Please Wait a Moment
X

Infor LX Tips, Infor LN Tips, BPCS Tips, Baan Tips, Infor M3 Tips & Infor ERP News

Crossroads Connections

Infor ERP Tips & News from the Experts

Infor LX | Infor LN | BPCS | Baan | Infor M3

BPCS/LX Tip of the Week: Receiving to Inspection

Anthony Etzel 0 66468 Article rating: No rating

If the item being received needs to be inspected prior to being available for use, there are two schools of thought.

The first is to receive the item to a QC hold location. The downside is the item will show up in on hand inventory.

A better method would be to do a PO receipt to inspection. Both Inv500 and Pur550 support this method. Now you have received the item without showing it in inventory. Only the PO quantity in inspection is updated. This method also allows you to create an Inspection Dispatch Report. After the QC process for the item is complete, then the transaction Receipt from Inspection to Stock is processed. That transaction then updates the PO quantity received field and the Item on hand field in inventory.

Baan/LN Tip of the Week: Purchase Inquiry

Kathy Barthelt 0 84967 Article rating: No rating

In Baan IV Purchase Control, the purchase inquiry procedure enables the user to:

  • Request a specific supplier to submit a quotation on the purchase inquiry for the delivery of an item.
  • Compare the prices and discounts of the quotations that are submitted by different suppliers.
  • Copy the inquiry data to a purchase order.


In LN, you can:

  • Request multiple business partners to submit a quotation on a specific request-for-quotation for the delivery of an item.
  • Compare the received quotations based on the following criteria:
  1. Price
  2. Quantity
  3. Vendor rating
  4. Delivery dates
  5. RFQ subjective criteria
  • Copy the quotation data to a purchase order, a purchase contract, or a price book.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 58627 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 60505 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

Filtec Selects Crossroads RMC for Baan Data Collection

Kathy Barthelt 0 28926 Article rating: No rating

Filtec, a leading provider of in-line inspection solutions for the food, beverage, and pharmaceutical industries, has selected the Web Collect, formerly RMC3 data collection solution from Crossroads RMC for their Baan IV system. Filtec plans to implement Labor Reporting and Report Operations Complete as part of this project with the goal of eliminating manual data entry and gaining better visibility to gap time. The project is scheduled to go live in early November 2015.

BPCS/LX TIP OF THE DAY: MATERIAL REQUIREMENT DATES AND LEAD TIME OFFSETS IN MRP

Anthony Etzel 0 63729 Article rating: No rating

The system automatically performs offsets for requirements dates for components in the MPS/MRP calculations. It also performs offsets for calculation of material need dates at the time that shop orders are released.

To calculate the offset, the system takes the parent lead time from the Item Master and adjusts it by the bill of materials offset (plus or minus) for the component. This gives the lead time days for that specific component. The system starts with the due date of the parent and backs up and skips all non-workdays in the shop calendar.

Note that the offset calculation uses only calendar records that have a blank work center (the calendar record applies to all work centers). See the information for the Shop Calendar Maintenance program, SFC140, in your Shop Floor Control documentation for shop calendar details.

Baan/LN Tip of the Week: Data Sizing Moving to LN

Kathy Barthelt 0 57828 Article rating: No rating

The Infor LN database must be created with the appropriate size. For example, if at least 150 GB is required for a year, create the database with the required size from the beginning. Do not let the size increase to the required size and cause additional fragmentation in the database and the NTFS volume.  Set the autogrowth to a minimum of 10 percent or 1 GB (for each extent) to avoid fragmentation on file system level. Never use the default extent size of 1 MB.

BPCS/LX Tip of the Week: Work Center & Machine Locations

Anthony Etzel 0 61260 Article rating: 3.0

For either file, you must specify a valid location code as defined in the Location Master File.

If the machine master locations are blank, then the work center locations are used. There are cases where you may want to do a combination between the two in defining the locations.

Let’s say the end item has one operation. The operation is at work center 510 and Machine A is in the work center. You have locations setup in both the Work center file and the Machine master File. You report 100 complete at the work center without specifying the machine.

In this case, the inventory will be processed based on the locations defined in the work center file. If the transaction included the machine number, then the locations in the machine file would be used.

First111112113114116118119120Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

An ERP System Review is NOT a Report Card

It's a no-judgment-review - we promise!

report card C minusWe all remember our school days and the nervousness that we felt when it came time to get our grades. Even if we were doing well, we were still nervous. Sometimes we experienced that same nervousness when it came time for a performance review on our job. Nervousness…sometimes dread…knowing that our performance was not what we wanted it to be, or others expected it to be. 

Somehow I think the feelings that we felt in our past often find ways to creep into our present. I have seen this recently when I suggested an ERP system review to one of our customers. They immediately became flustered and thought about every possible problem that they knew existed within the software and how they were currently using it. I asked them to consider the purpose of the ERP system review.

An ERP Utilization Review will:

  • Document how your company is using your ERP system (or a particular aspect of the system) and to what extent the system meets the needs of the business.
  • Identify challenges encountered using the software.
  • Create opportunities for improving business processes and generating additional value.
  • Identify potential risks and areas that need improvement.


key hole to the futureSo, if the result of ERP system review is to establish a path forward for growth based on current status, then why doesn’t every company take advantage of it? I think for some, the answer lies in the feelings of nervousness and dread still stuck in the recesses of our brains.

An ERP system review or more specifically a utilization review is NOT a personal report card, or performance review showing how well a particular individual does his/hers/their job, nor is it an attack on the team that implemented the software. 

As they say, hindsight is 20/20. What we view now to be a less than ideal implementation methodology may have been absolutely appropriate at the time the software was originally deployed. The software has likely matured and the skillsets of the individuals responsible for the system have likely matured as well. In some cases, those resources are no longer with the company, leaving those that remain with no back story as to how and why implementation decisions were made.

Instead of viewing the ERP utilization review as a reason to find fault in previous decisions, think of it as discovering untapped potential – both of the ERP system and the people who use it. Viewing an ERP utilization review in this way puts a positive spin on it and allows us to challenge ourselves to identify opportunities for growth far greater than anything we imagined before. This means not only moving our businesses forward faster but also advancing the strength of the company as individuals and as a team.

What untapped potential lies within your company?

Consider a utilization review of your entire ERP system, or just a part of it like Finance, Technology, Materials Management, Order Processing, or Shop Floor Control. You just might be surprised at what greatness can be achieved… far greater than anyone could have imagined.  

Get a free phone consultation button

800.762.2077

Print
28961 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories