BPCS/LX Tip of the Week: Top Down Shop Order Schedule

Anthony Etzel 0 75472 Article rating: No rating

In ERP LX, this function is called Backward Scheduling. This is a simple, easy way to create and release shop orders associated with the end item.

The result is a shop calendar with the associated order start dates. Setting up ERP LX properly with correct Queue Times, Setup and Run Times, along with Move Times, will result in accurate shop order start dates.

Baan/LN Tip of the Week: Back Dating Cycling Counting Orders

Kathy Barthelt 0 102992 Article rating: No rating

Cycle Count Orders cannot be directly “back dated” in Baan IV, Baan V or LN, however, there are some work-arounds.

In Baan IV you can do an inventory adjustment and back date. Just set all dates on the adjustment to the date you want and Baan will post the adjustment in that period.

In LN you can do a Cycle Count/ Adjustment and again back date and Baan will post to that period.

 

Unfortunately, there is no work-around for Baan V.

BPCS/LX Tip of the Day: Inventory Management

Anthony Etzel 0 73428 Article rating: No rating

Establishing the Quantity On-Hand and the Quantity Available.

LX maintains buckets for information associated with the following inventory transactions for each item:

  • Opening Balance
  • Issues
  • Receipts
  • Adjustments
  • Allocations for the Customer
  • Allocations for Manufacturing


The on hand quantity does not include any allocations. To arrive at the on hand quantity, start with the opening balance, less any issues, plus any receipts, then add or subtract any adjustments. Available inventory is the on-hand less any allocations.

 

 

Baan/LN Tip of the Day: Chart of Accounts

Kathy Barthelt 0 106658 Article rating: No rating

Zero sublevel accounts are posting level accounts. All others are parent accounts. Once the balances have been updated in the child ledger accounts, the parents are automatically updated.

Inquiries and reports can be printed or displayed either by child accounts or by parent accounts. On line drill-down is possible from either child or parent.

BPCS/LX Tip of the Day: Cycle Counting Part 2

Anthony Etzel 0 75173 Article rating: No rating

Understanding: The Cycle Count Alternative

The best way to cycle count is to count the same number of items each day and at the same time each day. The goal is to count your “A” items 4 times a year. The “A” items should be those item that are about 80% of the total inventory value and 20% of the total items. Consider creating your own cycle count schedule then instead of using the cycle count transaction, use the inventory adjustment transaction. The item balance is changed at the time the transaction is keyed. The transaction list can be used for the reconciliation process.

Baan/LN Tip of the Day: Company Calendar

Kathy Barthelt 0 103457 Article rating: 5.0

Baan uses the company calendar in the following modules to determine the start and end dates for planned orders:

  • Master Production Scheduling
  • Material Requirements Planning
  • Capacity Requirements Planning
    (All three combined in a single planning module for Baan V and LN)
  • Shop Floor Control

The calendar provides the valid working days, number of shifts per day and the number of hours in a day.

Baan allows for a single calendar for the whole company or for a calendar for each work center.

BPCS/LX Tip of the Week: Cycle Counting Part 1

Anthony Etzel 0 82007 Article rating: No rating

Understanding: The Cycle Count Transaction

If you rely on BPCS to provide you with a cycle count list, the number of items could vary from day to day from a few items to count, to several. So the person doing the cycle counting may spend a few minutes to a few hours counting items. After the cycle count is complete, the balances are not changed until the reconciliation is complete. This process could take some time before the balances are changed.

The cycle count transaction process is similar to the physical inventory transaction process.

Baan/LN Tip of the Week: GRINYA

Kathy Barthelt 0 109444 Article rating: 3.0
GRINYA is one of the more complex issues in ERP Finance. GRINYA is the tracking via ledger account of the value of items received on a purchase order that have not been matched to a supplier invoice.

Baan solutions for Baan IV and V were incomplete. To take full advantage of the current GRINYA reconciliation process, check Infor solution #107147, which contains the GRINYA user manual and a link to download the software for your version of Baan. For ERP LN, look at Document Code U8942C US.

It is called User Guide for Reconciliation and Analysis. If you are not running the latest GRINYA solutions, patching will require a good amount of time in filling the Interim tables this solution runs from. Infor has posted several procedural write ups, so check the Support Site and read up before tackling this for the first time.
First117118119120122124125126Last

Tips:  LX | BPCS | M3

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities

New IDF Inquiries 

Infor LX has a long history of providing IDF inquiries over most critical business areas, but there are still some areas that lack this capability.
The following IDF inquiries are now available in 8.4.2:

  • Customer Quote
  • Customer Quote Line
  • RMA (Return Material Authorization)
  • RMA Line

Benefits

  • Ability to sort, subset, filter, and view information in a modern and intuitive way
  • Point and click navigation to related information – 360 views
    • Exceptional personalization and extensibility capabilities
Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for EXECUTIVES

TECHNOLOGY: Data Sharing Methods (Advantages and Disadvantages)

Depending on the multicompany scenario you choose, an implementation team must decide whether or not tables must be logically linked or if data must be synchronized in another way to achieve availability of data across various companies. 

There are 3 ways in which data may be shared among companies. Here are some advantages and disadvantages of each:

  1. Logical Table Linking - If two companies use the same physical data, the physical table exists, or is used, in only one company: the physical company. Each piece occurs only once: one instance of the same data. If the term logical table linking is used, users from multiple companies use a single physical instance of the data. If the company tables are on the same server, this can be accomplished by logical table linking. Access to specific data can be restricted, if required.

