Baan/LN Tip of the Week: Default Order Frequency

Kathy Barthelt 0 1943 Article rating: No rating

In Baan IV, requirements for an MPS item with the order method lot-for-lot result in daily planned MPS orders.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, an MPS planning run generates one planned MPS order of 200 pieces for each working day in the plan period.

In Infor LN, requirements for a planned item with the order method lot-for-lot result in one planned order per plan period.

For example, if a plan period contains 10 working days and the net requirements for an item in that period is 2000 pieces, a master planning run will generate a single planned order of 2000 pieces for the first working day in that plan period. To influence the order quantity of the planned orders, enter appropriate values in the Maximum Order Quantity field and the Order Interval field in the Items – Ordering (tcibd2500m000) session or choose a fixed order quantity.

BPCS/LX Tip of the Day: Cost Accounting – LX

Anthony Etzel 0 868 Article rating: No rating

The challenge in cost accounting is tracking your manufacturing to the levels needed for useful management information. You need feedback for corrective action; but, you need to minimize the cost of collection. Some parts of your operation require specific job-cost tracking while the Just-in-Time areas require

costing in terms of cost per process hour or day. Apply overhead in different ways to different processes and products. Segregate costs into enough detail

to provide management with an accurate picture of the contents of your product. Material, material overhead, labor, fixed overhead, variable overhead, outside processing, outside processing overhead, and so forth all have to be considered.

 

LX meets your cost accounting needs with the following functionality:

▪ Four sets of costs: actual, standard, frozen standard, and simulated

▪ Nine user-defined elements per set

▪ Full and partial cost roll-up and simulation

▪ Cumulative in-process cost tracking

▪ Cost summaries by item

▪ Cost definition tied to work centers or material type

▪ Process hour costing

Baan/LN Tip of the Day: Vendor Rating

Kathy Barthelt 0 1416 Article rating: No rating

In LN, a supplier's reliability is no longer based only on correct deliveries. The vendor rating functionality of LN is based on various objective criteria and subjective criteria that can be used to calculate the vendor’s rating.

 

The set up procedure for analyzing suppliers has changed completely compared to Baan IV.  To execute the vendor rating process, users must update the vendor ratings in the Update Vendor Rating (tdpur8850m000) session.

If users update the vendor ratings, the following stages exist in the update vendor rating procedure:


1. Calculate actual weightings

2. Calculate ratings for objective criteria

3. Calculate ratings for subjective criteria

4. Update overall vendor rating

Baan/LN Tip of the Day: Release Commissions/Rebates to Invoicing

Kathy Barthelt 0 3103 Article rating: No rating

In Baan IV, this session is called Release Commissions/Rebates to Invoicing (tdcms2201m000) and is used to set the status of the commissions/rebates to Reserved, or Closed. In Infor LN, this session is only used to set the status to  Closed. Users can reserve commissions/rebates in the Reservation and Approval of Reserved Commissions/Rebates (tdcms2202m000) session. In addition, the following fields are added to the Release Commissions/Rebates to Invoicing (tdcms2201m000) session:

▪ Commissions to Accounts Payable

▪ Rebates to Central Invoicing

BPCS/LX Tip of the Day: How Does LX Fit in With Just-In-Time?

Anthony Etzel 0 364 Article rating: No rating

For years, repetitive manufacturing industries have been applying many of the principles in Just-in-Time philosophy. They have established balanced production lines that depend on a steady flow of material to each work station. They schedule production in daily or weekly rates rather than in discrete shop order lots. They track finished inventory by work center rather than by job. They typically backflush stock balances (decrement stock balances upon completion of specific manufacturing steps rather than issued at the beginning of each production run).

 

Costing is typically based upon a daily rate or hourly rate rather than being associated with specific shop orders. 

 

Repetitive manufacturers use MRP II software adaptable to their environments

in the following key areas:


 Product definition

 Inventory tracking

 MRP/Master Scheduling

 Shop Floor Control

 Purchasing

 Costing

BPCS/LX Tip of the Day: What is Just-In-Time?

Anthony Etzel 0 313 Article rating: No rating

Just-in-Time (JIT) is a management philosophy that focuses on minimizing the resources necessary to add value to your products and to operate your factory in ways that eliminate waste. Resources are labor, materials, equipment, space, and time. Waste is anything that does not add value to your products. Moving work-in-process from place to place, stacking and sorting, investing capital in large work-in-process and raw material inventories, inspecting materials at your vendors' sites, and tying up warehouse space with finished goods are all activities that add cost, not value, to your products. 

JIT is a process that reduces lead time. JIT does not replace an MRP, an inventory program, a scheduling technique to bypass your Master Schedule, or a materials management project. JIT is the never-ending commitment of everyone, from top management to your workers on the floor, to maximize your effectiveness through continuous, incremental improvements.

Baan/LN Tip of the Day: Configuring Items

Kathy Barthelt 0 2237 Article rating: No rating

In LN, the configuration of a generic item not always results into a customized item. Configured items can now be customized items as well as standard items. If users configure items without PCS projects, standard items are generated instead of customized items.

