BPCS/LX Tip of the Week: Changing the Master Schedule

Anthony Etzel 0 760 Article rating: No rating

You can change your master schedule by specifying the type of master schedule update to perform. You can run a Net Change or Regenerative Schedule.

You also have the ability to clear the lower level requirements out of the Planned and Firm-Planned Order file.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 1086 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 1064 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer

With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1101 Article rating: No rating

If Location Control is turned on in Baan IV, then inventory should never be negative.

If Location Control is not turned on in Baan IV, and the parameter “Negative Inventory Allowed” in INV Parameters is set to “NO”, then inventory should never be negative.

In Baan V and LN, the parameters in Inventory Handling Parameters determine whether you can have negative inventory. If these parameters are set to “NO”, then inventory should never be negative.

BPCS/LX Tip of the Week: Why define location fields in the work center file?

Anthony Etzel 0 568 Article rating: No rating

If you setup the “From” and “To” Location fields in the Work Center file, this will then determine the locations for material issue transactions and production reporting transactions.

The reporting of the transactions would happen through production reporting, JIT600, or using the Shop Floor labor posting, SFC600, or Shop Floor Posting from SFC650.

Remember, any location used in the work center file must first be set up in the location master file. Using an MES solution by-passes the need to key any of the data to ERP LX.

Baan/LN Tip of the Week: Negative Inventory

Kathy Barthelt 0 1143 Article rating: No rating

What should you do if you have negative inventory reflected in your system?

You should do a cycle count or inventory adjustment, but first, do a review of the inventory or location history to determine when this happened.

If a negative inventory is allowed, it most likely will be corrected upon receipt of the item. For example, assume that there is a PO that has not been received in Baan/LN, but the goods came in and got shipped out on a sales order. The inventory goes negative, but when the PO receipt is entered, the inventory would be corrected. In this case, no adjustment should be made.

A little due diligence will go a long way to ensure that you are only making an adjustment to your system when warranted.

BPCS/LX Tip of the Week: What is Lean Make to Order?

Anthony Etzel 0 261 Article rating: No rating

This is a simple way to go from the customer order to making the order and shipping the order. It involves a few simple steps:

  1. Receive and enter the customer order
  2. Automatic credit review
  3. Automatic release of the shop order tied to the customer order
  4. Issue material, report labor to the production order receipt
  5. Pick the order, ship the order, invoice the customer


With lean, you can skip processing the demand through MRP. You can go directly from the customer order to the shop order creation.

Baan/LN Tip of the Week: Optionally Include Tax Amounts In Order Balance

Kathy Barthelt 0 133 Article rating: No rating

In Baan IV, the order balance amount always includes the tax amount. Consequently, the tax amount must be recalculated every time an order line is modified in order to update the balance correctly. If the tax provider is activated, this requires an API call for every re-calculation of tax.

In Infor LN, users can select or clear the new Include Tax in Order Balance check box in the COM Parameters (tccom0000s000) session to indicate whether users want to include tax amounts in the order balance amount. This parameter has an effect on various sessions in Order Management.

First110111112113115117118119Last

Tips:  LX | BPCS | M3

Anthony Etzel
/ Categories: Infor LX & BPCS Tips

Infor LX / BPCS Tip of the Week: Pre-assigned lot numbers for multi-level SO release

In addition to assigning lot numbers in Shop Order Entry/Maintenance (SFC500) after the shop orders have been released, users can now pre-assign lot numbers during the Multi-level Shop Order Release process (SFC530) and the Multi-Level Back-flush process (LMP600) for sub-assemblies that are lot controlled items. The user has the choice of using the parent lot ID, using the next sequential generated lot ID, or not pre-assigning lot IDs. Multiple items per lot must be installed to use the parent lot number option.
Previous Article Infor LX & BPCS Tip of the Week: ION Tip – Pausing Receiving and Sending of Messages
Next Article Infor LX & BPCS Tip of the Week: 6 Powerful Steps to Win with Automation
Print
56865 Rate this article:
5.0

Contact

Anthony Etzel

Anthony EtzelAnthony Etzel

Other posts by Anthony Etzel

Contact author

x

Tips: LN | Baan

You can move monthly periods to a different parent period. For example, if you have a monthly calendar, you can create quarter periods and move months to the quarters.

  1. Select Financials > Global Ledger > Setup > Finance Enterprise Group > Maintenance.
  2. Open the finance enterprise group.
  3. Click the Calendar tab.
  4. Open the calendar for which you want to move periods.
  5. Click the Hierarchy tab.
  6. Select the periods to move.
  7. Select Actions > Move.
  8. Select the new parent period under which you want to move the periods.
  9. Click OK.

Categories