Industry News: Technology - The Secret Life of the American Factory

Crossroads RMC 0 43693 Article rating: No rating

New Data: New Fruit…that’s the promise of finding new data sitting right there under your nose on the factory floor.

Doug Woods, president of the Association for Manufacturing Technology and MTConnect champion says it this way:
"At the end of the day," he explains, "after you've invested in hardware and machines, at some point it all comes down to how do you wring the maximum amount of productivity out of them? How do you get the ultimate efficiency out of the facility?" The only way to be confident you're doing that, he says, is to really understand what is going on with all of the equipment in the factory all of the time. And that, he says, comes down to having "really good data." 

Read Full Article>

Discover How Crossroads RMC can meet this need with Analytics Dashboard.

Baan/LN Tip of the Week: Project Templates

Kathy Barthelt 0 83303 Article rating: No rating

Project templates are useful because you can specify all of the information that you would normally want to include when creating a new project such as project structure, budget, and so on.

In Baan IV/V, project templates do not exist, but you can set up a project template by creating a regular project, and setting the status to simulated or free. This is done so that the project does not create plans. Under this scenario, you can easily copy one project to another.

In LN, when you create a new project, a template can be used as the starting point. This is similar to copying a normal project, but unlike normal projects, no costs or revenues can be posted on a template.

BPCS/LX Tip of the Week: Work Center - Cells

Anthony Etzel 0 86222 Article rating: No rating
The LMP module (Lean Manufacturing Process) uses work centers but refers to them as production cells.

A cell is one or more work centers that produces an end item. So when a company decides to adopt the lean manufacturing philosophy, the concept of work centers takes on a new meaning.

In lean terms, the work center, or group of work centers, becomes a production cell. In other words, a mini-factory producing end items with similar characteristics.

BPCS/LX Tip of the Week: The Machine Master Part 2

Anthony Etzel 0 83164 Article rating: No rating
Understanding:

The Machine Master File

Do your machines have a fixed asset tag? The machine master file has a field called Fixed Asset.

BPCS does not use this field, so you can use this field for anything. You can record your fixed asset tag in this field and use the effective date. You can create a custom fixed asset list by using a DFU or Query program.

Baan/LN Tip of the Week: Business Partner Structures

Kathy Barthelt 0 85749 Article rating: No rating

In ERP LN, users can define a distributed business partner organization by defining parent business partners to link the business partners with different roles.

In Baan IV, users can define a distributed business partner organization in the Maintain Concern Structure of Trade Relations (tccom3101m000) session.

Harsco Rail Goes Live With the RMC3 Data Collection Solution

Crossroads RMC 0 36299 Article rating: No rating

Harsco Rail, an industry leader in the railway track maintenance, has completed the first phase of their implementation of the Crossroads RMC Data Collection Solution for Baan V. The initial implementation included receiving and putaway. Harsco’s data collection project manager reports, “When I ask them (the users) how it’s going, they smile. I have had nothing but very positive feedback. It’s been very uplifting for me to work on this project and have it so well received.” The next phase of the implementation will include Report Operations Complete, Inventory Transfers, and Stock Inquiry.

Baan/LN Tip of the Week: Tax Exemption Certificates

Kathy Barthelt 0 82915 Article rating: No rating

In Baan IV, tax exemption processing is supported only on sales orders for non-tax provider users.

In Infor LN, tax exemption certificate processing is also performed for purchase orders, and for sales orders if users use a tax provider.

Users can define tax-exemption certificates in the following sessions:

  • Tax Exemptions for Sales (tcmcs1142m000)
  • Tax Exemptions for Purchasing (tcmcs1560m000)
  • Register Warehouse for Tax Exemptions (tcmcs1561m000)

 

BPCS/LX Tip of the Week: The Machine Master Part 1

Anthony Etzel 0 82152 Article rating: No rating
Understanding:

The Machine Master File


Machines are associated with a work center. For example, in the work center you may have multiple machines and each machine can have a unique machine ID. If there are several machines that perform the same function, they may operate at different speeds and efficiencies. Setting up the machine master can be a benefit for planning capacity and shop order throughput.
First121122123124126128129130

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

BPCS/LX Tip of the Week: Understanding What Goes On – Out on the Factory Floor

Ok… so you want to know the status of a specific shop order that was released two days ago.

What do you do?

It’s a sure bet that you have a manager, supervisor, or planner who can walk the floor and find the order at whatever work center it happens to be at. He/she can then answer “what operations have been completed and how many were completed?” All this requires leg work, and of course, a fair amount of time.

Now, if you have setup your BPCS master files properly, and you report transaction activity, you should be able to get those shop order statuses much faster using the SFC300 Shop Order Inquiry Screen.

At your fingertips you can see:

  • Release date & due date
  • How many hours remain in total and at each operation
  • The quantity required, what was finished and the remaining quantity
  • What components (materials) have been issued

Pretty basic information, right? Are you getting what you need to know? If not, then you may want to reexamine how your BPCS files are setup and what transactions along with their frequency are captured.

Optimize Your Manufacturing Today!

Previous Article BPCS/LX Tip of the Week: Role-Based Security
Next Article BPCS/LX Tip of the Week: Inventory Transaction Post to G/L by Cost Type
Print
28515 Rate this article:
No rating

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.

Categories