 

The sessions for generating product variant structures for sales quotations and sales orders are moved from the Product Configuration module in Manufacturing to the Sales Control module in LN. The following new sessions are available in Sales Control:

▪ Generate (Budget) Structure for Sales Quotations (tdsls1201m100).

▪ Generate (Project) Structure for Sales Orders (tdsls4244m000)

BPCS/LX Tip of the Day: Shop Order Control

Anthony Etzel 0 443 Article rating: No rating

To create and maintain shop orders use SFC500 Shop Order Entry Maintenance. These orders use the standard bill of material (BOM) as the base list of components. You can also set up standard routings, which list the operations,

or work steps, involved in manufacturing.

 

To release shop orders, use the Shop Order Release program, SFC505. Infor ERP LX groups shop orders by user ID for batch processing. Use Shop Packet Print, SFC520, to print the shop orders that you select. SFC530 allows you to create multi-level shop orders to link shop orders together with a common end item parent. Linking multiple shop orders together for a final assembly product provides support for make-to-order and engineer-to-order manufacturing environments which need to schedule these multiple orders together or as a vertical slice in the production schedule.

 

You can make changes to shop orders after you print them. Use Shop Order Entry/Maintenance, SFC500, to update the shop orders. Changes are immediately visible on the inquiry screens for SFC300 and SFC350. To reprint the shop packet, use Reprint Shop Packet, SFC560.

First110111112113115117118119Last

Tips:  LX | BPCS | M3

Improves control over PO costing changes during invoice entry by replacing passive warnings with an intentional override action.

  • In ACP500D3 (Invoice Entry PO Costing), users previously could unintentionally accept changes by pressing ENTER, even when quantity to cost or amount to cost values had changed.

  • A new “F14 to Override” warning message replaces the old message:
    “Details have changed. Press enter again to accept data.”
    This ensures users acknowledge and confirm significant changes explicitly.

New System Parameter:

  • “Apply GRN Costing Tolerance for PO Costing” (optional):

    • Within tolerance: Displays the original message —
      “Details have changed. Press enter again to accept data.”

    • Outside tolerance: Triggers the new override requirement —
      “F14 to Override”

Benefits:

  • Enhances oversight and reduces unintentional cost acceptance.

  • Enables better control of PO costs when invoice details differ from expectations.

Last

Tips: LN | Baan

An ERP System Review is NOT a Report Card

It's a no-judgment-review - we promise!

report card C minusWe all remember our school days and the nervousness that we felt when it came time to get our grades. Even if we were doing well, we were still nervous. Sometimes we experienced that same nervousness when it came time for a performance review on our job. Nervousness…sometimes dread…knowing that our performance was not what we wanted it to be, or others expected it to be. 

Somehow I think the feelings that we felt in our past often find ways to creep into our present. I have seen this recently when I suggested an ERP system review to one of our customers. They immediately became flustered and thought about every possible problem that they knew existed within the software and how they were currently using it. I asked them to consider the purpose of the ERP system review.

An ERP Utilization Review will:

  • Document how your company is using your ERP system (or a particular aspect of the system) and to what extent the system meets the needs of the business.
  • Identify challenges encountered using the software.
  • Create opportunities for improving business processes and generating additional value.
  • Identify potential risks and areas that need improvement.


key hole to the futureSo, if the result of ERP system review is to establish a path forward for growth based on current status, then why doesn’t every company take advantage of it? I think for some, the answer lies in the feelings of nervousness and dread still stuck in the recesses of our brains.

An ERP system review or more specifically a utilization review is NOT a personal report card, or performance review showing how well a particular individual does his/hers/their job, nor is it an attack on the team that implemented the software. 

As they say, hindsight is 20/20. What we view now to be a less than ideal implementation methodology may have been absolutely appropriate at the time the software was originally deployed. The software has likely matured and the skillsets of the individuals responsible for the system have likely matured as well. In some cases, those resources are no longer with the company, leaving those that remain with no back story as to how and why implementation decisions were made.

Instead of viewing the ERP utilization review as a reason to find fault in previous decisions, think of it as discovering untapped potential – both of the ERP system and the people who use it. Viewing an ERP utilization review in this way puts a positive spin on it and allows us to challenge ourselves to identify opportunities for growth far greater than anything we imagined before. This means not only moving our businesses forward faster but also advancing the strength of the company as individuals and as a team.

What untapped potential lies within your company?

Consider a utilization review of your entire ERP system, or just a part of it like Finance, Technology, Materials Management, Order Processing, or Shop Floor Control. You just might be surprised at what greatness can be achieved… far greater than anyone could have imagined.  

Get a free phone consultation button

800.762.2077

Print
28419 Rate this article:
5.0
Kathy Barthelt

Kathy BartheltKathy Barthelt

Other posts by Kathy Barthelt

Contact author

x

Categories