BPCS/LX Tip of the Week: Inventory Control

Anthony Etzel 0 58107 Article rating: 1.0

Is Lot Control necessary?

Certain industries require lot control, where others may find it an option based on how they want to trace the material used in a product in the event of a defect, or recall.

LX provides tight lot controls and flexibility with lot number assignments. Shop orders can have a pre-assigned lot number, or a lot number can be automatically assigned when the item is produced. You can also assign a specific lot number for the entire shop order, or for each item/quantity reported against a shop order.

BPCS/LX Tip of the Week: Alternate Items

Anthony Etzel 0 56404 Article rating: No rating
How can I use an alternate item on a shop order?

The best way is to have the approved alternate item appear on the Bill of Material just after the standard item with a zero required quantity. Now the alternate item will appear on the Shop Order. So, if the standard item is not available, the alternate item can be issued to the shop order.

When the shop order is closed out, one item will have an unfavorable variance while the other shows a favorable variance. This is an easy way to provide alternate items provided engineering approves and they are part of the Bill of Material.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 54404 Article rating: No rating

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: User Defined Transactions

Anthony Etzel 0 59571 Article rating: No rating

When to use a user defined inventory transaction

ERP LX (BPCS) provides you with the flexibility to create inventory transactions without program modifications. The typical transaction types are defined with effects set on how the transaction will impact inventory balances.

Perhaps you want to process a customer return and don’t want to the inventory to be impacted. You can create a user define transaction effect to allow the customer receipt and not update the inventory balance.

Baan/LN Tip of the Week: Old Porting Set

Kathy Barthelt 0 51522 Article rating: No rating

Here are some issues that you might run into if you stay on an old porting set too long:

  • Incompatibility because of operating system patches
  • Printing issues because of out-of-date libraries
  • Potential performance issues if binaries are not updated
  • Updating third-party products may not be possible because of dependencies
  • Limited support from Infor
  • Issues with updating database software/patches because of dependencies (if the database is also running on the same server as the application)

Need help getting on a newer porting set? Let us know! We’d be happy to help.

Crossroads MES Released for Windows 10

Anthony Etzel 0 27046 Article rating: No rating

Crossroads RMC is pleased to announce the availability of Crossroads MES, V11 for Windows 10. Any customers wishing to upgrade from a previous version to V11 can do so by contacting  support@crossroadsrmc.com. As previously announced, Crossroads MES  is also compatible with tablet PCs running Windows 8.1. Tablet PCs are becoming the clipboard replacement for supervisors and managers to monitor what’s happening on the shop floor.

BPCS/LX Tip of the Week: Shop Order Release Date

Anthony Etzel 0 62659 Article rating: No rating

The shop order release date is the date that the shop order is scheduled to be released for production.

If you want to use the backward schedule method, make sure the release date is blank and the due date is maintained.

If you maintain the quantity on the shop order and the due date is prior to the system date, the due date and the release date are the same.

Baan/LN Tip of the Week: Plan Codes

Kathy Barthelt 0 58950 Article rating: No rating

In Baan IV, plan items exist within the context of a plan code. A plan code includes only items of the MPS Item item type. Planned orders are independent of a plan code. Users can compare plan codes by means of the Plan Code Performance Comparison (cprmp4504m000) session.

The scenario concept in Infor LN replaces the plan code concept in Baan IV.

In Infor LN, the basic data for plan items is the same for all scenarios. However, users maintain not only the master plan within a scenario, but the planned orders as well.

For example, for each scenario, Users can specify:

  • Special demand for an item.
  • The availability of resources (in the Scenario – Availabilities (cprpd4160m000) session).
  • The sourcing strategies and supply strategies.

Users can compare scenarios by means of the Performance Indicators (cprao2201s000) session.

First110111112113115117118119Last

Tips:  LX | BPCS | M3

Tips: LN | Baan

An ERP System Review is NOT a Report Card

It's a no-judgment-review - we promise!

report card C minusWe all remember our school days and the nervousness that we felt when it came time to get our grades. Even if we were doing well, we were still nervous. Sometimes we experienced that same nervousness when it came time for a performance review on our job. Nervousness…sometimes dread…knowing that our performance was not what we wanted it to be, or others expected it to be. 

Somehow I think the feelings that we felt in our past often find ways to creep into our present. I have seen this recently when I suggested an ERP system review to one of our customers. They immediately became flustered and thought about every possible problem that they knew existed within the software and how they were currently using it. I asked them to consider the purpose of the ERP system review.

An ERP Utilization Review will:

  • Document how your company is using your ERP system (or a particular aspect of the system) and to what extent the system meets the needs of the business.
  • Identify challenges encountered using the software.
  • Create opportunities for improving business processes and generating additional value.
  • Identify potential risks and areas that need improvement.


key hole to the futureSo, if the result of ERP system review is to establish a path forward for growth based on current status, then why doesn’t every company take advantage of it? I think for some, the answer lies in the feelings of nervousness and dread still stuck in the recesses of our brains.

An ERP system review or more specifically a utilization review is NOT a personal report card, or performance review showing how well a particular individual does his/hers/their job, nor is it an attack on the team that implemented the software. 

As they say, hindsight is 20/20. What we view now to be a less than ideal implementation methodology may have been absolutely appropriate at the time the software was originally deployed. The software has likely matured and the skillsets of the individuals responsible for the system have likely matured as well. In some cases, those resources are no longer with the company, leaving those that remain with no back story as to how and why implementation decisions were made.

Instead of viewing the ERP utilization review as a reason to find fault in previous decisions, think of it as discovering untapped potential – both of the ERP system and the people who use it. Viewing an ERP utilization review in this way puts a positive spin on it and allows us to challenge ourselves to identify opportunities for growth far greater than anything we imagined before. This means not only moving our businesses forward faster but also advancing the strength of the company as individuals and as a team.

What untapped potential lies within your company?

Consider a utilization review of your entire ERP system, or just a part of it like Finance, Technology, Materials Management, Order Processing, or Shop Floor Control. You just might be surprised at what greatness can be achieved… far greater than anyone could have imagined.  

Get a free phone consultation button

800.762.2077

Print
28959 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories