BPCS/LX Tip of the Day: Material Requirement Dates and Lead Time Offsets in MRP

Anthony Etzel 0 343 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-work days in the shop calendar.

 

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Database Sizing – Moving to LN

Kathy Barthelt 0 219 Article rating: No rating
The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

How Do You Measure Success in Your Business?

Anthony Etzel 0 52948 Article rating: 5.0

Business owners may measure success in different ways – some tangible, some intangible.

In order to establish how you should measure success for your business, you need to first examine how you measure your personal success. If you are a business owner, or a part of the management team of the company you work for, ask yourself these questions to see how you measure up:

Assess personal success.

1.    Am I happy in my job?

2.    Do I have passion for what I’m doing?

3.    Do I get the desired results based on the effort I’m putting in?

4.    Am I putting forth my best effort?

5.    Am I patient and allow for sufficient time to see results?

6.    Do I get respect from my co-workers?

7.    Do I have the endurance to hang in there when things get a bit rough?


Reflect on successes and failures.

After answering these questions, do you need to make any changes? Do you still have the same ambition and drive to achieve the goal? Are you content with your work, or have you come to the conclusion that you have not done your best?

To be successful...

Baan/LN Tip of the Week: Switching to a Difference Series

Kathy Barthelt 0 204 Article rating: No rating

In general, you can enter a different series in the order field if you have an available series.

To add a new series, find the appropriate group in the First Free Number session, and add a new series and first free number (usually 1).

In Baan IV, go to the Maintain First Free Numbers Session (under Common, Tables, Maintain Logistics Tables, Maintenance 1). Groups are easily identified (e.g., Purchase Order, Sales Order, etc.).

In Baan V, go to the First Free Number Session (under Common Data, Tables, Logistics). There are number groups (e.g., 570 may be for Purchase Orders, 650 may be for Sales Orders, etc.).

In LN, go to the First Free Number Session (tcmcs0150m000 – it is in different places in the menu under different Feature Packs). There are number groups (e.g., 210 may be for Purchase Orders, 310 may be for Sales Orders, etc.).

BPCS/LX Tip of the Day: MRP/MPS Simulation

Anthony Etzel 0 786 Article rating: No rating
The system allows you to manipulate and maintain a simulated MPS and MRP. You can copy the simulation from the existing first cut or you can create a totally new schedule. You can also perform a simulation of the rough-cut capacity plan. This allows a quick visual inspection by inquiry or menu of needed work center loads for the proposed MPS. After you choose a suitable MPS and rough-cut capacity, the system allows you to transfer the simulated MPS to the live Master Production Schedule.

BPCS/LX Tip of the Day: Inventory Stocking Levels – LX

Anthony Etzel 0 735 Article rating: No rating

The system supports four levels of inventory. You can view summaries of stock at each level through the Material Status Inquiry program or through reports.

 

Below are the four levels:

▪  Item

▪  Item + warehouse

▪  Item + warehouse + location

▪  Item + warehouse + location + lot

 

The lot number level and/or container of inventory can cross multiple warehouses and locations. For example, item + lot or item + lot + container. Locations exist within warehouses. There is no limit on the number of warehouses, locations, or lots that you can assign to an item.

Baan/LN Tip of the Day: Transfers - LN

Kathy Barthelt 0 2779 Article rating: No rating
A Transfer involves either one or two warehouses. If items are transferred between two different warehouses, all activities of the warehousing procedures must be carried out. However, if a transfer takes place between two locations within the same warehouse, the receipt activities are not carried out. You can use transfer orders to define a replenishment system within a single warehouse. This system controls replenishment from bulk locations to pick locations. Note: LN allows you to modify the outbound order line data based on the value the Allow Updating Outbound Order Lines up to and including field is set to in the Warehousing Order Types (whinh0110m000) session.

BPCS/LX Tip of the Day: LX Inventory Pallet Status Flow

Anthony Etzel 0 49963 Article rating: No rating

Four fields in the Item/Warehouse record (IIW file) affect the disposition of the

pallet status.

 

1.  Goods Receiving Code: You define these codes in Goods Receiving Maintenance (WHM130). The codes control whether or not the stock passes through inspection, what percentage, or quantity of a delivery to inspect, and the number of quarantine days, if any.

 

2.  Inspection Zone/Inspection Location: Either the Inspection Zone or the Inspection Location must be entered on the Item/Warehouse Master Maintenance screen WHM150D2-01.

 

First112113114115117119120121Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

Kathy Barthelt

Infor LN & Baan Tips & Tricks for TECHNOLOGY: Archiving Concept

Companies are developing procedures for entering data into an ERP system and for archiving manuals, drawings, specs, and other hard-copy documents. However, in many cases there is no defined procedures to store historical electronic data. Archiving electronic data should be an integral part of your business processes. 