    • Advantages: Logical Table Linking takes place in real time; therefore, the moment a record is created or modified in one company, a record becomes available in all other linked companies as well. The setup and maintenance of logical table linking is easier than the setup and maintenance of data replication. Logical table linking is extremely reliable because this type of linking is independent of network connections and user interventions. 

    • Disadvantages: Table sharing implies that all attributes for a record are the same in all companies. Therefore, suppose you share the item table and, for a particular item in a company, the product class is XXX. In this case, in all other companies, the product class for this item must be XXX as well.

  2. Data Replication - In this situation, each company has exactly the same data, but each company has a unique copy of the data. The same piece of data exists in multiple (physical) places: multiple instances of the same data. The process to copy the data is called data replication.

    • Advantages: Rather than using table sharing by means of the logical linking of tables, you can replicate the content of tables between companies. The advantage is that, on company level, some (non-key) attributes of a record can differ by company. For example, if the bills of materials are replicated instead of shared, for each company, you can link a different warehouse to the bill of material. As a result, the bills of materials can be the same across all companies and only the warehouses differ. Using replication, you can also make only a subset of the records available in other companies. For example, if you replicate items between companies, in a sales company, for example, by means of the item group, you can only make end items available. In addition, you can replicate only a subset of items, for example, depending on the item group. Note that replication also requires that the referenced tables are replicated or shared.

    • Disadvantages: Replication is not in real time, and therefore, for processes that require real-time integrated data as the financial integration processes, replication is not an option. For replication, you also must take into account the sequence in which you replicate. First, you must replicate the child tables and then the parent tables, and therefore first the business partners and then the purchase contracts. During the replication process, the data must be frozen. This point is of particular importance if the replication process takes a lot of time.

  3. Manual Syncronization - If only a small number of records are the same between some companies, you can enter, maintain, and keep the records synchronized manually. Note that the more dynamic data is, the more difficult this process is. This solution is strictly procedural. Therefore, depending on the discipline of the users, the solution is error sensitive: data can be forgotten, updated too late, or typing errors may occur.

  • Advantages - The main advantage is the flexibility so that only the data that really must be shared can be kept synchronized. By manually keeping data synchronized, not all attributes of a record need to have the same value.

  • Disadvantages - The main disadvantage is that this method depends on user interaction. Therefore, the method depends on the user’s time - because the method is not a real time procedure and the user may forget to update the data - and users can make mistakes.

OPERATIONS: Creating a Purchase Order with Subcontracting

To create a purchase order (with subcontracting) third party outsourcing from purchase order, execute these steps:

  1. Create a purchase order using the same data set defined in the Subcontracting Models (tisub1100m000) session.
  2. In the Purchase Order Intake Workbench (tdpur4601m200) session, click New. The Purchase Order (tdpur4100m900) session is displayed.
  3. Select the business partner in the Business Partner field, Press Tab. Note: Infor LN populates the default data for the selected business partner in the other fields of the purchase order header.
  4. Select the order type for subcontracting in the Order Type field, purchase office in the Purchase Office field, and the related order series in the Order field.
  5. Click New on the Order Lines tab and select your subcontracted price item in the second segment of the Item field.
  6. Specify the required quantity in the Ordered Quantity field, price of the item in the Price field and click Save.
  7. Click the Approve button to approve the purchase order. The purchase order Status is updated to Approved.
  8. Verify that the material to be sent to the subcontractor is updated on the Material Supply Lines tab.
  9. Select the material line on the Material Supply Lines tab and click Actions > Generate Supply Order.
  10. Select the generated supply order line updated in the Supply Order Line field on the Material Supply Lines tab and click References > Supply Lines. The Warehousing Order (whinh2100m100) session is displayed.
  11. Select the outbound order line on the Outbound Lines tab and click References > Status Overview. The Outbound Line Status Overview (whinh2129m000) session is displayed.
  12. In the Outbound Line Status Overview (whinh2129m000) session, ensure that the Generate Outbound Advice and the Release Outbound Advice activities are automatically executed.
  13. On the specific menu, click Freeze/Confirm. The Shipment Lines (whinh4131m000) session is displayed.
  14. Select the shipment line and click Confirm. The shipment line Status is updated to Confirmed on the Status tab.
  15. Verify that the Line Status is Shipped for the outbound order line on the Outbound Lines tab in the Warehousing Order (whinh2100m100) session.

FINANCE: Cash Flow Statements (tfgld 0123m100)

Use this session to define or maintain cash flow statements and hierarchical structures of cash flow reasons for cash flow statement reports. 

On the Cash Flow Reasons by Statement tab, you can select cash flow reason groups and cash flow reasons to build a hierarchical structure of cash flow reasons for the cash flow statement report.

To link a child cash flow reason group to a parent cash flow reason group:

  1. In the Parent Cash Flow Reason Group field, select the parent cash flow reason group.
  2. In the Child Cash Flow Reason Group field, select the child cash flow reason group.
  3. Leave the Child Cash Flow Reason field empty.

To link a cash flow reason to a cash flow reason group:

  1. in the Parent Cash Flow Reason Group field, select the cash flow reason group
  2. Make the Child Cash Flow Reason Group field empty.
  3. In the Child Cash Flow Reason field, select the cash flow reason.

Note: To link cash flow reasons to a child cash flow reason group, you must select the child cash flow reason group in the Parent Cash Flow Reason Group field.

Previous Article Infor LN & Baan Tips & Tricks for EXECUTIVES
Next Article Infor LN & Baan Tips & Tricks for TECHNOLOGY: Data Sharing Methods (Advantages and Disadvantages)
Print
34923 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories