity, you may want to look into reporting quantities at the operation level as well as examining how scrap is controlled and reported.

Previous Article BPCS/LX Tip of the Week: Getting the Most Out of the Shop Order Inquiry Program – Part 2
Next Article BPCS/LX Tip of the Week: Understanding What Goes On Out On The Factory Floor – Part 4
Print
57300 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

Use this session to to define which fields must be audited, and when they must be audited.

Note: 

  • It is not required to define the fields that must be audited. Only if not all fields in a table must be audited, you must specify the fields that must be audited. You can only specify fields for a table for which you selected Specified in the Field Selection field of the Audit Tables by Profile (ttaud3120m000) session. If you selected All in that field, all fields in the table are audited, and no fields can be specified.

  • For a detailed explanation of the relation between audit type and field specification, refer to the section How to determine the net result of the audit configuration in the Audit Configuration Management topic.

  • The audit functionality uses the positive approach, which means that you can only specify which tables and fields must be audited, but not which tables and fields must not be audited. Therefore, through the appropriate menu, commands are available to load all (key) fields. You can then delete the fields you do not require.

Categories