Generally, archiving is the process of moving historical data from the operational environment to a special archive environment. At home, you might move old bank statements from a closet in your study to a box in the attic. At the office, you might store old hard copies of purchase orders in a room far from your own desk. Just because you no longer need the information in your daily work, does not mean you can dispose of the information. In terms of electronic data in your ERP system, archiving means moving historic data from the operational company to a special archive company; in that way, the historic data will be out of your way and safely stored. To free up disk space on your machine after you have archived the data, you can also move the historic data to an external medium.

Archiving strategy:
Archiving historical data is an irreversible process. After data is moved to the archive company, the data can no longer be uploaded back into the operational company. Archiving has a direct effect on the accessibility and availability of information; therefore, you must define a robust archiving strategy which addresses three major topics: What, When, and Who.

Business requirements:
Your business requirements determine what must be stored and for how long. For example, if you have a warranty situation on your projects for five years, you might be required to keep your project open during this time, or you may keep the project in an archive company. Therefore, if the project must remain open, no project-related information, including orders and integration transactions, can be archived.

Every business manager must decide how long what data must be stored in an operational environment for quick access. Reporting requirements must also be listed.

Legal requirements:
In most countries, legal requirements apply to financial data. Tax authorities may require financial data to be stored for a minimum number of years. Additionally, in specific lines of business such as food and beverages or aerospace, governments maintain specific legal requirements, which impact your archiving strategy.

User requirements:
Users rely on historical information. For example, a customer service employee may need to have shipment information of up to one year in the past to accurately address customer queries. These requirements must also be taken into account when you define what can be archived.

Data to be archived or deleted:
Various parties related to your company use information based on logistical and financial transactions occurring in the past. Before you archive or delete this information, you must investigate the need for the information.

Your ERP system contains standard archiving sessions in all major modules. These sessions are designed to copy historical data to the archive company, and then delete the data from the operational company. 

You have three options in archiving sessions:

  1. Archiving and deleting: Data is transferred to the archive company and then deleted in the operational company.

  2. Deleting: Data is deleted in the operational company, but not archived.

  3. Archiving: Data is transferred to the archive company, but not deleted in the operational company.

Using option 1 or 2 makes archiving irreversible. If you archive only because you want to preview the results, the archiving can be done a number of times.

Usually, in archiving sessions, you can also specify:

  • The date up to which the data must be archived
  • If texts must also be archived
  • If texts that already exist in the archive company must be replaced

In addition to archiving logistical and financial data, you can archive general data. 

Delete sessions:
In all major modules, your ERP system contains delete sessions. These sessions only have delete functionality, no archive functionality. Consequently, they are used to clean up data in the operational company, not to transfer data to the archive company. For more information about these delete sessions, see the "Delete sessions" sections under the various modules. For example, see Delete sessions under Procurement.

After data is deleted using delete sessions, the data is no longer available in the operational company. However, parameter settings may determine whether history data is logged when you remove specific data. If required, you can archive the history using the appropriate archiving session.

When can data be archived?
Based on the answers to the previous question, you can now set a term of retaining relevant historical data in your operational environment, and a term of keeping data available in the archive environment.

Who can archive data?
Because archiving is an irreversible process, a certain risk is involved. For example, what if one of your employees starts up an archiving session by mistake? For this reason, you must determine who is authorized to archive and delete data, and then set up these authorizations with the functionality your ERP system offers.

Because no further changes must be made to archived data, access to the archive company must also be restricted to read-only authorization for most users.

Match strategy with ERP functionality: 
After you list all your requirements, the next step is to verify whether the standard ERP functionality is sufficient to facilitate your needs. Usually, your ERP system provides the functionality to meet all of your needs, but must not force you to compromise. We recommend that you avoid customizing your software, however, because we are looking for long-term operational-data storage, customizations must not be ruled out entirely. An example is the requirement to show, in one report, the data from the operational company and archive company. In the current version, this is not standard functionality, but this can be important to manage your business. What can be even more important, if you are using customized software, is the question of whether the archiving sessions have been included. Do you take into account the fields and tables you have customized? Customized tables and fields may have to be included when performing delete/archive runs.

Archiving plan:
After you define an archiving strategy that suits your requirements, you can define the archiving plan. In this plan, you translate the strategy to a more operational level.

Contact Crossroads RMC— Let's take the next step together to execute your archiving plan.

800.762.2077

Previous Article Infor LN & Baan Tips & Tricks for OPERATIONS: Blocking or Unblocking Warehouses
Next Article Infor LN & Baan Tips & Tricks for FINANCE: Remap Posted Integration Transactions (tfgld4282m100)
Print
43489 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories